Determination 536831

Insurer denied fire claim for non-disclosure of renovations and then cancelled and avoided the policy

FirmFinancial Firm (Unknown - Insurer)
Decided2019-07-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$55,231
Non-financial loss$1,500
Amount claimed$148,564
SourceAFCA PDF

Summary

Owners renovating their home claimed for a fire loss, and the insurer denied the claim for non-disclosure, then cancelled and avoided the policy. AFCA ordered the claim settled at a cash value of $55,230.96 with interest, removal of the cancellation and $1,500 non-financial loss, rejecting the water ingress claim and reducing the $115,841 scope substantially.

The insurer did not clearly explain the duty of disclosure as required by section 22, the renewal did not meet section 21B, and the insurer had no section 60 ground to cancel mid-term.

Issues

Subjects and remedies

home or building damagecorrect recordspay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 536831 Page 1 of 16 Determination Case number: 536831 10 May 2019 1 Determination overview 1.1 Complaint On 25 January 2018 the complainants’ house sustained damage following a fire. The insurer assessed the claim and denied it. In doing so, the insurer says:  the complainants failed to disclose the true condition of the house given the policy renewed several times since inception  misrepresented the true condition of the house at the May 2017 renewal The complainants disagree and say they disclosed the house renovations to the insurer at the inception call. Further, they were not required to contact the insurer until the constructio n work was completed pursuant to the insurer’s advice in that call. 1.2 Issues and key findings Can the insurer deny the claim due to non-disclosure or misrepresentation? No. The complainants had disclosed to the insurer that they were undertaking renovations at inception. A reasonable person in their circumstances would not have disclosed anything at renewal given the insurer’s advice and the fact the works had not been completed by that time. Can the insurer deny the claim based on policy exclusions? No. The insurer has not established that a policy exclusion applies. Therefore, the insurer is to settle the claim as set out in section 2.2 of this determination. Have the complainants suffered a loss due to the insurer’s actions? No. The exchanged information does not shows the water ingress was due to the insurer’s contractors actions. Is the insurer entitled to cancel the policy? No. The insurer did not have a right to cancel the policy. Determination | Case number: 536831 Page 2 of 16 Is the insurer liable for any compensation? Yes. The insurer has not handled the claim in a reasonable way and should pay $1,500 in non-financial loss. 1.3 Determination This determination is in favour of the complainants. The insurer is required to:  settle the complainants’ claim as set out in secti on 2.2 of this determination  remove the cancellation from the complainants’ claim history and any third parties to whom it has communicated the cancellation  pay the complainants $1,500 for the non-financial loss Determination | Case number: 536831 Page 3 of 16 2 Reasons for determination 2.1 Can the insurer deny the claim due to non-disclosure or misrepresentation? The insurer must clearly inform the complainants of their duty of disclosure When an insurer denies a claim on the basis an insured failed to comply with their duty of disclosure (non-disclosure), consideration must be given to section 22 of the Insurance Contracts Act 1984 (the Act). This section of the Act requires the insurer to show it clearly informed the insured of the nature and effect of the duty of disclosure, prior to entering into the co ntact of insurance. If the insurer fails to do so, then it is not entitled to rely on non-disclosure unless it was fraudulent. Further, the insurer must prove the following:  the complainants failed to comply with their duty – sections 21, 21A and 21B of the Act  the extent of the insurer’s prejudice by this failure – section 28 of the Act Under the Act, an insured has a duty to disclose to the insurer, before entering into a contract of insurance, every matter that the insured person knows (or a reasonable p erson in the circumstances could be expected to know) is relevant to the insurer’s decision whether to offer insurance. The insured is required to comply with their duty of disclosure prior to each renewal of their policy. Where the insured person fails to comply with the duty of disclosure, the insurer is entitled to reduce its liability for a claim under the policy to the amount for which it would have been liable, had the insured complied with their duty of disclosure. The insurer says the complainants have breached their duty of disclosure On 25 January 2018, the insured property was partially fire damaged. This occurred whilst the complainants were undertaking renovation works that commenced around 2011. The insurer says at inception the complainants described the property as a single storey, timber cladding with a tin/colourbond roof. Further, the complainants received the policy schedule at every subsequent renewal confirming the specifications of the property. Following its assessment of the fire eve nt, the insurer identified that the property is no longer