Home / Financial Firm (Unknown - Insurer) / Determination 538230

Determination 538230

Cash settlement amount for storm damage repairs after claim delays

FirmFinancial Firm (Unknown - Insurer)
Decided2019-02-22
ProductGeneral Insurance · Other general
OutcomeFor the complainant in part
Amount awarded$100,000
Non-financial loss—
Amount claimed$172,189
SourceAFCA PDF

Summary

After a December 2016 storm, the insurer accepted a claim and offered cash settlements while the complainant's delays and cancelled inspections slowed assessment. AFCA ordered a $100,000 cash settlement, above the insurer's offer, but refused compensation for non-financial loss.

The insurer must exercise its cash-settlement discretion fairly and in good faith, and the complainant's own delays did not justify limiting the insurer's liability for storm damage.

Issues

Subjects and remedies

natural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 538230 Page 1 of 11 Determination Case number: 538230 11 February 2019 1 Determination overview 1.1 Complaint The complainant lodged a storm damage claim on 9 February 2017 with the financial firm (the insurer) for an event which occurred on 27 December 2016. The insurer accepted the claim. It obtained a scope of works and elected to cash settle the claim because:  the complainant failed to mitigate her loss, causing exacerbation of damage  the complainant failed to complete maintenance issues, allowing further damage  it is not liable for the extra non-event related damage  its repair contractors cannot separate claim related and non-claim related repairs. The insurer says the complainant lodged the claim six weeks after the damage occurred, cancelled numerous claim related appointments , caused delays in obtaining her own report and inhibited its ability to promptly assess the extent of damage. The complainant disagrees with the insurers claim of exacerbated damage and rejected the latest cash settlement offer of $93,400. She says the amount is not sufficient and does not consider her absorbing the risk of having the work carried out. She maintains her quote of $172,189.05 reflects the true value of the repairs. 1.2 Issues and key findings Did either party contribute to the claimed delays? The chronology of events in section 3.3 of this determination shows most delays experienced during the claim were substantially caused by the complainant. Is the insurer liable for all claimed damage? Although the insurer has not substantiated what extra damage occurred due to delays, it is reasonable to find that the delays had some impact on the assessment of claim related damage. Determination | Case number: 538230 Page 2 of 11 Is the complainant entitled to compensation? For the reasons outlined in section 2.3 below, the complainant is not entitled to compensation. 1.3 Determination This determination is partially in favour of the complainant. The insurer is required to cash settle the claim for the sum of $100,000 to complete all repairs in line with policy provisions. Determination | Case number: 538230 Page 3 of 11 2 Reasons for determination 2.1 Did either party contribute to the claimed delays? The property owner who lodged the claim with the insurer is represented by a broker. For the sake of brevity, this determination refers to the property owner and her representative as „the complainant‟. Insurer was unable to promptly determine the extent of loss The complainant explained that the property which sustained storm damage is not her primary place of residence, and she was suffering ill health at the time. She says it is for these reasons the claim was not lodged for six weeks. Following receipt of the claim, the insurer attended the property and confirmed its acceptance of liability. It attempted to arrange an on-site inspection to determine the extent and cost of the loss. Claim notes show the following dates were arranged, however, the complainant cancelled each of them:  2 March 2017  10 April 2017  20 April 2017. The insurer, on 19 April 2017, then enquired if the complainant would provide her own quote. A few days later she confirmed she would. The insurer successfully arranged AI‟s on -site assessment on 1 May 2017, and obtained its detailed scope of works and estimate on 9 May 2017. It also attempted to arrange a quote from HP around 23 June 2017, as it still had not received the complainant‟s preferred repairer‟s report. The available information shows the complainant refused property access to HP, and informed HP its services were not required. Complainant’s actions resulted in delays Information shows the insurer was inhibited in obtaining information required