claim_denial

Firmentitled to deny the claim
Decided2019-04-04
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A member claimed for storm damage to a business building after roof trusses and walls failed. AFCA decided the mutual society was entitled to deny the claim because the evidence did not show a protected storm event caused the damage rather than long-term deterioration.

Cover applies only to damage caused by a protected event, and the wear, tear and gradual deterioration exclusion applies where the evidence points to gradual deterioration.

Issues

Subjects and remedies

home or building damageno remedy

Related

Find similar determinations

Text of the determination

Determination | Case number: 538265 Page 1 of 8 Determination Case number: 538265 4 April 2019 Determination overview 1.1 Complaint The complainant is a member of the financial firm, which is a discretionary mutual society. Membership of the financial firm confers on its members the right to claim for the benefit of certain „protections‟. The complainant lodged a claim for damage to his building. The damage comprised of the failure of roof trusses and other structural damage. The complainant says this was caused by a significant storm event with high winds on 19 December 2017. The financial firm, relying on expert reports, said the damage did not arise from a „protected event‟. Instead, the financial firm says the damage arose from exclusions in its protection cover. Namely, the damage to the building was due to long term gradual deterioration. On this basis, the financial firm exercised its discretion to deny the complainant‟s claim. The complainant disputes this and maintains the damage was caused by the storm. 1.2 Issues and key findings Can the financial firm deny the claim? The financial firm can deny the claim because the evidence does not show the damage to the complainant‟s property was caused by a storm. 1.3 Determination The determination is in favour of the financial firm. The financial firm was entitled to deny the complainant‟s claim. The financial firm is not required to take any further action. Determination | Case number: 538265 Page 2 of 8 Reasons for determination 2.1 Can the financial firm deny the claim? Policy provides cover for protected events subject to exclusions The rights of members are set out in the Product Disclosure Statement (PDS) dated 1 December 2015. The operation of the scheme is also governed by the financial firm‟s constitution and rules. There is no dispute the complainant is a member and is entitled to the protection cover issued by the financial firm. The PDS says the financial firm will consider claims for damage to the building caused by a „protected event‟ during the „period of protection‟. A „protected event‟ includes ten „perils‟. Relevant to this is „storm, wind, rain or snow‟. The PDS also says the financial firm will not pay for damage caused directly or indirectly by wear, tear or gradual deterioration. There is no dispute the financial firm exercised its discretion to deny the complainant‟ s claim on either of the following bases:  the damage was not caused by a „protected event‟  the cause of damage falls within the exclusion for wear, tear or gradual deterioration Information does not show the storm damaged the property Both parties have provided a report from engineers. IM was engaged by the insurer and T by the complainant. Neither of these experts concluded that the damage was caused by the storm. In the first report, IM concluded the damage was caused by footing movement of the eastern wall. T disagreed. T said the damage was due to the failure of the roof trusses. This was caused by the failure of the masonite connection plates at the bottom chord join in the centre of the trusses. Given the age of the building, he said „the failure of t he masonite plates is possibly due to long term fatigue from cyclic wind loading ‟. As evident, neither engineer says the cause of damage was the storm. Further, if I accept T‟s opinion, the damage is consistent with wear, tear or gradual deterioration. The complainant has provided other opinions in support. These are from R, C, K and W. These experts disagreed with IM‟s opinion that there was footing movement. This is consistent with T‟s evidence that footing movement was not a cause. However, only Determination | Case number: 538265 Page 3 of 8 R and K were prepared to say the wind caused the damage. The other two provided no opinion as to the possible cause. In his conclusion, K simply said „the only other factor would be wind‟. K did not appear to take into consideration T‟s opinion of the masonite plates failing. Therefore, K‟s opinion is not persuasive. R (a builder) does say that in his opinion, the plates looked to have been broken by sheer force. However, this is inconsistent with T‟s evidence who provided no such conclusion. It is also inconsistent with the fact:  the highest recorded wind speeds from the nearest weather station was about 70km/hr – this would not be enough to cause such structural damage  there is no evidence of such significant damage in the neighbourhood that day Therefore, I am n ot persuaded by R‟s opinion. Given all this, I am not satisfied the available information shows the storm damaged the property. Financial firm entitled to deny the claim The financial firm exercised its discretion to deny the claim on the basis the evidence did not show the storm cause the damage. I am satisfied the financial firm‟s conclusion was reasonably open to it based on the available information. Therefore, I accept the financial firm is entitled to deny the complainant‟s claim. Determination | Case number: 538265 Page 4 of 8 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint 3.2 Reports Re port Key points financial firm’s expert ( AN ) Report 1 February 2018  We have conducted a review of the Daily Weather Observations that were rec orded in Mount Gambier on 19 December 2017 and note that a north westerly wind was recorded at 2:12pm with a speed of 70km/h. That was the second highest wind speed recorded in Mount Gambier during that month.  