single storey and mainly clad in timber. Instead, the policy was insuring a double storey, mainly clad in concrete building project that commenced from 2011. Determination | Case number: 536831 Page 4 of 16 The insurer says had it known the nature of the works to be undertaken , it would not have insured the property. On 5 March 2018, the insurer cancelled the policy effective 20 March 2018 due to the complainants’ non -disclosure. It then wrote to the complainants on 13 September 2018 avoiding the policy from 30 May 2017 on the basis the complainants misrepresented the condition of the property. The insurer argues, given E is an architect and her husband is a builder, the complainants were aware of the insurance requirements for a building site and that a domestic building insurance policy is not designed for this purpose. The insurer did not clearly inform the E of her duty of disclosure The insurer provided a copy of the inception call recording and the transcript of this call. For ease of reference, the panel will refer to the transcript. Relevantly the panel notes (Q47) the insurer’s representative says: So I just need to ask you some questions with doing the estimate. If you decide to buy the policy, we’ll use the answers you give now, to work out whether we can insure you and the terms of your insurance. The panel has carefully considered the inception call. The panel notes at no point throughout the call does the insurer advise the complainant of the nature and the effect of duty of disclosur e before the contract was entered into. The ‘effect’ should explain the potential consequences of a failure to comply with the duty. This would include the possibility of the claim being denied. The insurer provided a proof of dispatch for the inception policy documents. The schedule summarises the information the complainant disclosed to the insurer, including the property’s cladding and that it is a single storey. Both the schedule and the product disclosure statement (PDS) set out the duty of disclosure clearly. However, the panel is not satisfied the insurer clearly informed the female complainant of the general nature and effect of her duty of disclosure during this phone call. The Panel does not accept Q47 satisfies the requirements of section 22. This failure is not cured by explaining the duty of disclosure after the contract was entered into by provision of the insurance documents. E complied with her duty of disclosure Having reviewed the entire transcript, the panel notes:  A48: E says she was carry ing out renovations which includes adding a ‘big concrete wall around the house for insulation’ and ‘in the future we would put an extension on the top floor  A49: E confirmed at this point the property is still single storey Determination | Case number: 536831 Page 5 of 16  Q51 and Q52: the insurer says that when the complainants do the renovations or extensions, E ‘may need to call us to look at upgrading the value that you have the home insured for’ and ‘also if we need to change the building material for the external walls … we can do that for you at that time’  A56 and A57: E confirms the bathroom is under development at the moment  Q58: the insurer acknowledges the complainants are undertaking ‘some big renovations’  Q59: E confirms her husband is a licenced builder and he will carry out the work Having reviewed the initial call, even if the insurer clearly informed E of her duty of disclosure, the panel accepts E complied with her duty. She answered all of the questions honestly. She explained to the insurer that renovations were being undertaken, they were sizeable and she broadly described the extent of work being done. At this point, the insurer plainly had the opportunity to further assess this change in the risk by asking additional questions. Such as clarifying the details of the renovations, timeframe of completion, seeking copies of plans, documents or any other details relevant to its assessment. The insurer did not do so. As evident in the exchange, it was satisfied by E’s answers. The insurer then told her that she only needed to contact it after she does the renovations or extensions to maybe adjust the sum insured and updated the details about the external cladding. The insurer now says the nature of the complainants’ work is not a renovation but rather building a new house. The panel disagrees. There is an existing dwelling. The plans provided and approved by the council described the proposed works as ‘alterations and additions to existing dwelling’. It is clear that when the word ‘renovations’ is used, it often encompasses alterations and additions to an existing dwelling. Given this, the panel accepts E complied with her duty of disclosure as set out in section 21A(6) of the Act when answering the insurer’s questions. Further, and in the alternative, the panel considers it would be unfair in all the circumstances to conclude E failed to comply with her duty of disclosure for similar reasons. No non-disclosure or misrepresentation in the 2017 renewal The insurer says there is an onus on the complainants to review the schedule at inception and at each subsequent renewal and advise if their property had changed from what is described in the document. Section 21B of the Act sets out the duty of disclosur e when renewing an ‘eligible