to explore a fair and reasonable outcome with the complainant to finalise the claim. Despite numerous follow ups with the complainant and SC, the insurer did not receive her quote until 15 August 2017. Nor was it allowed to obtain HP‟s comparative quote. While the panel considers the complainant was of ill health, it acknowledges her representative‟s presence during the claim. The panel is not satisfied sufficient action was taken by the complainant‟s representative to assist with progressing the claim. The panel is satisfied:  the delays were imposed by the complainant Determination | Case number: 538230 Page 4 of 11  the insurer‟s claims of exacerbated damage due to these delays is not substantiated  these delays are not a valid reason for the insurer to limit its liability. 2.2 Is the insurer liable for all claimed damage? Insurer did not substantiate how delays caused extra damage On 13 and 14 September 2018, the complainant confirmed the issue in dispute is the cost of the repairs. She also maintains there is no extra damage, and all damage occurred because of the storm. The insurer is unable to specify what extra damage occurred due to delays. Nor is it able to confirm if any damage was exacerbated by the delay or how the delays contributed to the extent of damage. However, it is reasonable to find that the delays did have some impact on the claim related damage. In these circumstances, the panel is satisfied that it is fair and reasonable to take into account the delays in assessing the cash settlement of the claim. Insurer is liable for damage to the upstairs landing area At conciliation, both parties agreed the landing area was struck out of the scope of works. Following the conciliation, the complainant retracted from the agreement. AI‟s report recommends the complainant arrange a roof assessment to determine the cause of long term water damage to the landing area; the complainant did not arrange a roof inspection, and the insurer has not substantiated why it says it is long term damage. Due to the uncertainty in respect to the insurer‟s liability , the panel cannot be completely satisfied the landing area damage occurred d ue to the storm giving rise to this claim, but an allowance should be made by the panel in assessing a cash settlement. Insurer must exercise discretion to cash settle reasonably The policy allows the insurer to settle a claim by repairing damage or paying the complainant the cost to repair or reinstate the property to the condition it was in just before the loss or damage occurred (cash settlement). However, the insurer must exercise this discretion fairly, reasonably and consistent with the principles of utmost good faith. The panel recognises the insurer never initially offered to complete the repairs. When the complainant eventually requested it to do so it refused, as there may be exacerbated damage and the quote originally obtained was out of date (only valid for 30 days). The insurer chose to offer a cash settlement for the repairs: Determination | Case number: 538230 Page 5 of 11  based on the scope of works provided by AI  because it says it is not liable to complete repairs not directly caused by the storm. As already discussed, the panel is not satisfied the insurer substantiated what non- storm related damage occurred for which it is not liable, but believes allowance should be made for the impact of the delays on the storm related damage. Given how long this claim has remained unresolved, the panel forms the view that obtaining further quotes to determine a fair cash settlement amount will likely result in further disagreements and delays. It finds that a cash settlement with appropriate allowance for contingencies is appropriate in this circumstance. Insurer is required to repair all claimed damage reported There is an argument that there is insufficient information available to determine a fair and reasonable repair cost because:  the insu rer‟s scope of works was an estimate only  the insurer says the original settlement offer fell short of the true cost of repairs  neither party provided a comparative quote  the insurer‟s amended cash settlement calculations are not sufficiently substantiated to show repairs are actionable for the offered amounts. In addition, the panel is satisfied by the material available and discussions during the conciliation, that th e complainant‟s quote is likely inflated (see section 3.3 below, complainant‟s representative‟s claim note of 31 August 2018). For the above reasons, it is unfair to entirely rely on the estimates and quotes currently available. The panel further considers the complainant‟s material