Extent of insurer liability for storm claim; repair quality and handling disputed
Text of the determination
Determination | Case number: 538329 Page 1 of 8
Determination
Case number: 538329 29 May 2019
1 Determination overview
1.1 Complaint
The complainant’s home was damaged by hail and storm on 19 December 2017. The
insurer accepted the claim and elected to repair the damage.
The complainant says that not all of the agreed scope of works (SOW) were
completed, there are workmanship issues and further items were damaged by the
insurer’s tradespeople.
The complainant seeks to be cash settled $50,920 for the outstanding items.
1.2 Issues and key findings
What is the extent of the insurer’s liability for the claim?
The insurer must pay $32,361.35 in settlement of this claim.
Should the insurer pay non-financial loss?
The insurer should pay $1,500 in non-financial loss because the claim was not
handled reasonably. This is because the agreed SOW were not completed, there
were rectification issues and additional damage was caused by the insurer’s
tradespeople.
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer must cash settle the complainant $32,361.35 for the outstanding items
and in settlement of the claim.
The insurer must also pay the complainant $1,500 in compensation for non-financial
loss.
Determination | Case number: 538329 Page 2 of 8
2 Reasons for determination
2.1 What is the extent of the insurer’s liability for the claim?
Some items are no longer in dispute
A case analyst provided the parties with a recommendation on the issues in dispute.
The recommendation was substantially in favour of the complainant.
Both parties accepted the recommendation’s findings in relation to the insurer’s
liability for items: 2 ($350), 4 (nil), 5 ($1,500), 6 (nil), 10 ($100), 11 ($550), 13 ($100),
14 ($300), 18 ($452), 19 ($1,000) and 20 ($1,000). The total of these items comes to
$5,352 .
The other items in the recommendation remain in dispute.
1. Replacement of air conditioning condenser
The insurer denies liability for the air conditioning condenser, as it says the
complainant has not established this was damaged by the storm. The insurer says the
wiring/contacts are fused and unlikely related to the storm.
The insurer says the SOW was limited to the replacement of the air conditioner
casing. The insurer notes this was indicated to the complainant as early as 19 April
2018.
The documentation is inconsistent with the insurer’s position.
The SOW plainly says to ‘remove and repla ce air- conditioning condenser’. This is
consistent with CC’s initial report which said, ‘Hail has impacted … air -conditioner
condenser’.
The insurer provided an email from CC to the complainant dated 24 April 2018 to say
this item is on hold immediately a nd will be reviewed by an independent specialist. No
report from this specialist was provided. It is not clear why CC changed its position
from its initial report, particularly given that the initial report was completed about
three months prior and CC was satisfied there was hail impact to the condenser.
After the recommendation, the insurer presented an estimate for replacement of the
unit. In this quote, the tradesperson has advised that it will not be conducting any
works at this property ‘due to suspicious tampering of existing condenser unit’.
However, the tradesperson has not provided any further detail in relation to this. It is
not clear if such tampering occurred before or after the claim or was a result of CC’s
actions.
Determination | Case number: 538329 Page 3 of 8
I note the insurer provided an invoice from CC that said an air-conditioning mechanic
charged for three hours work. It is not clear what works were done to the machine or if
this is the tampering referred to in the current estimate.
On balance, I accept the air conditioner condenser should be replaced. It was
included in the SOW, and CC’s contemporaneous report was satisfied it was
damaged by the hail. The insurer is liable to replace this.
The insurer provided a new quote for the replacement of the unit, which totalled
$6,038 (including parts, labour and GST). However, as noted above, the tradesperson
who provided this figure was not willing to conduct the works for this amount.
The complainant submitted a quote from HAC totalling $17,645 (incl GST) for the
replacement of the air conditioning unit.
I prefer HAC’s quote. It is clear they are prepared to do the works for the complainant.
The works included taking all the ducting from the site and installing 10 ceiling outlet
positions, as well as allowing for four zones and controls. The insurer’s estimate for
labour only allowed $780 for all of this. This appears low.