contract of insurance’. This policy would be an eligible contract of insurance given it Determination | Case number: 536831 Page 6 of 16 insures a building used for residential purposes and one of the insureds is a natural person. Subsection 3 is particularly relevant to this dispute and it says: Before the contract is renewed, the insurer may do either or both of the following things: (a) request the insured to answer one or more specific questions that are relevant to the decision of the insurer whether to accept the risk and, i f so, on what terms; (b) give the insured a copy of any matter previously disclosed by the insured in relation to the contract and request the insured: (i) to disclose to the insurer any change to that matter; or (ii) to inform the insurer that there is no change to that matter The 2017 renewal offer is a four page document. On the first page, the insurer says ‘Review the information on the following pages and if you need to make changes call …’ The following three pages contains a varying amount of information. This i ncludes the policy details, premium, details of home, the sum insured, key policy features, government charges, excesses, options chosen, calculation of the premium, insurance history, payment schedule and other information. It is plain that not all of thi s information was relevant to the insurer’s assessment of the risk. Further, neither the wording nor the document makes any effort to highlight to the complainants:  what specific information the insurer relied on in assessing the risk  what ‘matter previously disclosed’ were the complainants required to update. In addition, the wording makes no reference to the significance of reviewing the information or the consequences for failing to do so. It simply says for the complainants to call the insurer if it wants to make changes. This cannot be consistent with the requirements of section 21B(3). Subsection 4 says that if the insurer does not comply with subsection 3, then it is deemed to have waived compliance with the duty of disclosure. This is arguably applicable here. At the least, it is fair in all the circumstances that it is applicable given the concerns highlighted above. Determination | Case number: 536831 Page 7 of 16 Even if it is not, the panel does not accept the insurer’s position. The complainants disclosed the fact the property was being substantively renovated. In response, the insurer told the complainants they only needed to contact it after the works were completed to possibly adjust the sum insured and update the external cladding. Given this, the panel accepts a reasonable person in the position of the complainants would not have disclosed the change of the building until after the works were completed. Therefore, the panel does not accept the complainants failed to comply with their duty of disclosure when renewing the policy in 2017. For similar reasons, the panel does not accept the complainants misrepresented the state of the property. Even if the panel is incorrect on its findings under the Act, it would be unfair in all the circumstances to conclude the complainants misrepresented or breached their duty of disclosure for similar reasons. 2.2 Can the insurer deny the claim based on policy exclusions? Complainants have established a valid claim The complainants are required to show, on the balance of probabilities, they have suffered a loss caused by a risk insured against under the policy. This is known as a prima facie (valid) claim. If the complainants are able to establish a valid claim, the onus shifts to the insurer to show, on the balance of probabilities it is entitled to rely on an exclusion under the policy, or is otherwise entitled to deny the claim. The complainants’ policy provides cover for loss or damage caused by the events listed in the policy, including fire, subject to a number of conditions and exclusions. On 25 January 20 18, the property was damaged by a fire while A (E’s husband) was welding a steel post into a metal container. The panel accepts the complainants have established a valid claim under the policy. It follows, the insurer is required to establish its entitlement to deny the claim. Insurer is relying upon a number of policy provisions The insurer says the product disclosure statement (PDS) was updated in 2017. However, the insurer was unable to provide proof of dispatch of this version to the complainants. The insurer provided proof of dispatch for the 2011 PDS. This was dispatched successfully to the complainants at the time of the policy inception in 2013. The insurer seeks to rely on the terms and conditions of the 2011 PDS. Determination | Case number: 536831 Page 8 of 16 The panel will assess the claimed damage in light of both the 2011 and 2017 policies, bearing in mind the complainants were not clearly informed of the terms and conditions of the 2017 PDS. The insurer says the building on the property does not meet the policy definition of ‘home’. Both policies define home improvements as any permanent additions at your site which add to the cost of rebuilding or repairing your home such as a garage, inground pool and carport. Both policies define home as any enclosed building at your site that has walls and a roof and can be locked up. Further, both policies note:  under the insured event of ‘Storm’, damage