Cash settlement adequacy for leaking-pipe building damage and claimed loss of rent
Text of the determination
Determination | Case number: 535643 Page 1 of 11
Determination
Case number: 535643 3 April 2019
1 Determination overview
1.1 Complaint
In April 2014, the complainants lodged a claim under their home insurance policy for
cracking and movement damage to their home caused by water leaking from a
broken pipe in their main bathroom.
The insurer delayed repairs for over two years to allow the soil to dry out. During this
period, the kitchen waste pipe was also found to be leaking. In November 2016, the
insurer appointed a new engineer who recommended a further 12 month drying out
period.
The insurer has accepted liability for damage to the home caused by the leaking
pipes and has offered to cash settle the complainants for $60,400 (including $2,000
as compensation for non-financial loss). The insurer has also paid the complainants
$20,800 in temporary accommodation benefits.
The complainants are dissatisfied with the settlement offer as they consider it does
not fully compensate them for the losses they have suffered during the claim process.
In particular, the complainants seek payment for the loss of rental income from the
property during the lengthy period for which the repairs were delayed.
1.2 Issues and key findings
Is the insurer’s settlement offer for building repairs appropriate?
The cash settlement amount for the building repairs reflects the reasonable cost to
the complainants of repairing the damage to their property caused by the leaking
pipes. Accordingly, the insurer is not required to increase this amount.
Are the complainants entitled to further payment for loss of income?
While the insurer handled the claim poorly, it has paid the complainants temporary
accommodation benefits for the period during which their property was uninhabitable.
The insurer is not required to compensate the complainants for loss of rent during the
period while the property was able to be lived in.
Determination | Case number: 535643 Page 2 of 11
1.3 Determination
This determination is substantially in favour of the financial firm (insurer).
The insurer is required to pay the complainants the amount of $60,400 in full and final
settlement of their claim.
Determination | Case number: 535643 Page 3 of 11
2 Reasons for determination
2.1 Is the insurer’s offer of settlement appropriate ?
Claims process has been long and protracted
The complainants’ claim has been ongoing for a number of years. A brief summary of
the key events which occurred during the claim process is set out below. Further
details are provided in section 3.3 .
In April 2014, the complainants lodged a claim for cracking and movement damage
caused by a water leak. The pipe under the shower in the main bathroom had
separated from the shower riser, allowing water to leak under the house .
The insurer accepted the claim but delayed the repairs to the cracking and movement
damage on the advice of its engineer (MP), who recommended that a suitable period
be allowed for the soil to dry out.
The initial twelve month drying out period recommended by the insurer’s en gineer
(MP) was extended by another six months in April 2015 and a further six months in
November 2015. During this period, the complainants did not repair the leaking pipe
but used their en suite bathroom instead.
Prior to any repairs being carried out, a leaking sewer pipe was discovered under the
floor of the storeroom next to the main bathroom.
The insurer accepted that the second leak may have been related to the initial leak.
Accordingly, the insurer agreed to repair the sewer pipe and to cover any additional
damage to the home caused by the second leak.
In June 2016, the insurer’s engineer (MP) advised that the bulk of the cracking and
movement damage had been caused by seasonal earth movement, rather than by the
leaking pipes.
In response to the co mplainants’ concerns about MP’s advice , the insurer appointed a
second engineer (MB) to attend the property and report on the cause of the damage.
MB was critical of MP’s methodology and disagreed with his findings.
In summary, MB concluded that most of the cracking and movement damage to the
south side of the house had been caused by the leaking pipes.
After a further twelve month drying period which ended in November 2017, MB
prepared a scope of works for the repair of the claim-related damage. The insurer
obtained a quotation from its builder (UT) for the necessary repairs.
In response to the complainants’ concerns that UT’s quotation did not include all of
the damage caused by the leaking pipes, the insurer appointed MB to carry out a
further inspection.
Determination | Case number: 535643 Page 4 of 11
In May 2018, MB provided a detailed report outlining his conclusions as to the cause
of damage for each of the additional items raised, together with a revised scope of
works. The insurer’s builder (UT) provided a revised quotation of $41,716 for the
repairs.
Insurer has offered to cash settle claim for $60,400
As outlined above, the insurer has accepted liability for damage to the property
caused by the leaking pipes.
During the course of this complaint, the insurer offered to cash settle the claim for a
total of $60,400. This offer represented a significant increase from the initial offer of
$39,650 made in August 2018.