The Beaufort Wind Scale describes wind speed betwee n 63km/h and 75km/h as „gale force‟ winds with a physical description on land including the breaking of twigs on trees and walking progress generally impeded. The scale does not include the likelihood of any structural damage within that range.  The recorde d wind speed on the date of loss does not appear to have been sufficient to have caused the extent of damage on its own however it is possible that stronger wind gusts may have occurred near your Member‟s premises. We have no means of being able verify thi s occurring. financial firm’s expert ( IM ) Report 9 March 2018  Before the roofing was replaced, the roof was clad with c orrugated iron sheeting that was prone to leakage during rain events because of corrosion.  There was staining from previous and prolonged moisture ingress to the roof purlins and trusses throughout the warehouse (including to the Mas onite connection plates)  Our review of records from the same weather station indicate the wind speed recorded on 19 December 2017 has been equalled or exceeded eleven times in the preceding twelve months, reportedly Determination | Case number: 538265 Page 5 of 8 Re port Key points without causing damage to the building. This indicates the building has been subjected to numerous similar wind gusts throughout its life without suffering damage.  Our review of aerial site i mages from Nearmap.com suggests the roof sheeting was replaced between 16 October 2017 and 18 January 2018.  […]  The member advised us the roofing was replaced approximately five years ago.  We also found evidence which, in our opinion, indicates the damage is not entirely recent (although it is possible the damage recently worsened, refer further discussion below).  The bottom chord splice connection included two skew nails that protruded from the face of one member into the adjoining member. These nails were corroded [8], with the corrosion being particularly more severe at the more severe failures. This indicates the nails have been ex posed to the atmosphere for some time, which means the splice began to separate some time ago.  The ceiling grid has separated along its junction with the eastern wall. Based on the accumulation of contaminants between the separated members (such as dust and cob webs) [9], this separation has not occurred recently.  On the two southern trusses, where the failure has not been as se vere, the Masonite splice plate has rupt ured, but the secondary plate along the chord‟s top face has not (nor has it been pulled out from the bottom chord or otherwise disturbed) [10]. This may indicate that this secondary member was retrofitted to the tru sses after the splices had begun to fail in an attempt to strengthen them. If the Masonit e‟s failure had occurred recently, we would expect to observe a failure of this secondary member as well. financial firm’s expert (IM) Report 3 July 2018  […] the most recent failure of the roof trusses had occurred after previous instances of failure (such as the rupture of the original M asonite splice plat es).  considerable moisture staining to the roof framing (including purlins, the truss members themselves a nd the original Masonite splice plates), which indicates the roof trusses have been deteriorating from exposure to le ak age in the roof for some time, and  the tapered gap between the new boundary fence and the eastern wall, which extends perpendicular to th e eastern wall near the boundary with S s treet (refer to photo 7 in our p revious r eport ). The tapered gap indicat es the fence was probably constructed whilst the wall was already in a rotated position, otherwise the fence would have been constructed flush against the eastern wall. ( o ur review of aerial site images confirms this fence was constructed before, at least, October 2017 and, therefore, before the day the damage to the wall is alleged to have occurred).  Therefore, even if footing movement was not t he caus e of damage in this instance (which we maintain our opinion that it is), in our Determination | Case number: 538265 Page 6 of 8 Re port Key points opinion, there is clear evidence that: • the damage predates the day the damage is alleged to have occurred, and • the structure was in a deteriorated condition and had undergone structural failures prior to the day the damage is alleged to have occurred. financial firm’s expert (IM) Report 11 July 2018  The R r eport alleges there was no evidence of “moisture or wear and tear” to the central bottom chord splices. We respectfully disagree with this finding. As outlined in our original report, we observed evidence of long - term roof sourced moisture ingress througho ut the building (including, but not limited to, staining to the suspended ceiling tiles, timber purlins and truss members, and the m asonite splice plat es ). financial firm’s expert (IM) Report 17 September 2018  The evidence outlined in our p revious r eports shows the damage was not caused by a single fort uitous wind or storm event, or other insurable peril.  