Therefore, the insurer is to pay HAC’s quote, being $17,645.
3. Replacement of 2 x garage lights
The insurer accepted liability for this and the amount awarded in the recommendation
($314.15).
The complainant says the quote submitted does not include installation costs and has
sought an allowance of $100.
It is fair that an allowance for installation be included. The quoted provided by the
complainant was clearly limit ed to the items only. The complainant’s proposal for
$100 appears reasonable.
Therefore, the insurer should pay $414.15 for the lights.
7. Damaged pergola roofing and beams ($6,500)
The complainant relies on his quote from AP to rectify the pergolas, which totalled
$6,500.
The insurer provided a settlement to the complainant which included the cost to
remove and replace the pergola roofing (settlement email to the complainant dated 18
June 2018). The total amount allowed was $4,573.80 (incl GST). This settlement
email did not itemise the works to be settled.
The complainant disputes that this full amount went to the pergola works. He says
that:
Determination | Case number: 538329 Page 4 of 8
the cost to replace two garage doors, based on his quote from BG is $3,564
($1,782 per door)
the actual cost to rectify the pergolas is $6,500, based on his quote from AP.
The complainant’s quotes appear to be reasonable.
When the amount of $3,564 is deducted from the settlement figure of $4,573.80, that
leaves $1,009.80.
Based on the information presented, I agree with the complainant that the insurer
should pay the difference between $6,500 (the complainant’s pergola quote) and
$1,009.80 (the amount left in the settlement figure); that is, $5,490.20.
8. Garage ceiling issues – finish and paintwork ($8,662) and
9. Water entry to garage ceiling ($500 to $1,000)
The insurer advised the amount for the garage ceiling needed to be substantiated by
the complainant.
This amount appears to be associated both with the poor workmanship alleged by the
complainant as well as there being water entry coming into the garage (item 9). The
complainant says the water entry is associated with the original claim which was not
addressed originally.
There is no eviden ce supporting the complainant’s position regarding the water entry.
According to CC’s initial report, the complainant conducted make safe works to the
roof. This included replacing multiple roof tiles. It is unclear if this included tiles to the
garage. The complainant later engaged a contractor to review the garage roof and
conduct repairs after water entry.
That contractor provided no opinion as to the likely cause of water entry.
No other information has been presented to explain how the water entry has occurred
and in what way this was connected to the claim.
Therefore, based on the minimal information, there is insufficient basis to conclude
the insurer is liable for the additional water entry to the garage ceiling as part of this
claim.
The reinspect ion report obtained by the insurer says ‘insufficient repairs appear to
exist throughout ceiling/cornice’ when reviewing the works for removing and replacing
the ceiling plasterboard. The report also noted that for the cornice, there was ‘some
minor insuff iciency prepping and repairs’.
Determination | Case number: 538329 Page 5 of 8
The complainant has provided a quote from AP to supply and install materials for the
garage. The quote totals $8,662.50. This quote includes the removal and replacement
of the ceilings, cornices, lights and garage doors.
It is plain this quote accounts for damage associated with both the rectification and
water entry. As I am not satisfied the complainant has shown the water entry was due
to the original claim or repairs, then this quote cannot be accepted.
It is not clear what amount is necessary to address the rectification issues associated
with the ceiling and cornice. It would appear that this would likely require a painter
and possibly a plasterer.
Having considered the issues identified, and in the interests of achieving finality to this
dispute, I consider it fair in all the circumstances to allow $1,000 . This is to account for
contractors and materials (e.g. paint).
12. Garden shed shelving thrown out ($500)
The complainant provided a photo showing the shelving previously existed. He said
this was removed by the insurer’s contractor and not replaced.
The insurer has not provided any evidence to refute this.
The insurer should pay $500 for the garage shelving.
15. Outdoor table damage ($1,350)
The insurer’s submission dated 4 April 2019 accepted this was overlooked. The
insurer should pay $1,350 for the aluminium table.