The insurer says the claim should be cash settled because its builder is unable to
guarantee the claim-related repairs due to pre-existing issues with the property
(including its ongoing susceptibility to naturally occurring earth movement).
The insurer’s cash settlement offer of $60,400 included:
the amount of $41,716 quoted by UT for the claim-related repairs
a builder’s margin of 19%
an additional allowance of 20% to allow for any unforeseen expenses
an amount of $2,000 as compensation for delays experienced during the claim.
Complainants consider offer for building repairs is appropriate
When the complainants initially lodged their complaint, they wanted the insurer to
carry out the repairs to the property. Among other things, the complainants were
concerned that:
the scope of works approved by the insurer did not include all of the damage to the
property caused by the leaking pipes, and
the settlement amount offered would not be sufficient to cover the costs to them of
engaging their own contractors to complete the repairs (and co-ordinating this
process).
As noted above, the insurer subsequently increased its offer to include a builder’s
margin of 19% and an additional allowance of 20%.
In response, the complainants confirmed that they considered the insurer’s revised
offer of $60,400 to be appropriate to cover the cost of repairs, as well as the
additional stress and inconvenience associated with arranging the repairs.
However, the complainants rejected the settlement offer because it did not include
any additional amount for loss of rental income.
Determination | Case number: 535643 Page 5 of 11
Settlement offer for building repairs is fair and reasonable
Having carefully reviewed the available information, the panel considers the insurer’s
settlement offer for the building repairs is fair and reasonable in the circumstances.
The panel accepts that it is appropriate for the claim to be cash settled, given the
evidence of pre-existing cracking and movement damage to the property.
As outlined above, the insurer’s engineer (MB) confirmed that the leaking pipes under
the bathroom and the storeroom floor had caused cracking and movement damage to
areas in the immediate vicinity.
However, MB also observed prior repairs to cracks in the lounge and dining rooms, as
well as additional damage in areas which were remote from the leaking pipes. While
the complainants said the scope of works should be expanded to include this
damage, MB concluded it had not been caused by the leaking pipes.
MB advised that the property will continue to be affected by long-term seasonal earth
movement, due to the manner in which it has been constructed (using non-articulated
brickwork on concrete strip footings) and the reactive clay foundation soils.
The panel is satisfied that the scope of works approved by the insurer generally
reflects the extent of the damage caused by the leaking pipes, which is confined to
the south side of the property (being the shaded area shown in the diagram included
in MB’s report s).
It is reasonable for the repair of the claim-related damage to include the cornices and
cracking to the reverse side of the affected walls.
However, the panel is not satisfied that all of the other items of damage identified by
the complainants were caused by the leaking pipes (for example, the sagging of the
store room ceiling and the cracking and movement in the master bedroom and front
entry).
T he complainants’ builder (OR) has confirmed that there was no further movement of
the underpins that had been installed in 2011. However, this does not of itself
establish that all of the current damage to other areas of the property was caused by
the leaking pipes.
The panel accepts the conclusion s of the insurer’s engineer (MB) regarding the cause
of damage to the disputed items. MB’s reports provided a detailed and logical
explanation of how the disputed damage occurred, which is consistent with the
observed facts.
The panel considers the quota tion provided by the insurer’s builder (UT) provides a
reasonable basis for the insurer’s cash settlement offer. The quotation was originally
provided in circumstances where it was envisaged that UT would undertake at least
some (if not all) of the repairs.
Based on the available information, the panel is satisfied that the location of the
property (75 kilometres from Adelaide) will not significantly increase the costs of the
repairs, given the nature of the works involved.
Determination | Case number: 535643 Page 6 of 11
Having regard to the factors outlined above, the panel considers that the additional
buffer of 20% (in addition to the builder’s margin) included in the settlement offer is
appropriate to provide for any extra costs the complainants may incur due to the claim
being cash settled. Such costs may include:
any minor items of claim-related damage which have not been included in the
scope of works (together with any other variations which may be required during
the course of the repairs)
the additional costs to the complainants of engaging their own contractors, in the
absence of the volume discounts and rebates available to the insurer
the fact that the complainants will not have the benefit of the life time guarantee
which would have applied under the policy, had the insurer carried out the repairs,
and
any increase in costs since UT ’s revised quotation was provided in May 2018.
Accordingly, the insurer is not required to increase the cash settlement offer for the
building repairs.
2.2 Are the complainants entitled to further payment for loss of income?
Insurer paid complainants temporary accommodation benefits for 12 months
The policy provides cover for temporary accommodation costs where the damage to
the property caused by an insured event is so extensive that the policyholder is
unable to live in it.
