Home / Financial Firm (Unknown - Insurer) / Determination 539671

Determination 539671

Declined building damage claim under ground movement exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2019-05-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$41,000
SourceAFCA PDF

Summary

Complainant's building claim of about $41,000 for damage linked to a leaking storm water pipe was declined under the ground movement exclusion. AFCA found the damage most likely caused by localised subsidence and seasonal movement, so the insurer need not pay.

The policy excludes earth movement, and the complainant did not establish on the balance of probabilities that the leaking pipe caused the damage.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 539671 Page 1 of 6 Determination Case number: 539671 24 May 2019 1 Determination overview 1.1 Complaint The complainant held a home, building and contents policy with the financial firm (insurer) and lodged a claim on 21 May 2018 for damage sustained because of a leaking storm water pipe. The insurer declined the claim and maintains that the damage is most likely due to ground movement which is excluded from cover under the terms of the policy. This matter has been subject of a recommendation. The recommendation was in favour of the insurer. The complainant has rejected the recommendation. 1.2 Issues and key findings Is the insurer liable for the claimed damage? Given the available information, I am satisfied that most likely the damage was caused by ground movement over time rather than because of leaking storm water pipes. Although there is no dispute that leaking pipes had been identified the available information does not link the movement to the leaking pipes. The insurer is entitled to rely on the exclusions in the policy to refuse payment of the claim. 1.3 Determination This determination is in favour of the financial firm. The insurer is entitled to rely upon the terms and conditions of the policy and to refuse payment of the claim. Determination | Case number: 539671 Page 2 of 6 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues from the information exchanged This determination follows consideration of all the information provided including information provided by the complainant following the recommendation. The determination is based on what is fair in all the circumstances having regard to the relevant legal principles, terms of the policy, good industry practice; including codes of practice and prior determinations where applicable. 2.1 Is the insurer liable for the claimed damage? Onus on complainant to establish claim within the terms of the policy The complainant’s policy is a listed events policy that provides cover for a series of listed events including storm or the escape of liquid. The onus is therefore on the complainant to establish on the balance of probabilities that the damage to the property was caused by an event listed under the terms of the policy. Circumstances of the loss The property was built approximately in 1993 and according to the complainant, there was no history of water leaks or other damage to the property. In December 2017, the complainant says he started to notice cracking . In May 2018 he appointed a reblocker MU to determine to cause of the cracking. MU recommended underpinning the property to ensure structural integrity on the advice of its building engineer. He did not comment on whether the damage was caused by a leaking pipe. The underpinning commenced on 21 May 2018 and during the works, water was found to be entering the excavated areas. GDI a plumber confirmed that he attended the property and identified a two -metre rectangular cast iron drain which had collapsed. This drain has now been replaced. Plumber LT confirmed on 29 January 2019, he identified a blocked storm water drain on the north side of the house. I accept based on these reports that there were issues with the storm water drainage and leakage from the storm water pipes at the property. I am not satisfied, however, that the reports from MU or the plumbers establish that there was movement to the complainant’s property caused by the leaking pipes. Determination | Case number: 539671 Page 3 of 6 Engineering report indicates damage caused by ground movement Although the complainant’s experts have confirmed a leaking pipe, the insurer’s experts suggest the damage was due to ground movement caused by the reactive nature of the soil. The insurer’s assessor AI while identifying cracking damages in multiple locations, was unable to accurately determine the cause of the damage as the complainant had already commenced the underpinning work prior to the assessor attending the property. AI’s report is of limited value in determining the cause of damage. According to AI, as the repair process was underway, and the repair method had been advised by an engineer not appointed by AI a claim decision could not be made. There is no indication that AI attempted to speak with the engineer. AI believed it did not have a reasonable opportunity to properly investigate the cause. The insurer subsequently appointed IL, an engineer to report on the damage. IL attended the complainant’s property on 19 June 2018 and at the time of inspection , all underpinning works had been completed. IL inspected both the internal and external damage. Part