Home / Financial Firm (Unknown - Insurer) / Determination 537421
Determination 537421
Insurer refused to complete water damage repairs until waterproofing was done; cash settlement disputed
Summary
The complainant's water damage repairs stalled after the firm insisted on waterproofing before repairs, and the firm had rejected cash settlement offers. AFCA ordered the firm to undertake the agreed repairs, found it not liable for waterproofing, and awarded $2,000 non-financial loss for delay.
The conciliated repair obligation governed, and waterproofing was outside the policy because the walls had no structural damage from the insured event, while the firm's poor communication and delay justified non-financial loss.
Issues
- Repairs or contractors primary · upheld
“The financial firm is required to undertake rather than cash settle the repairs. However, the financial firm is not liable for waterproofing the wall.”
- Delay secondary · upheld
“This has unduly extended the time taken to resolve this dispute and required it to return to AFCA.”
- Poor communication secondary · upheld
“The financial firm... failed to adequately communicate its requirements to undertake repairs to the complainant.”
Subjects and remedies
home or building damagepay non financial lossrepair or rectify
Text of the determination
Determination | Case number: 537421 Page 1 of 14
Determination
Case number: 537421 7 January 2019
1 Determination overview
1.1 Complaint
The complainant holds a home building and contents insurance policy with the
financial firm. The complainant lodged a claim for water damage arising from a
leaking pipe which occurred on or about 15 May 2014. A dispute regarding the claim
was later lodged at the Financial Ombudsman Service (now the Australian Financial
Complaints Authority). The dispute was conciliated and terms of agreement were
entered into between the parties. The relevant terms included that:
within 4 weeks the complainant was required to confirm that the gap in the
concrete path identified by the financial firm during its claim assessment had been
rectified.
within 14 days of the confirmation that the concrete path was rectified the financial
firm would authorise its repairer to conduct repairs.
The complainant met the requirement to rectify the gap in the concrete path and
notified the financial firm. The financial firm determined that no waterproofing of the
walls had been completed by the complainant. It refused to undertake repairs until
waterproofing had occurred. The complainant disputes the financial firm‟s refusal to
progress the repairs and has rejected cash settlement offers.
1.2 Issues and key findings
Is the financial firm required to undertake the outstanding repairs?
The financial firm is required to undertake rather than cash settle the repairs.
However, the financial firm is not liable for waterproofing the wall.
Is the complainant entitled to non-financial loss?
The complainant is entitled to $2,000 for non-financial loss to compensate her for the
delay caused by the financial firm in resolving the dispute adequately.
Determination | Case number: 537421 Page 2 of 14
1.3 Determination
This determination is partly in favour of the complainant. This determination finds:
The financial firm and the complainant should undertake and finalise repairs in
accordance with 2.1 of this determination.
The financial firm should pay compensation of $2,000 for non-financial loss to the
complainant within 21 days from the date of the acceptance by the complainant of
this determination.
Determination | Case number: 537421 Page 3 of 14
2 Reasons for determination
For the purpose of this Determination the complainant and her authorised agent will
both be referred to as „complainant‟.
This complaint has been the subject of a recommendation issued by AFCA on
7 November 2018. The financial firm has rejected the recommendation and provided
further submissions.
This determination follows consideration of all of the exchanged material, both before
and after the recommendation and is based on what is fair in the circumstances.
2.1 Is the financial firm required to undertake the outstanding repairs?
The parties agree that an insured event has occurred
The parties have agreed that an insured event occurred which resulted in damage
covered by the insurance policy.
A disagreement has arisen regarding the extent to which the financial firm is liable for
the repairs. In particular, whether the financial firm is required to undertake or cash
settle repairs and whether it is required to complete waterproofing to the walls.
The complainant had notice of the need to conduct waterproofing
The evidence provided to AFCA suggests the financial firm has previously
communicated to the complainant that she needed to undertake waterproofing. The
financial firm informed the complainant of the need to water proof both prior to and
post the agreement, as follows:
The claims decision letter dated 6 August 2014
Email to the complainant‟s broker dated 27 October 2014
Report dated 29 October 2015 stating the assessor had met with the complainant
and her representative to discuss concerns. It appears that they had not heard
from the broker in over 12 months at this point. However, the report goes on to
suggest that the complainant had agreed to pay for waterproofing to the relevant
wall.
Email to the complainant dated 12 May 2017
There are also several expert reports which refer to the need for waterproofing which
have been exchanged with the complainant.
The expert evidence that waterproofing is required to ensure the repairs can
withstand ongoing elevated moisture levels is accepted. The relevant walls are
partially below ground level and were exposed to water from the storm water pipe.