Under the terms of the policy, temporary accommodation costs are payable for the
time it takes to repair the property, up to a limit of twelve months from the date the
damage occurred.
The complainants remained living in the property after the leaking water pipe from the
bathroom shower was discovered in April 2014. The leak became apparent after the
complainants started using the main bathroom while undertaking renovations to their
en suite.
The claim notes reflect that the complainants rejected the insurer’s offer of a
temporary en suite and used the outdoor shower instead, until the renovations to the
en suite had been completed. They did not repair the leaking pipe in the main
bathroom but continued to use the en suite.
After the leaking sewer pipe was discovered in April 2016, the complainants moved
out of the property into an unoccupied property owned by their parents (the V
Property).
The complainants have continued to live in the V Property and have not returned to
their own property, even after the insurer repaired the sewer pipe in March 2017).
Determination | Case number: 535643 Page 7 of 11
The insurer has paid the complainants temporary accommodation benefits of
$20,800. This amount reflects their maximum entitlement under the policy, based on
the estimated market rental of $400 per week for the V Property.
Complainants seek additional payment for loss of income
The complainants say the amount paid by the insurer does not fully compensate them
for the loss of income they have suffered due to the delays experienced during the
claim process.
The complainants say the insurer and its contractors mishandled the claim during the
initial two year period (from April 2014 to 2016). Among other things, the
complainants say:
the insurer failed to act on the recommendations provided by its original engineer
(MP) to test all pipes at the property (to identify any further leaks) and to carry out
level surveys to provide a baseline against which to monitor future movement, and
the subsequent brickwork surveys undertaken by MP were inaccurate and his
inconsistent advice and recommendations for extended drying periods further
delayed the claim.
The complainants say that, as a result of the extended delay in resolving their claim,
they have lost an additional amount of approximately $40,000 in rent, due to their
inability to rent out the insured property (or the V Property).
While the policy limits the maximum amount payable for temporary accommodation,
this does not preclude the award of an additional amount for losses suffered as a
result of the insurer’s poor claims handling (rather than the insured event itself).
Poor claims handling contributed to delays
The insurer has acknowledged that it failed to act on MP’s recommendation to carry
out a full inspection of the pipes in April 2014. However, the effect of this failure is
unclear.
It is possible the leaking sewer pipe would have been discovered had further testing
been carried out at the time. However, it is also possible the leak did not occur until
later (given the bad smell which precipitated the discovery of the leak did not become
apparent until April 2016).
The panel also accepts that the advice provided by MP was i nconsistent and
inaccurate. A proper analysis of the damage caused by the leaking pipes was not
carried out until after MB was appointed in November 2016.
Given the nature of the damage, it is likely that an extended drying out period would
have been required before the internal repairs could commence. Nevertheless, the
panel considers the inadequate advice provided by MP has further delayed the
resolution of the claim.
Determination | Case number: 535643 Page 8 of 11
Complainants are not entitled to additional payment for loss of income
The panel is satisfied that the complainants have suffered additional stress and
inconvenience as a result of the manner in which the insurer handled the claim.
The insurer’s cash settlement offer of $60,400 includes an amount of $2,000 as
compensation for the non-financial loss suffered by the complainants. The panel
considers this amount is appropriate.
However, the panel is not satisfied that the complainants have suffered a loss of
rental income due to the delay in resolving their claim.
As outlined above, the complainants were living in the insured property as owner
occupiers when the damage occurred. There is no information to suggest they were
intending to sell or lease this property.
The complainants moved into the V Property when the insured property became
uninhabitable due to the broken sewer pipe. The sewer pipe carried kitchen waste,
which meant the kitchen could not be used until the pipe was repaired.
The insurer arranged for the sewer pipe to be repaired in March 2017, which meant
the property was once able to be lived in again from this date. The cracking and
movement damage caused by the leaking pipes was not such as would make the
property uninhabitable.
On this basis, the property was only uninhabitable from April 2016 until March 2017.
The insurer has paid the complainants temporary accommodation benefits for this
period (reflecting the market rent payable for the V Property).
Once the sewer pipe was repaired, the complainants could have moved back into the
insured property (which would have left the V Property available for rent). The insurer
is not liable for any loss of income which occurred as a result of the insured property
being left empty in circumstances where it was able to be lived in.
Accordingly, the insurer is not required to pay the complainants any additional amount
to compensate them for loss of income.