of its assessment involved assessing the hydrostatic floor measurements which it noted indicated that the slab had a uniform fall across the north/south direction. IL considered from the photographs provided that the cracking and movement of the property was very slight to slight. In this case IL considers the underpinning of the dwelling uneconomical, unnecessary and unjustified. As for the cause of the damage IL considered there was inadequate evidence to indicate that a leaking storm water drain was the primary cause for all the recorded damage. IL considered the localised subsidence was more likely directly attributed to the presence of uncapped perimeter soils and natural seasonal movement of the highly reactive clay bearing strata. Whilst I accept the complainant had discovered blocked and damaged storm drains, the available information does not link that to the movement of the property. I am persuaded by the engineering report from IL that most likely the damage was caused by a localised subsidence and natural seasonal movement. I am satisfied the proximate cause of damage resulted from ground movement over time which is excluded from cover under the terms of the policy. The insurer is entitled to decline the claim under the terms of the policy and is not liable for the cost of repairing the damage. Determination | Case number: 539671 Page 4 of 6 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with Financial Ombudsman Service (FOS). This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint claim claim 3.2 Reports Report Key points insurer’s expert (A I ) Report 21 May 2018  The underpinning company nor the engineer did any discovery work in trying to find out what was the cause of the movement and it was only until the underpins were being dug out that they found water in the soils around the home.  As the repair process is currently under way and the repair method has been advised by an engineer that has not been appointed by A I we will not be able to proceed with any works at the property due to there not being a drying out period allowed. This is a general practice by engi neers to allow the soils to dry out back to their normal conditions. insurer’s expert (IL) Report 28 June 2018  There is inadequate evidence to indicat e that a leaking stormwat er drain is the primary cause for all recorded damage. Instead, localised subsidence along the south and east elevations of the dwelling can be directly attributed to the presence of uncapped perimet er soils and natural seasonal movement of the highly reactive clay bearing strata.  Cracking and movement at the dwelling pre - underp inning would be classified predominantly as Category 2, (slight), with a single case of a Cat egory 3 (moderate) crack  The overwhelming majority of cracks would be classified as Category 1 to 2, very slight to slight and such cracks would be Determination | Case number: 539671 Page 5 of 6 Report Key points considered norm al on all reactive sites across Victoria and generally do not require underpinning works to be carried out to rectify the distress. complainant’s expert (MU) Report 2 October 2018  During the inspection we conducted at the stated address it was deemed that the underpinning work had to be organised to ensure the continued structural integrity of the house. This work was performed according to the plans laid out by the engineer. Evidence of this will be attached in the form of photographs detailing the damage that the property had prior to the underpinning. complainant’s expert (GDI ) Report 1 October 2018  Attended property, found storm water blocked. Ran high pressure drain machine through storm water and partially cleared blockage. After further investigation found collapsed drain at the front of the property, there was a section of approximately 2m of rectangle cast iron drain which was collapsed. Re attended property dig up cast iron drain and replaced with New PVC drain. Drain is now flowing. complainant’s expert (L) Report 22 February 2019  29/1/19 To investigate storm water drain on north side of house with drain camera to find blockage in pipe. To clear blockage in storm water pipe with water jet. To re inspect storm wat er drain with drain ca mera to find dips in drain holding wat er causing blockages. Drain is flowing at moment. Water seepage may have occurred due to blockage in stormwater pipes on north side of house. 3.3 Relevant policy wording Record Key points Cover for insured events page 22 We cover: Loss or damage to the building caused by liquid leaking, overflowing or bursting from any of the following :  any drain, fixed pipes, roof gutters or guttering and rainwater downpipes, drainage and sewage systems; General exclusions page 37 What we do not cover - You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Ground movement erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the Determination | Case number: 539671 Page 6 of 6 Record Key points following insured events: Storm;  Flood (but only if you have co ver for insured event ‘Flood’);  Earthquake and Tsunami;  Explosion. Recommendation | Case number: 539671 Page 1 of 6 Recommendation Case number: 539671 24 January 2019 4 Overview 4.1 Complaint The complainant holds a building insurance policy with the financial firm (the insurer) and lodged a claim on 21 May 2018 for structural damage to his property after he discovered a leaking stormwater pipe during underpinning repair works. The insurer, relying on the reports from its experts, stated that the damage arose from an uninsured event under the policy. The insurer says that the damage was caused by naturally occurring earth movement, which is excluded from cover under the policy. The complainant disputes the insurer’s decision and seeks to cover the cost of repairing the damage to his property amounting to $41,000, which he has already incurred. 