Determination | Case number: 537421 Page 4 of 14
However, the walls will also be continuously affected by general ground level moisture
variation in the soil adjacent to the wall. Accordingly, if the wall has no waterproofing
then the re-painting of the walls will fail as the paint will flake and peel.
Based on the evidence, the waterproofing is required and the complainant had notice
that waterproofing was necessary, prior to any repairs.
The conciliated agreement failed to address the issue of waterproofing
The parties conciliated the dispute on 4 February 2016 and reached terms of
agreement. The terms of agreement did not address the issue of waterproofing.
The complainant has stated they had no knowledge of the requirement to waterproof
the affected walls. The financial firm has provided contrary evidence that the
complainant was aware of the need to waterproof the walls.
The terms of agreement do not address the significant aspect of waterproofing which
the financial firm states it required prior to undertaking repairs.
There is no evidence that the relevant wall needs rebuilding
The policy requires damage to the insured building by an insured event to apply the
policy terms, which includes rebuilding to current building standards.
The expert reports do not record any structural damage to the walls. As the structure
of the brick wall has no damage caused by the insured event, the policy does not
require the financial firm to either rebuild it or bring the wall itself up to current building
standards.
The financial firm is not responsible for the cost of waterproofing
The damage recorded to the walls was to the painted surface of the wall which the
financial firm has agreed to pay to clean and re-paint. The painting cannot be
undertaken until the masonry surface has adequately dried to ensure the paint finish
will be up to a workmanlike standard. It is accepted that if a waterproofing coat is not
applied to the wall then it will result in the paint peeling and flaking. The financial firm
is not liable for the waterproofing.
The financial firm must undertake the repairs as agreed
The complainant and the financial firm originally agreed that the financial firm would
undertake rather than cash settle the repairs.
The complainant should first complete the waterproofing works to the wall to ensure
the paintwork will not be negatively impacted by the moisture levels.
The financial firm should obtain new quotations for the work given the time which has
elapsed and then undertake the repairs.
Determination | Case number: 537421 Page 5 of 14
The complainant should also provide the documentation evidencing the returned
funds from the financial firm‟s prior attempt to cash settle. The complainant clearly
cannot retain these funds if the financial firm undertakes repairs directly.
Alternative ly, exclusively at the complainant‟s discretion, they may elect to cash settle
and the financial firm is to make payment to the complainant in accordance with the
updated repair quotations, less any amount previously paid.
The financial firm has agreed to cover additional items post-agreement
A review of the correspondence after the terms of agreement indicates that the
financial firm also agreed to perform additional works to the property.
As the terms of agreement do not appear to encompass all the agreed repairs, it is
appropriate for the financial firm to undertake all repairs it has previously agreed to.
This includes, but is not limited to, the additional works recorded in its email
correspondence dated 26 April 2016.
The complainant’s claim for con tents cannot be assessed
The complainant has raised a claim for contents but has failed to provide an itemised
list to AFCA with replacement costs for the items claimed. Given this, AFCA has no
ability to determine what items can be claimed under the polic y.
It is also noted that the complainant has a duty to mitigate her loss and should take
steps to protect her items from any damage.
2.2 What is the second issue?
AFCA may award compensation for non-financial loss
AFCA will only award compensation for non-financial loss where there has been an
unusual amount of physical inconvenience, time taken to resolve a situation, or
interference with the complainant‟s expectation of enjoyment or peace of mind. In
assessing whether to award compensation for non-financial loss, AFCA expects the
complainants to be moderately robust, bear the normal degree of inconvenience
experienced when a problem occurs, and take reasonable steps to minimise the
inconvenience suffered.
The complainant is entitled to compensation for non-financial loss
The financial firm engaged in a conciliation to resolve the dispute and within the terms
of agreement itself, failed to adequately communicate its requirements to undertake
repairs to the complainant. It then relied on the need to waterproof, which did not form
part of the agreement, to refuse to undertake the repairs. This has unduly extended
the time taken to resolve this dispute and required it to return to AFCA for a
determination.
Determination | Case number: 537421 Page 6 of 14
The delay has clearly had an impact on the complainant‟s peace of mind and
interfered with her enjoyment of the property which over two years later is still
unrepaired. After reviewing the course and conduct of the dispute, it is considered
appropriate to maintain the award for $2,000.
Determination | Case number: 537421 Page 7 of 14
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
a pplicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Relevant Policy Terms
Section 1 - Buildings and Contents
What is covered
We will cover your buildings and your contents for loss or damage from the events
listed below.