Determination | Case number: 535643 Page 9 of 11
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previ ously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Our approach to this complaint
This complaint has not been the subject of a recommendation. Due to the nature of
the complaint, it has been referred directly to a panel for determination, in line with the
Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this complaint based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.
3.3 Chronology of key events
Date Action
Determination | Case number: 535643 Page 10 of 11
Date Action
Late 2011 Complainants underpinned the area around the chimney at the front of the
property to address cracking and movement issues.
These works were undertaken on the advice of the complainant’s engineer
(SH) who concluded that the chimney footings were too small. No insurance
claim was lodged.
April /May 2014 Complainants lodged claim under home insurance policy for cracking and
movement damage caused by leak from pipe under shower in main
bathroom. Insurer accepted claim.
Insurer’s engineer (MP) recommended a t welve month drying out period,
testing of all pipes at the property and level surveys to provide a baseline for
monitoring of future movement.
May 2015 Insurer’s engineer (MP) re - attended property and carried out perimeter
brickwork level surveys.
MP advised the soil had not yet dried out and therefore the building had not
yet stabilised. He queried whether the leak was the cause of the damage and
recommended a further six month drying out period.
November 2015 Insurer’s engineer (MP) re - attended property an d carried out a further
perimeter brickwork level survey. He advised the building had not yet
stabilised from the potential influence of the bathroom leak.
MP considered the movement at the property was being caused by a number
of factors and recommended a further six month drying out period.
April 2016 Complainants notified insurer of bad smell. Insurer’s plumber (PP) identified a
broken sewer drain under the floor of the store room next to the main
bathroom.
Complainants moved out of home into an unoccu pied property owned by a
family member .
June 2016 Insurer’s engineer (MP) re - attended and carried out a furt her perimeter
brickwork level survey. He advised that there had been minimal additional
movement over the previous thirteen months.
MP concluded that the bulk of the cracking and movement damage had been
caused by naturally occurring eart h movement due to seasonal changes in
the moisture content of the surrounding soils (and not by the leaking pipes).
October 2016 The complainants ch allenged the findings in MP’s report that the bulk of the
damage to the property was caused by seasonal earth movement. They
provided a report from their builder (OR), stating that no additional movement
had occurred in the area which was underpinned in 20 11 prior to the leak
being discovered in 2014.
November 2016 The insurer appointed a second engineer (MB), who disagreed with MP’s
findings. MB carried out a floor level survey and confirmed that the leaking
pipes had caused cracking and movement damage t o the property.
M B prepared a scope of works which he considered should be completed as
‘a bare minimum’ to address this damage.
MB noted that there was ongoing dampness to the soil, even though the
property had been vacant for some time. He recommended a further drying
period be allowed before repairs commenc ed.
Determination | Case number: 535643 Page 11 of 11
Date Action
March 2017 The insurer’s plumber (PP) repaired the broken sewer drain.
November 2017 The insurer’s engineer (MB) re - attended the property and carried out a further
floor level survey.
MB conc luded that the movement caused by the leaks had stabilised and
therefore repairs could be carried out (although movement caused by the
long - term effects of seasonal variations in the moisture cont ent of the soil
would continue to occur).
MP prepared an upd ated scope of works for the repair of the cracking and
movement damage caused by the leaking pipes.
January 2018 The insurer’s builder (UT) prepared a scope of works and quotation of
$39,650 for the claim - related repairs, which excluded certain items of
damage. UT also advised that it was unable to warrant some of the repairs
due to pre - existing issues, including seasonal eart h movement.
March/April 2018 The insurer’s assessor (JL) and engineer (MB) carried out a further
assessment of the property, after the complainants raised concerns about
various items omitted from UT’s scope of works.
May 2018 The insurer’s engineer ( MB ) prepared a report setting out his conclusions as
to whether each of the additional items of damage raised by the complainants
had been caused by the leaking pipes.
MB provided an updated scope of works for the claim - related repairs,
reflecting his conclusions about the cause of the damage.
The insurer’s builder (UT) prepared an updated scope of works and quot ation
for $41,716 for th e claim - related repairs.
June /July 2018 Insurer paid complainants $20,800 for temporary accommodation benefits.
Insurer offered to complete claim - related repairs which could be guaranteed
by its builder and cash settle complainant for estimated cost of co mpleting
remaining claim - related repairs.
August 2018 Insurer provided revised offer to cash settle complainants for the estimated
cost of completing all the claim - related repairs ($36,650) .