is not covered when water enters the home through any tarpaulins or fixings installed whilst renovating or altering the home  under the insured event of ‘Accidental damage’, excluding damage caused by water entering the home through an opening made for alterations, additions, renovations or repairs  to review your sum insured after you extend or renovate the home  cover for building materials whilst you a re renovating or altering the home It is plain both policies provide coverage when the home is undergoing renovations or alterations. Further, both exclude damage when water enters the home through an opening caused by these works. In addition, there is no dispute the complainants were residing at the property and that part of the structure was enclosed with walls and a roof and can be locked up. Given all this, the panel does not accept the insurer’s argument that the structure is not covered by the policy under the definition of home and/or home improvements. The insurer is not entitled to rely on the policy exclusions The insurer seeks to rely on faulty workmanship and reasonable care exclusions outlined in Section 3 of this determination. The insurer a rgues the fire occurred due to A’s faulty workmanship in welding a steel pole to the roof of the shipping container inside the house where the insulation material ignited. The insurer says A did not ensure the combustible materials were removed from the area of work prior to the welding commencing. The insurer did not tender any evidence outlining the correct and safe welding procedure or the health and safety requirements for the building site. It is unclear what standards were applicable to A’s practice. Determination | Case number: 536831 Page 9 of 16 In the absence of this substantive information, the panel is not persuaded that A’s work was faulty or that he failed to take reasonable care. Parties are in dispute regarding the scope of works The complainants tendered a builder’s scope of works to reinstate the fire damage totalling $115,841. The insurer’s assessor PO does not consider the complainants’ quote to be fair and reasonable for the following reasons:  any builder’s scope of works will include the upgrading of the repairs to meet current building regulations  the policy excludes any additional cost to meet the building regulations which were already in place when the house was built  uninstalled building materials are capped at $1,000  complainants’ quote allows for engineering input; however, this should not be allowed for given the structure was not built to engineering standard PO estimated the cost of repairs as $33,449.46 after taking into account the observed damage and the complainants’ scope of works. The complainants highlighted this i s a large discrepancy from the insurer’s first builder who inspected the property and estimated the cost for repairs to be $98,175. A cash settlement should be based on PO’s estimate Based on the exchanged evidence, the extent of the loss is questionable. It is not in dispute the building design is unorthodox given the nature of the construction. The property is constructed using recycled second-hand materials to an extent. The complainants initiated the project in 2011 with an anticipation completion date 2021. A Development Application was provided and agreed to by the complainants on 15 April 2012. It appears following this, the works have commenced without any council inspections prior to the fire. Whilst this appears to be consistent with the requiremen ts of the council’s consent, it means there is no independent evidence to show that the works done from 2012 till the date of the fire are consistent with required building standards. The complainants say given their profession of being an architect and a builder, there should be no concerns regarding the compliance of the construction and the compliance issues (if any). The exchanged information though raises a number of questions regarding the building compliance with the Australian standards at the time of construction. Both 2011 and 2017 policies clearly and expressly exclude any cost to meet building regulations which were already in place when the home was built, renovated or altered. Further, the policies limits the unfitted building material to $1,000. Determination | Case number: 536831 Page 10 of 16 In addition, it appears there are aspects of the complainants’ quote that discusses water damage. This is presumably in reference to their claim for water entry they allege was due to the insurer’s make safe works. This is addressed later. I also note PO made the following points which the panel considers has merit:  he has provided estimates of rates and hours of contractors which the complainants’ quote does not do  there is a discrepancy in the complainants’ quote for the amount of roofing to be demolished (200 square metres) versus the amount to be replaced (120 square metres)  engineering requirements do not appear to have been met during renovations – it would be unreasonable for the insurer to pay for this in the repair cost Given this, the panel pre fers to rely on PO’s estimate of works as setting out a foundation to calculate a cash settlement. The panel does not consider the insurer’s first assessor’s estimate should be considered given it is not broken down. Insurer should settle