• Liquid that escapes from… a fixed pipe or something attached to a pipe, fixed
gutter, fixed tank or a drain
• Storm, rainwater, hail, or wind. This includes storm, rainwater, hail or wind
damage to gates, fences or walls that are entirely or partly at the situation.
We will not cover storm, rainwater, hail or wind damage:
– where water enters your buildings through an opening made for any building
renovation or repair work
– where water enters your buildings because of a structural defect, faulty design
or faulty workmanship when your buildings were constructed.
Determination | Case number: 537421 Page 8 of 14
(Contents)
• If you have insured your contents, we will pay for storage charges necessarily
and reasonably incurred to protect them from further loss or damage following a
claim by fire, storm or rainwater.
• If you are unable to live at your situation after loss or damage has occurred, we
will pay the reasonable costs to remove and store your contents while your
situation is being repaired. We will pay this for up to 12 months. We will also cover
your contents while they are in storage. We will only pay for this when you are
unable to live at your situation.
Additional things we will pay for when you have insured your buildings
We will pay the costs necessary to meet the requirements of any statutory
authority in connection with rebuilding or repairing the buildings at the situation…
The most we will pay in any one period of insurance is $25,000.
How we pay a claim for your buildings
When loss or damage occurs to your buildings, we will pay the cost of rebuilding
your buildings or repairing the damaged portions to the same condition as when
they were new.
We will also pay any additional costs required for your buildings to comply with
government or local authority bylaws. We will not pay these additional costs if you
were required to comply with these bylaws, and had not done so, before the loss
or damage occurred.
3.3 Relevant correspondence and chronology of events
Date Activity
16 - 07 - 2014 Assessment report obtained by insurer.
06 - 08 - 2014 Insurer‟s letter:
“As per the reported findings … and in line with the noted policy wording the
following portions of the claim have not been accepted:
Repairs to the storm water pipe that has caused the damage
Water proofing required at propert y
Drainage required at property
These work s are maintenance related and do not fall under one of the listed insured
events. … We recommend you engage a suitable tradesperson to attend to the
maintenance work required to prevent further damage as liability will not be
accepted for any future claims arising due to these issues not being addressed.”
Determination | Case number: 537421 Page 9 of 14
Date Activity
07 - 08 - 2014 Insurer‟s email to broker informing only accepting resultant damage accepted.
27 - 10 - 2014 Insurer‟s email to broker outlining its position following a phone convers ation:
There has been a leak in the stormwater which has led to some damage to the
property. The following aspects are not covered by the claim:
repairs to the storm water pipe/drainage that caused the damage
waterproofing which is required at the property
drainage which we have been advised is required at the property
the concrete path - subsidence of this area did not occur within 72 hours of the
leak ing storm water.
03 - 02 - 2016 Insurer‟s email to the complainant confirming the EFT transact ion completed and
enquiring if all furniture from rumpus room is removed to commence work.
Insurer‟s email to repairer:
enquiring if further damage has been identified
asking repairer to contact the complainant about when to commence works
providing update to complainant about moving forward wit h repairs.
04 - 02 - 2016 Conciliation call attended.
Complainant said:
downpipe has already been redirected and sort ed.
she will arrange for a concreter to rectify the footpath within 4 weeks. Terms of
agreement state the concret e path repairs to be completed are those identified
by Calliden during its assessment of claim HH xxxxxx 11.
Insurer said it will:
authorise repairs directly to the repairers and not offer cash settlements.
However, they would like the insured to rectify the issues regarding the downpipe
and the gap in the footpath.
authorise repairs ( as per quote xxx/ 1CC ) once concrete has been rectified.
authorise repairs ( as per quote 18138 ).
08 - 02 - 2016 Settlement terms issued to bot h parties.
Insurer email to complainant:
confirming its receipt of terms of agreement
JL sent complainant approval paperwork to discuss with repairer about when the
works can commence
PB has sent authority for her to complete and return to PB with policy excess
payment of $300
insurer believes these are the three main areas covered by the agreement and
all actions have been attended to as required by the insurer
insurer invit es complainant to contact it if repairer has not contacted her, as well
as if there are any unreasonable delays in getting the works underway.
08 - 02 - 2016 Insurer confirmed it provided authority to repairer per quote 1CC. Repairer claims
Determination | Case number: 537421 Page 10 of 14
Date Activity
it sent complainant approval paperwork for work to discuss/commence.
Builder claims it sent complainant documents on 03 - 02 - 2016 to be complet ed
and returned with $300 excess payment.