Moreover, T ‟ s assertion that the damage was caused by material fatigue from cyclic wind loading is consistent with our assessment that the damage was not caused by a single wind or storm event. Material fatigue occurs from the cumulative effects of tens of thousands (if not hundreds of thous ands or more) of loading cycles (i.e. innumerable wind gusts), which gradually weaken material over time. Material fa tigue does not occur from a single excessive or fortuitous event. Consequently, our understanding is that T also believe the damage was not caused by a single wind or storm event. financial firm’s expert (AN) Report 18 September 2018  The aforementioned part of the T report highlighted in bold text above, suggests that the failure of the masonite plates is possibly due to long term fatigue from cyclic wind loading. The T report is unable to 'pinpoint a specific cause for the failure' such as a defined eve nt or covered peril.  Both reports tend to concur that the ultimat e cause of the failure to your Member's roof is by long term gradual deterioration rather than it being caused by a single and identifiable peril or event as has been alleged by your Member.  On that basis, whilst the difference in opinion as to the cause of the walls rot ation remains, it appears as though the damage to your Member's building has been caused by long term gradual deterioration, howsoever caused. c omplainant’s expert (R) Report undated  While inspecting the damage, I noticed that there doesn‟t seem to be any damage to the limestone foundation buried at the base of the wall as stated in the engineer‟s report. The stones and mortar joints show no sign of downward deviation.  The wal l looks to have been damaged by downward motion of the roof (e.g. wind event) which has cracked a number of the plat es across the joins in the centre trusses of the building. The centre Determination | Case number: 538265 Page 7 of 8 Re port Key points plates show no signs of either moisture or wear and tear and look to h ave been broken by shear force.  As the top chords of the trusses have pressed downward, they have caused an outward motion which has pushed on the exterior wall, and therefore caused it to fail. complainant’s expert (W) Report 28 May 2018  It is my opinion that the tilting (leaning) of the masonry wall is not caused by footing failure, either tilting or subsiding.  There is no horizontal or vertical cracking in the Mt. Gambier stone wall or the mort ar joints, which would be obvious if footing failure had occurred. complainant’s expert (C) Report 24 May 2018  A visual inspection of the wall does not show any signs of cracking in limestone blockwork or separation in mortar joints between blockwork. No indication of any diagonal or vertical movement of blockwork mortar joints was visible.  The condition of the soil below this point in which the footings have been placed was moist and firm.  No visual or statistical evidence was found to support the theory that the walls had been affected by settlement or s ubsidence.  In conclusion, it is clearly evident that there is no subsidence or long - term settlement in the footings. Accordingly, it would be inaccurate to say that the present truss damage was caused by settlement or subsidence. complainant’s expert (K) Report 25 May 2018  It appears that there isn‟t any damage at the base of the stone walls to suggest movement of footings. […]  For the roof ceiling trusses to be damaged as it is the only other factor would be wind (sic) complainant’s expert (T) 30 August 2018  We do not agree with the I report that the footing has rotated due to long term settlement of the foundation soils. The soils encountered adjacent and below the stone footing appeared compact.  We are of the opinion that the eastern wall has rot ated due to failure of the roof trusses. The trusses have failed due to a failure of the masonite connection plates at the bottom chord join in the centre of the trusses. The roof trusses have been performing satisfactorily up until the point of failure. I t is difficult to pinpoint a specific cause for the failure of the masonite plates, but given the age of the building, the failure of the masonite plat es is possibly due to long term fatigue from cyclic wind loading. c omplainant’s expert (T) Email 15 November 2018  on review of our site photos and the I report, we don‟t believe that there is enough evidence to suggest that the masonite plates have been damaged by moisture. The surrounding timber members of the truss don‟t appear to be moisture stained s o we highly doubt that if there was moisture staining that it would be isolated to the Determination | Case number: 538265 Page 8 of 8 Re port Key points masonite plates only.  Secondly, we don‟t agree with the I report that the secondary timber over top of the bottom chord splice was ret ro fitted aft er the masonite plate s began to fail. More likely the secondary member was used during construction of the trusses to secure the two bottom chord members prior to fixing the masonite plates and nails to the splice connection. 3.3 Relevant policy wording Record Key points What is protected Page28  If 'Business Buildings' is specified in your Schedule of Protection, we will protect you for loss or damage to your business building(s) in Australia and caused by a protected event during the period of protection. What is not protected Page 31  Specific exclusions We will not pay loss or damage to or arising from: […] (d) wear and tear, gradual deterioration or any gradually operating cause.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.