the claim in this way When carefully reviewing PO’s adjustments, the panel considers a number of extra allowances should be factored. These are:  in calculating the relevant rate, PO sometimes refers to a range ($50 to $55 per square metre) but then applies the lowest – given the insurer is not proposing to do the works, the panel considers it fair to refer to the higher amount  PO noted the roofing required removal and replacement at 123 square metres but only allowed for 120 square metres  it is not clear why no allowance h as been made for ‘General Expenses’ as it does not appear they have been incurred (unlike the ‘Owners emergency expenses) – these should be allowed  the allowance for the ‘Building work’ appears to be $3,600 short – this appears to be due to PO’s omission to include the $3,600 labour allowed for under the ‘Builder and Carpenter’ subsection  PO reduced the amount for the spa from $1,600 to $800 based on a trade discount – given the insurer is cash settling the claim, the amount should be based on the complaina nts’ actual cost so the $1,600 is to remain Therefore, applying PO’s formula, his adjusted estimate is calculated as follows: Works Amount Uninstalled building materials $ 1,000 1. Repair & clean $ 400 2. Demolition work $ 1,600 Determination | Case number: 536831 Page 11 of 16 Works Amount 3. Roof demolition work $ 1,495 4. Owner Emergency repairs $ 0 5. General ex penses $ 5,070 6. Building works $25,920 Sub total $35,485 Builder’s margin 18% $ 6,387.30 GST 10% $ 3,548.50 TOTAL $45,420.80 Given the nature of the cash settlement transfers the risk to the complainants, and the fact it is not clear PO’s rates may be reflective of the local trades, the panel considers it is fair in all the circumstances that a 20% contingency be allowed. Therefore, taking this into consideration, and the $726 provided by the complainants’ electrician for make safe repairs, the insurer should pay the complainants the sum of $55,230.96. The insurer should also pay interest on this amount pursuant to section 57 of the Act. Interest is payable from the date the insurer first denied the claim until payment is made. The panel also notes that if the complainants are able to produce invoices for any of the emergency expenses that were excluded by PO, this should be added to the settlement. Interest is also payable on those amounts from the date the invoices were paid or the date the insurer first denied the claim, whichever is sooner, until payment is issued. 2.3 Have the complainants suffered a loss due to the insurer’s actions? The complainants say the insurer’s make safe repairs wer e inadequate During a telephone conciliation conducted by AFCA, the complainants say the initial make safe repairs by AJ were inadequate and as a result there has been water ingress damage at the property. The complainants tendered a builder’s quote totall ing $32,722.80. The complainants say water has entered through the roof in a number of areas. The complainants provided a chronology of events where they argue the insurer’s delays to respond caused further damage. Determination | Case number: 536831 Page 12 of 16 The insurers experts says defective gutter box caused water ingress The insurer engaged PO as well as a roofer (LG) and plumber (LP). All of the experts agree that the likely cause of water entry is the defective work associated with the box gutter. In his report LG says:  the gutter’s back ed ge is either level or lower than the front edge – this leads to a storm water breach back into the building  no flashing or seal between a roof sheet and top of gutter edge – water would be able to readily flow back into the building In addressing the causation of the water ingress and resultant damage, LP says second hand material has been utilised to construct the box gutter and roof of this property. LP also says the box gutter and roof do not comply with the Australian standards and codes. Further LP says water would certainly enter the building or has potential to allow water to enter and damage materials. LP outlined a number of entry points for the water ingress:  storm water pipe cut down the middle and been joined with a flash tape – this has started to separate and will likely cause a water leak  the roof sheets in some sections are short of the box gutter and during rain water would soak the cement render In response to the insurer experts’ reports, the complainants say:  there is no physical evidence showing the box gutter is discharging water into the kitchen  the insurer’s reports did not mention the exact building code which the complainants have breached The complainants provided a photograph of a damaged wall where they say this subject wall is four metres away from the box gutter. The insurer is not liable for the water ingress damage to the property The panel has carefully considered the information submitted by the parties and their subsequent arguments. The available expert evidence does no t support the cause of water entry to be the make safe works. They have highlighted various issues with the box gutter which appear plausible. The complainants have not provided any expert evidence to refute this. Therefore, the panel does not accept the c omplainants’ position that the water entry was due to the make safe repairs. Instead, the available evidence