12 - 04 - 2016 Insurer moisture report obt ained.
18 - 04 - 2018 Insurer‟s claim notes indicate it authorised mould remediation works and flooring
replacement to commence.
26 - 04 - 2016 Insurer‟s email to complainant confirming insurer regularly updated on the
progress of works being attended to.
16 - 06 - 2016 Insurer‟s claim notes indicate complainant email enquiry to have bedroom carpet
assessed as part of wat er damage claim.
PB certificate of satisfaction signed by complainant: I/We hereby certify that the
reinstatement of damage situated at (address) has been carried out by PB to
my/our satisfaction…
27 - 06 - 2016 Insurer‟s claim notes indicate JL waiting for walls to dry before painting.
15 - 09 - 2016 Insurer ‟s claim notes indicate it emailed JL seeking update of walls drying out
and if complainant has done anything in this regard.
29 - 09 - 2016 Insurer‟s claim notes indicate JL plan to attend the natural drying of the wall,
anticipates not going well given the wet weather.
In response, insurer requests JL to enquire with complainant what they intend to
do with the external wall, if anything.
07 - 10 - 2016 JL still waiting for wall to dry before painting and replacing cupboards.
Next inspection due 05 - 10 - 2016.
10 - 10 - 2016 Insurer‟s claim notes indicate JL attended site, wall still damp, arranged R to
attend and take further readings to det ermine if it is decreasing since last report.
22 - 12 - 2016 Insurer‟s claim notes indicate JL advised best to wait until next year to finish the
job as moisture levels are still too high.
02 - 02 - 2017 Insurer‟s claim notes indicate updat ed report from JL received.
06 - 03 - 2017 Insurer obtained moisture report.
07 - 03 - 2017 JL email to insurer: on hold for nine months, awaiting moisture levels to drop.
Moisture report shows readings remain elevated.
Without some form of waterproofing the issue will exist at all times of the year.
JL are unable to carry out the works – suggests cash settlement per R report.
Determination | Case number: 537421 Page 11 of 14
Date Activity
08 - 03 - 2017 Insurer‟s email to J L: complainant rejects cash settlement offer.
Insurer requests further details about the recommended waterproofing.
11 - 04 - 2017 Insurer email re wat erproofing:
“ Can you please refer this back to JL to source a waterproofing contractor and
obtain a quot e pleas e as this will be the only way we can finalise this work s and
both close our files. Once I hear back I will tak e this to the insured and
advise/recommend that we will be arranging for the water proofing to be applied so
that the internal painting can be finish.”
19 - 04 - 2017 Insurer follow up to JL for waterproofing quote.
JL confirmed unsuccessful call to complainant made in attempt to attend to
complete quote this week.
27 - 04 - 2017 JL email to insurer confirming voice message left for complainant and await
return call to arrange inspection for next week hopefully.
11 - 05 - 2017 JL repairer report/quote obtained.
12 - 05 - 2017 Insurer email to complainant re waterproofing: not covered, i.e. maintenance
related work.
Insurer not willing to pay $30k+ for waterproofing.
Insurer suggests a cash settlement to settle the claim.
02 - 06 - 2017 Complainant email to insurer to commenc e (previously mentioned) repairs.
05 - 06 - 2017 Insurer seeking complainant‟s clarification about what works she refers to..
21 - 06 - 2017 Insurer follow up email to complainant for clarification.
03 - 07 - 2017 Complainant email to insurer seeking copy of original JL scope of works agreed
upon to be completed.
03 - 07 - 2017 Insurer‟s email to complainant providing copy of quote.
31 - 07 - 2017 Insurer claim notes state:
Due to no waterproofing of the external wall, internal wall will always contain level of
moisture. We have waited for 6 months and it remains the same so JL cannot finish
what they quoted - mainly painting and cupboards. I have a dvised insured that we
will cash settle the balance…
06 - 09 - 2017 Insurer update to complainant re no response regarding quote.
Insurer proposes cash settlement considering of length of time passed.
Determination | Case number: 537421 Page 12 of 14
Date Activity
16 - 10 - 2017 Complainant email to insurer demanding it to c omplete the work.
No works started or completed in the downstairs area since June/July 2014.
16 - 10 - 2017 Insurer email to complainant explaining the reason for settlement offer.
Insurer will raise payment in settlement of complaint.
16 - 10 - 2017 Complainant email to insurer rejecting cash settlement offer.
17 - 10 - 2017 Insurer acknowledging complainant‟s rejection of $8,000 payment but was
unable to cancel it through the system.
Insurer inviting refund of payment if complainant maintains settlemen t offer.