shows, on 29 January 2018, she was willing for AI to complete the repairs identified in its scope of works if a cash settlement could not be agreed. She reiterated this on 14 February 2018 and 30 March 2018. Additionally, upon lodging this complaint, she expressed her desire for a cash settlement amount, but also stated she „just needs it fixed‟. The panel is satisfied the complainant was willing since January 2018 for AI to complete the repairs, but would have agreed to an acceptable settlement. The panel notes that there have been a number of offers of cash settlement in the course of the dispute. The insurer‟s latest offer was around $94,000 , with the complainant‟s latest position being $120,000. Taking into account all the factors outlined above, the panel is satisfied that a settlement should be based on the original insurer‟s assessment of the damages of $73,366.91 together with a 25% allowance for the complainant having the builder‟s risk, making a total of $94,208, and a further a sum for other minor items in dispute or unexpected items. The panel finds it is fair that the insurer is required to pay $100,000 to the complainant to complete the repairs. Determination | Case number: 538230 Page 6 of 11 2.3 Is the complainant entitled to compensation? AFCA has a conservative approach to compensation Non-financial loss includes claims for stress or inconvenience caused by an error of the insurer. The maximum amount AFCA can award for non-financial loss is $3,000 for each claim of loss. AFCA will only award this type of compensation if there has been an unusual degree or extent of inconvenience. AFCA will not award compensation for loss a complainant may incur because of pursuing a complaint or rectifying an insurer‟s error. When assessing whether the circumstances are of an unusual nature , AFCA will review:  the degree or extent of physical inconvenience suffered  the general time taken to resolve the complaint  the extent to which the insurer‟s actions interfered with the complainant‟s expectation of enjoyment or peace of mind. If compensation is awarded, it is unlikely to be substantial. Complainant is not entitled to compensation The panel considered the chronology of events and:  the delay between the date of event and the date of claim lodgement  the complainant‟s cancellation of various initial assessment appointments  the complainant‟s delay in prov iding a quote  the complainant‟s refusal of allowing the insurer to obtain a comparative quote. Although the insurer is liable to complete the repairs and some delays arose due to its attempt to limit liability, the panel is satisfied the insurer attempted to seek avenues to progress the claim and it sought to accommodate the complainant in rescheduling appointments. The material available shows the complainant did not satisfactorily participate in allowing the assessment to progress in a timely manner. On this basis, the panel is satisfied the complainant is not entitled to compensation. Determination | Case number: 538230 Page 7 of 11 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint claim claim 3.2 Reports relied upon Report Key points AI (Insurer) Loss adjuster‟s report #1 09 - 05 - 2017  S torm - related damage to multiple rooms .  C omplainant informed writer the roof tiles were replaced by the SES .  Q uote allows for repair of damaged plaster glass ceilings including decorative mouldings – may require special attendance to replicate .  Q uote stands for 30 days only. AI (Insurer) Loss adjuster‟s report #2 12 - 05 - 2017  R eport completed following delayed ins pection of property on 01 - 05 - 2017 .  C onc erns re matching ceiling and decorative mouldings – to be advis ed accordingly if special manufacture required and quoted .  Q uote allows for replacement of carpets in lounge and second lounge, cutting off at doorway (policy provision only for “same room”) .  C omplainant advised carpet is imported and of high quality – to be determined if import is required and how policy responds in this case .  F laking paint on office ceiling – deemed age - related damage .  D amage in upstairs ceiling loft appears to be long - term water damage as noted in first report .  R oof should be inspected to determine cause of water ingress so that damage can be rectified – ins ured to arrange ins pection by preferred contractor .  D amage to carpet in second lounge room near sliding d oor: > not storm related, but a maintenance issue > sliding door repaired to prevent water entry into the room > carpet accept ed as other carpet damage was identified in same room > insured required to repair sliding door . Determination | Case number: 538230 Page 8 of 11 Report Key points  AI allowed provision for replacement of d amaged velvet wallpaper: > wallpaper company advised no longer available > would need to be sourced from England or Germany > unsure how policy would respond in such a circumstance .  