16. Rear garage door damage ($1,782)
The insurer says it settled the complainant $1,480 for the garage door, as per the
settlement email dated 18 June 2018.
However, as noted above, two amounts of $1,782 have been deducted from this
settlement to account for two garage doors, with the remainder of the settlement
going towards the pergola.
The insurer provided an invoice showing it paid CC $360 for labour and $3,072 for
materials regarding the ‘garage door installation or repair’.
Given all this, I do not accept there is sufficient basis to provide any further allowance
to another garage door.
17 Damage to outdoor waterproof power outlet ($610)
The complainant disputes the finding in the recommendation that this is not covered,
and says that:
Determination | Case number: 538329 Page 6 of 8
The Outdoor waterproof outlet was damaged by [insurer’s] trades this outlet is
connected to my spa p ump and it is a static plug. The [insurer’s] electrician
confirmed this was broken due to misuse.
Email from [representative] at [insurer’s claims services company] to [insurer]
liability stance has made an allowance for $610.
In the reinspection report, t he assessor identified this and said, ‘Leads likely pulled
during use age causing pins inside to snap/damage’.
Based on the available information, it appears this was damaged whilst being used by
the insurer’s tradespeople. Whilst the assessor says the pin s were damaged due to
age, he does not expand on how he was able to specifically identify this in contrast to
misuse.
As the damage occurred whilst being used by the insurer’s trades, it is fair the insurer
pays for this item. The amount of $610 appears reasonable.
Further two items – (22) and (23)
In his rejection of the recommendation, the complainant raised two further items
which he says were not addressed.
The complainant says that the insurer should cover (21) the weather seal to the lower
aspect of a window, and (22) a building professional management fee. For the seal,
the complainant says this was accepted by the insurer with an allowance of $228.
This email setting out the insurer’s acceptance was not provided. I noted the
reinspection report provided by the insurer identified the seals were consistent with
wear and tear or deterioration. Their expert opinion is unrefuted.
Given this, I am not satisfied the evidence shows the window weather seal was
damaged by the storm.
The complainant says he needs a builder to manage the project and seeks an
allowance for this. I do not accept this. The amounts he has sought have been based
on quotes provided directly to him by individual contractors and suppliers as opposed
through a builder. Settlement has been affected on this basis.
Therefore, I do not accept it is appropriate to add a project management fee in such
circumstances.
2.2 Did the insurer process the claim reasonably?
Insurer should pay $1,500 in non-financial loss
The insurer disagrees with the recommendation finding and says that it processed the
claim reasonably.
Determination | Case number: 538329 Page 7 of 8
Compensation up to $3,000 per claim for non-financial loss can be awarded where a
complainant has suffered an unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with their expectation of enjoyment or
peace of mind.
Compensation is not awarded for the normal degree of inconvenience a person would
experience when having a problem with their insurer.
The insurer said that the complainant had unreasonable expectations as he submitted
his own list of claimed items and demanded that he be settled on this costing, without
assessment or acceptance by the insurer or assessor.
The insurer also says that its tradespeople had numerous difficulties satisfying the
complainant’s demands and this resulted in the complainant refusing to allow re -
attendance by other trades.
However, the information plainly shows there were numerous rectification issues that
required addressing. This included extensive works to the pergola. The information
also shows the insurer’s tradespeople caused damage to the complainant’s property
unrelated to the hail. In addition, the insurer had not completed all the works set out in
the SOW.
The independent report acknowledged the issues noting:
Some of these issues would be acceptable in isolation, in this case due to the
number of issues it is understandable why the owner is not happy
Given this, I accept the insurer’s handling of the claim was not reasonable and this
caused the complainant to suffer an unusual degree of inconvenience and
interference.
Taking this into account as well as our conservative approach, I consider it fair the
insurer pays the complainant $1,500 for non-financial loss.
Determination | Case number: 538329 Page 8 of 8
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.