indicates the cause was due to issues with the box gutter. Determination | Case number: 536831 Page 13 of 16 2.4 Is the insurer entitled to cancel the policy as of 20 March 2018? Evidence does not show the insurer has a right to cancel the policy For the policy cancellation to be valid, the insurer must have a right to cancel the contract of insurance pursuant to one of the grounds set out in section 60 of the Act. The insurer sent a letter dated 5 March 2018 cancelling the policy effective 20 March 2018. The reason provided was because the property does not meet the underwriting guidelines. The Panel notes the underwriting guidelines are not one of the circumstances outlined by section 60. Whilst non-disclosure and misrepresentation can be grounds to cancel the policy, the panel does not accept these are substantiated. Therefore, the insurer has not established a right to cancel the policy mid-term. The panel also notes that the insurer purported to avoid the 2017 policy on the basis the complainants misrepresented the state of the property. An insurer cannot avoid a policy for misrepresentation unless it is fraudulent. No such allegation was made. Even if it was, it would be unsubstantiated given the panel was not satisfied a misrepresentation occurred. The insurer must amend its records Given this, the insurer’s purported cancellation of the policy is ineffective. Therefore, the insurer is to remove from its records, a nd the records of any organisation with whom it has communicated, any reference to the cancellation and avoidance. 2.5 Is the insurer liable for any compensation? The insurer has not reasonably handled the claim AFCA may award compensation for non-financial loss in circumstances where a person experiences an unusual degree of physical inconvenience, time taken or interference with an expectation of enjoyment or peace of mind. Compensation is awarded conservatively. The Panel notes the insurer:  unreasonably delayed the handling of the claim  changed the basis of its argument on several occasions  purported to avoid the policy when it had no entitlement to do so and without consideration of the significance this could hav e on the complainants’ insurance history Determination | Case number: 536831 Page 14 of 16  initially relied on an assessor’s opinion (TW) who was a qualified carpenter and therefore did not appear to have the insufficient qualifications to assess the quality of the complainants’ unusual renovations Given this, the panel ’s accepts the complainants have experienced an unusual degree of time taken and physical inconvenience . Therefore, the panel says it is fair in all the circumstances the insurer pays the complainants $1,500 compensation for non-financial loss. Determination | Case number: 536831 Page 15 of 16 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information exchanged. Because of the complexities involved in this dispute the matter has been referred to a panel for determination. In reaching this decision the panel has considered all the available information and has based this decision on what is fair in the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. 3.2 Key Terms Term 2011 PDS 2017 PDS Home is any enclosed building at your site that has walls and a roof and can be locked up which you use mainly for domestic purposes for Buildings Insuranc e, your home includes any home improvements or fixtures is any enclosed building at your site that has wa lls and a roof and can be locked up which you use mainly for domestic purpos es for Buildings Insuranc e, your home includes any home improvements or fixtures Home improvements are a ny permanent additions at your site that add to the cost of rebuilding or repairing your home, such as a garage, in - ground pool, above ground pool (when enclosed by are a ny permanent additions a t your site that add to the cost of rebuilding or repairing your home, such as a garage, in - ground pool, above ground pool (when enclosed Determination | Case number: 536831 Page 16 of 16 Term 2011 PDS 2017 PDS decking), carport, pontoon, boat jetty and permanent landscaping features. We do not consider soil or bushland to be home improvements. by decking), carport, pontoon, boat jetty and permanent landscaping features. We do not consider soil or bushland to b e home improvements. Maintaining and occupying your home We don't cover loss, damage, injury or death arising from:  faulty design or workmanship  you not maint aining your home in good repair and condition. This means your home must be watertight, structurally sound, secure and well maintained  you not taking reasonable care to protect your home or contents against loss or damage We don't cover loss, damage, injury or death arising from:  faulty design or workmanship  you not maint aining your home in good repair and condition. This means your home must be watertight, structurally sound, secure and well maintained  you not taking reasonable care to protect your home or contents against loss or damage Meeting building regulations Not covered costs to mee t building regulations:  that were already in place when your home was built, renovated or altered Not covered costs to meet building regulations:  that were already in place when your home was built, renovated or altered

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.