C leaning of piano area arranged to determine extend of piano damage .  I nitial res erve for repairs and carpet replacement are grossly inadequat e – possible repair costs may increase given concerns to match materials .  P er complainant‟s request, scope of works was forwarded to her preferred builder, SC, to obtain a quote. SC (Complainant) Repair quote 20 - 07 - 2017  Q uote compiled based on specifications/scope of works AI provided to SC via email on 12 - 05 - 2017 .  S ome photographs attached .  N o comments regarding cause of damage, only scope of works and quote. Claim note (Insurer) In ternal records 27 - 02 - 2018  If they (complainant) are not able to get more via c/s they are wanting AI to do the works, which P has said if they do, he will have to get them to re - quote again and it will be more than the above amount. 3.3 Chronology of events Date Event 27 - 12 - 2016  Date of storm event. 09 - 02 - 2017  Claim lodged by broker.  Insurer‟s claim notes indicate (p a g e 44, re delay in lodgement) applicant was unwell and had periods in hospital. 12 - 02 - 2017  Complainants representative‟s claim notes confir m loss adjuster appoint ed . 20 - 02 - 2017  Insurer ‟s loss adjuster attended premis es. 03 - 03 - 2017  Complainants representative‟s claim notes show insurer informed it is awaiting scope of works /quote from builder. 27 - 03 - 2017 Insurer‟s claim notes show :  claim liability accepted and communicated wit h complainant  insurer awaiting loss adjuster‟s report and quote  i nsured cancelled builder‟s appointment, not yet reschedule d . 31 - 03 - 2017  Complainant‟s representative‟s claim notes show AI builder‟s quote arrang ed . 19 - 04 - 2017 Insurer‟s claim notes indicate complainant cancelled appointments for assessment of reported damage:  0 2 - 0 3 - 20 17  10 - 0 4 - 20 17  20 - 0 4 - 20 17 Insurer requested complainant to confirm if she will provide her own quote. Determination | Case number: 538230 Page 9 of 11 Date Event 20 - 04 - 2017  Complainant‟s representative‟s claim notes show assessment booked for 01 - 05 - 2017. 21 - 04 - 2017  Insurer‟s claim notes show complainant confirmed she will get her own quote. 02 - 05 - 2017  Complainant‟s representative‟s claim notes show AI attended site assessment. 08 - 05 - 2017  Complainant‟s representative‟s claim notes show loss adjuster will liaise with SC re quote items. 18 - 05 - 2017 Insurer update d complainant :  Loss adjuster second report received  AI repair quot e provided  Loss adjuster awaiting insured‟s preferred r epairer quote (Structural Concepts)  Loss adjuster recommends loft roof ins pection due to long term water damage. 30 - 05 - 2017  Insurer‟s claim notes show an unsuccessful follow up call to the complainant for her preferred quote. 09 - 06 - 2017  IG informed complainant it continues to await SC‟s quote to progress the claim. 23 - 06 - 2017  Insurer ‟s claim notes show it emailed the complainant a follow up for her quote.  Complainant‟s representative‟s claim notes show she was informed b y SC it do es not specialize in domestic claims.  Complainant emailed insurer‟s loss adjust er seeking second quot e from HP . 26 - 06 - 2017  Insurer‟s claim notes show the complainant instructed t he insurer to obtain HP quot e as SC is slow. 10 - 07 - 2017  Insurer confirmed with the complainant HP is engaged to provide a second quot e. 20 - 07 - 2017  Insurer‟s claim notes show HP is unable to attend property as complainant changed he r mind and want s to wait for he r own report.  SC report completion date (not received by insurer until 15 - 08 - 2018). 28 - 07 - 2017  Insurer‟s claim notes show it confirmed with the complainant HP has not provided access to the property.  Still awaiting SC ‟s q uote.  Complainant‟s representative‟s claim notes show the insurer informed her HP unable to obtain second quote due to her refusal to allow another builder access to the property , and she instructed it their service was not required. 09 - 08 - 2017 Loss adjuster informed complai nant:  SC still has not provided its report  HP will attend in place of SC unle ss it provides the report by 11 - 08 - 2017  c laim file will be closed if SC report not provided and insured denies access to HP . 15 - 08 - 2017  Insurer received SC quote dated 20 - 07 - 2017 from SC directly.  Insurer‟s claim notes indicat e it recommends cash settlement. 