4.2 Issues and key findings Is the insurer entitled to decline the claim? The available information does not establish that the damage to the complainant’s property was caused by the escape of a liquid from a leaking pipe. Rather, the material suggests the damage cause was from an exclusion in the policy and as such, the insurer is not liable for the claim. 4.3 Recommendation This recommendation is in favour of the insurer. The insurer is entitled to deny the complainant’s claim. Recommendation | Case number: 539671 Page 2 of 6 5 Reasons for recommendation 5.1 Is the insurer entitled to decline the claim? Policy provides cover for insured events subject to exclusions The complainant is required to show that, on the balance of probabilities, he has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the complainant is able to establish a prima facie claim, then the onus shifts to the insurer to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The complainant’s policy provides cover for damage caused by insured even ts listed in the policy (including escape of liquid) subject to conditions and exclusions set out in the policy. Complaint says that damage was caused by the leaking pipe The complainant engaged MU to complete repair works to the property’s foundation after discovering structural cracking in the walls of his home. The complainant says that MU discovered a leaking stormwater pipe around the footings of the dwelling that was causing water seepage into the foundation. This was caused by a damaged stormwater pipe in the front of the property and the complainant arranged for the repair of it, at his own cost. The complainant states that the storm water pipe was accidentally damaged by a postman. The complainant has provided an invoice and a report from his plumber (GDI) who confirms that they attended the property to repair a section of a two-meter cast iron drain located in front of the property, that had collapsed. GDI states that as a result of the collapse, the storm water pipe had been partially blocked. Based on this, the complainant submits that escaped water caused ground movement and damage to his property. The complainant has submitted photographs and a video that show dampness in the excavation sites during the underpinning repairs. Insurer says damage to the property was caused by non-insured events The reports prepared by the insurer’s experts who inspected the complainant’s property suggest that there was cracking damage to the property caused by ground movement. The insurer appointed A1 to inspect the damage and provide a report to confirm the cause of the damage. While A1 acknowledges that the property presented some cracking damage in several locations, they state that they were unable to properly assess the cause of the damage as the complainant ’s underpinning contractor (MU) had completed the repairs. Recommendation | Case number: 539671 Page 3 of 6 The insurer appointed an engineer, IL to further investigate if the cause of the movement could be attributed to the defective storm water drain. Based on IL’s visual inspection and the information obtained, IL determined that there was inadequate evidence to indicate that a leaking stormwater drain was the cause of the damage. IL submits that they discovered localised subsidence along the south and east elevations of the dwelling. They directly attributed the subsidence due to the presence of uncapped perimeter soils and natural seasonal movement of highly reactive clay soil of the property. IL provided photographs of the to support their findings but did not provide any soil test reports. IL also provided a floor level survey depicting the variations in the floor levels, suggesting that the most variation had occurred close to uncapped perimeter soil. IL says that given that the dwelling had already been underpinned, IL was unable to confirm if the property’s defective floor levels had been caused by the water leak or the underpinning works that had been completed. IL also says that photographs of the excavations also do not show significant signs of water. IL says that the soil along the perimeter is not graded away from the dwelling and this contributes to the movement of the foundation soils caused by soil saturation. Based on this, IL contends that the dwelling would undergo minor movement and cracking through the natural movement of the foundation soil. Accordingly, IL concludes that there was inadequate evidence to confirm that the leaking pipe was the cause of the claimed damage. Insurer’s expert says that underpinning works was not required to rectify the damage IL’s inspection of the dwelling located cracks in the plasterboard, cornice, mortar joints, windows and ceiling. They also note that floor measurements recorded at the dwelling showed a deviation of approximately 40mm. They