3.4 Reports relied upon
Report Key points
A ( insurer )
Assessment report
16 - 07 - 2014
Complainant‟s son identified section of concret e paving had subsided
considerably, dislodging from the original concret e paved section.
Discovery of water damage in adjacent rumpus room.
Identified disconnected downpipe/stormwat er connection allowing
stormwat er discharge into surrounding soil areas, and flowing with the
gradient of the concrete to the collapsed concrete path section.
Pungent musty odour apparent in ru mpus room.
Extensive efflorescent salt growth apparent and in line with the gradient
of the land against the external side of wall.
Salt growth presents as aged with extensive “y ellowing” apparent –
damage has been occurring for at least 2.5 months.
Simila r findings in the adjoining water closet.
Similar, but less severe, findings on the eastern wall.
Moisture readings show high to off the scale to all areas of salt growth.
Results consistent with rising damp.
Waterproofing member not installed to perimeter brickwork of the
rumpus room, and likely no drainage, at time of construction.
Disconnected downpipe was major contributing factor to the severity of
salt growt h and exceedingly high moisture content in brickwork.
Inspection of kitchen cabinetry located on east wall shows extensive and
severe deterioration of back panel, further indicating moisture
penetration has occurred for an extended period of time.
Garage pres ents with similar results (less severe than rumpus room);
disconnected downpipe as major contributing factor.
Absence of waterproofing to sub - terrain habitable rooms is not
uncommon for a home of this era.
External concrete path has subsided approximately 150mm.
Nil mesh reinforcement apparent below concre te paving.
Original concreted area also showing subsidence, and no sealant
Determination | Case number: 537421 Page 13 of 14
Report Key points
applied along the join to prevent surfac e water ent ry.
Repairs completed by previous owners apparent, suggesting moisture
has been present and ongoing for a long time.
Disconnected downpipe below conc rete level is not visually accessible.
All evidence shows excessive moisture is penetrating through rumpus
room east wall, originating from surrounding soils.
East rumpus room wall is exposed to far more water than any other
lower level area.
Below ground stormwater pipe disconnection has discharged large
volumes of water into surrounding soils, damaging walls and cabinetry.
internal damages to East and North walls and associated cabinetry
cannot be rectified until appropriate waterproofi ng membrane and
agricultural drainage is installed to all lower level perimeter walls below
ground level as a matter of general maintenance.
Internal walls will not dry and damages will invariably reoccur unless
these work s are undertak en.
All other remaining walls show minor to moderate efflorescent salt
growth, attributable to rising damp and abs ence of waterproofing
membrane and agricultural drainage.
Evidence of musty odour suggests microbial contamination is present in
rumpus room.
R (insurer)
M oisture report
12 - 04 - 2016
Property had plumbing fixed and new conc rete laid at side of dwelling.
High moisture level detected on wall adjac ent to external concret e area.
Mould growth identified in carpet underlay.
Carpet and toilet vanity deemed unsalvageable due to mould growth.
Heavy treatment of mould affected vanity completed onsite.
Toilet wall adjacent to stairs has high moisture reading.
Recommend removal of carpet and associated parts and install
dehumidifie rs and air movers for 5 - 7 days.
Unless appropriate drainage/waterproofing is in place moisture will
continue to migrate through external rumpus wall.
Heavy mould growt h present on underside of upstairs ens uite flooring.
Area required to be cont ained off.
Upstairs ens uite tested – ensuit e floor has sunk and has a bounce. All
trades to be provided safety precautions.
Structural drying and mould remediation required for upstairs ens uite.
Extensive scope of works listed for upstairs ensuite and bedroom –
inclu des removal, remediation and disposal of non - salvageable walls,
floors and finishes.
Builder should not commence work until post remediation verification
report is provided.
Photographs attached.
R (insurer)
Moisture report
Service provided on behalf of JL to undertake moisture readings to
bri ckwork: determine if levels increased since May 2016 and Oct 2016.
Moist walls remain elevated in moisture readings.
Determination | Case number: 537421 Page 14 of 14
Report Key points
06 - 03 - 2017 Walls will not dry due to the ground level outside being higher than the
basement walls.
Hydrostatic pressure forces the moisture from the ground to be pushed
through to the brick.
Mechanic al drying in the sub floor void will only be a temporary solution.
Structural design issue identified.
Recommend paint to be stripped fr om the brick, water - proofing to be
applied over the brickwork.
JL (insurer)
Repairer report
11 - 05 - 2017
Variation report requested due to no waterproofing of external wall.
Detailed required works listed.