31 - 08 - 2017  Insurer‟s claim notes indicate loss adjusted followed up for response to cash settlement offer. Complainant‟s representative‟s claim notes show :  complainant‟s rela tive knew SC would be expensive  loss adjuster emailed informing there is room to negotiate but only in consideration of Determination | Case number: 538230 Page 10 of 11 Date Event what is fair to both parties considering the view that damage likely occurred over long period of time (but will not be anywhere near the quote provided by SC)  l oss adjuster confirmed compl ainant refus ed HP access  l oss adjuster keen to set up an appointment. Insurer‟s claim notes show it forwarded both quotes to the complainant with options for progressing claim. 18 - 09 - 2017  Meeting between complainant and loss adjuster confirmed for 27 - 09 - 2017. 27 - 09 - 2017 Complainant‟s representative‟s claim notes provide min utes for on - site client meeting:  r eviewed and compared SC and AIB quotes  m ajority of cost discrepancies are related to wall paper and carpets  w allpaper made of gold is under - priced by AI  explore if negotiating a settlement range to resolve, or insurer to complete repairs. 02 - 10 - 2017 Insurer‟ claim notes show contact from complainant :  disputing cash settlement amount  complainant said there is additional damage now (water damage to walls in the sleep outs that was not visible at t he time of inspections). The notes also say:  the property remains vacant and maintenance issues have not been addressed  alternative loss adju ster appointed to review quot e  acknowledges AI under - q uoted the reserve amount for carpet and wallpaper amounts. 05 - 10 - 2017 IG informed broker:  SC‟s quo te is quadruple that of AI‟s quote.  SC ‟s quote includes additional wor ks not relat ed to the claimed event  insurer suggest s an alternate loss adjuster (and qualified building consult ant) attend to inspect the pro perty  a ny identified maintenance needs to be rectified to avoid further damage. 10 - 10 - 2017  Complainant‟s representative‟s claim notes show meeting with the loss adjus ter arranged in an attempt to resolve the claim. 24 - 10 - 2017  Loss adjuster attempted to cont act complainant to arrange a time to inspect property, assess actual resultant damage , and amend the scope of works. 07 - 11 - 2017  Insurer‟s claim notes show new loss adjuster not yet allowed access to the property. 16 - 11 - 2017  Insurer‟s claim notes indicate new loss adjuster has not been allowed access to property, but an appointment now scheduled for 27 - 11 - 2017. 06 - 12 - 2017  Insurer‟s claim notes show new los s adjuster at tended property and report due shortly. 07 - 12 - 2017  Complainants representative‟s claim notes indicate wallpaper can be fixed rather than replaced ; a waiting update figures from loss adjuster. 29 - 01 - 2018  Loss adjuster confirmed complainant requested increased settlement amount based on SC ‟s quote , or AI to do identified repairs .  Insurer infor med complainant AI ‟s quote expired - further resultant damage occurred due to insured‟s delaying of claim process and failure to mitigate loss.  Insurer ‟s claim notes explain it cannot proc eed with AI as quote expired an d damage has escalated due to her dela ys and failure to mitigat e the loss. 14 - 02 - 2018  Complainant instructed the insurer to attend to repairs if it cannot offer a reasonable Determination | Case number: 538230 Page 11 of 11 Date Event cash settleme nt amount . 06 - 03 - 2018  Complainant discussed with the insurer the claim should be settled for $110, 000 , or AI to complete the repairs. Insurer responded:  AI unable to do the repairs due to further da mage caused by insured‟s delays  AI could have attended to quoted repairs back around May 2017 but in sured wanted to seek own report  SC‟s quote provided for non - claim - related repairs. 30 - 03 - 2018 Complainant informed insurer:  insured cannot fix repairs for offered amount  repairs already authorise d to proceed back on 14 - 02 - 2018  requests insurer to provide photographs and commentary of additional damage it says occurred due to delays . 09 - 04 - 2018 Insurer informed the complainant:  settlement offer stands as is  SC‟s quote is excessive  further damages occurred due to insured‟s failure to mitigate loss, restricting property access and seeking own report; insurer was unable to attend to repair damage due to the above. 03 - 07 - 2018 Loss adjuster informed the insurer :  of the main differences bet ween SC and AI‟s quotes (brea kdown provided)  SC are a commercial builder and do not carry out domestic work, leading to their significant delays and increased costs.