submit that this deviation indicates that the foundation slab would be considered defective. IL has provided the VBA guide on floor levels as supporting evidence. Photographs provided by the complainant taken prior to underpinning was studied by IL. IL’s review of these photographs dete rmined, based on the size of the cracks, that most of the cracking in the dwelling would be considered to be predominantly slight, with a single crack being categorised as moderate. IL has provided the interpretation of footings performance of buildings standards in support of their findings. Based on these findings, IL submits that they believe that the installation of 21 underpins at the dwelling was unnecessary, unjustified and uneconomical. They also state that in the event that the damage and movement was caused by the escape of liquid, the rectification works should not have been carried out until the moisture in the soil had dried. IL concludes that in their opinion, the minor movement and cracking in Recommendation | Case number: 539671 Page 4 of 6 the property cannot be attributed to a leaking pipe but rather to natural movement of the foundation soil. Insurer is not liable for the damage While I accept that the complainant strongly believes that the defective storm water drain may have caused the damage, the lack of expert opinion to confirm this and the underpinning works being completed at the time of claim lodgement, has not assisted the complainant to establish this. I am not satisfied that the evidence presented by the complainant is sufficient to establish that damage to his property was ca used by the leaking pipe. The complainant’s policy specifically excludes cover for ground movement caused by erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement. The policy also does not list ground movement as an insurable event. In the absence of any other substantive explanation, I am persuaded to rely on the insurer’s expert’s reports that conclude that the damage was caused by natural earth movement. Therefore, for the reasons outlined above, the insurer is not liable for the cost of the damage to the complainant’s property as it was not caused by an insurable events. Recommendation | Case number: 539671 Page 5 of 6 6 Supporting information 6.1 Reports Report Key points insurer’s expert (A1) Report 21 May 2018  The underpinning company nor the engineer did any discovery work in trying to find out what was the cause of the movement and it was only until the underpins were being dug out that they found water in the soils around the home.  As the repair process is currently under way and the repair method has been advised by an engineer that has not been appointed by A1 we will not be able to proceed with any works at the property due to there not being a drying out period allowed. This is a general practice by engi neers to allow the soils to dry out back to their normal conditions. insurer’s expert (IL) Report 28 June 2018  There is inadequate evidence to indicat e that a leaking stormwat er drain is the primary cause for all recorded damage. Instead, localised subsidence along the south and east elevations of the dwelling can be directly attributed to the presence of uncapped perimet er soils and natural seasonal movement of the highly reactive clay bearing strata.  Cracking and movement at the dwelling pre - underp inning would be classified predominantly as Category 2, (slight), with a single case of a Category 3 (moderat e) crack  The overwhelming majority of cracks would be classified as Category 1 to 2, very slight to slight and such cracks would be considered norm al on all reactive sites across Victoria and generally do not require underpinning works to be carried out to rectify the distress. complainant’s expert (MU) Report 2 October 2018  During the inspection we conducted at the stated address it was deemed that the underpinning work had to be organised to ensure the continued structural integrity of the house. This work was performed according to the plans laid out by the engineer. Evidence of this will be attached in the form of photographs detailing the damage that the property had prior to the underpinning. complainant’s expert (GDI ) Report 1 October 2018  Attended property, found storm water blocked. Ran high pressure drain machine through storm water and partially cleared blockage. Aft er further investigation found collapsed drain at the front of the property, there was a section of approximately 2m of rectangle cast iron drain which was collapsed. Re attended property dig up cast iron drain and replaced with New PVC drain. Drain is now flowing. Recommendation | Case number: 539671 Page 6 of 6 6.2 Relevant policy wording Record Key points Cover for insured events page 22 We cover: Loss or damage to the building caused by liquid leaking, overflowing or bursting from any of the following :  any drain, fixed pipes, roof gutters or guttering and rainwater downpipes, drainage and sewage systems; General exclusions page 37 What we do not cover - You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Ground movement erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the following insured events:  Storm;  Flood (but only if you have cover for insured event ‘Flood’);  Earthquake and Tsunami;  Explosion.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.