Text of the determination
Determination | Case number: 534413 Page 1 of 11
Determination
Case number: 534413 15 March 2019
1 Determination overview
1.1 Complaint
The complainant previously lodged a claim with the financial firm (the insurer) for
storm damage to her property. That claim was the subject of FOS dispute 485504 in
which a final determination was issued. The determination found the insurer liable for
storm damage to the support post and any resultant damage.
A dispute has now arisen in relation to the correct repair method and the cost for
such. Specifically, the complainant says a gabion style retaining wall is required for
the repair of the claimed damage. However, the insurer says the policy excludes
retaining walls and soil.
The complainant also raises concern with the insurer‟s handling of the claim.
1.2 Issues and key findings
Is the insurer liable for the cost of the recommended retaining wall?
The construction of the gabion style retaining wall is fundamental to the proper repair
of the support post. The policy says the insurer will pay for the cost to repair the
property to „as new‟ condition when damage is sustained due to an insured event.
Given this, I accept in these circumstances the insurer should pay the complainant
the estimated cost to repair the support post as provided by her engineer (RA) and
quantity surveyor.
Is the insurer liable to compensate the complainant further?
The insurer is to compensate the complainant $2,500 for her non-financial loss as
well as the expert report fees she obtained from CF and RA.
Determination | Case number: 534413 Page 2 of 11
1.3 Determination
This determination is in favour of the complainant.
Within 21 days of being notified of the complainant‟s acceptance of this determination,
the insurer is to pay the following in full and final settlement of this dispute:
the sum of $147,895.51 minus any outstanding policy deductions (e.g. excess)
interest on the amount payable above pursuant to section 57 of the Insurance
Contracts Act 1984 (the Act) from 10 May 2018 until payment is made
$2,500 in non-financial loss
$1,083.50 for expert fees
Determination | Case number: 534413 Page 3 of 11
2 Reasons for determination
2.1 Is the insurer liable for the cost of the recommended retaining wall?
The complainant’s claim was the subject of an earlier FOS determination
The complainant previously lodged a dispute with the Financial Ombudsman Service
(FOS) about the insurer‟s decline of her claim for storm damage. The determination
found the complainant‟s property had been d amaged by a landslide from the claimed
storm event. The determination found the insurer liable for damage to the support
post and any resultant damage.
Following the determination, the parties disputed the extent of repairs necessary to
give effect to the previous determination. As a result, the complainant lodged a new
dispute challenging the insurer‟s decision.
The complainant provided reports showing a retaining wall is needed
The complainant‟s civil and structural engineer (RA), who initially identifi ed the
damage, provided recommendations for remedial works.
RA stated additional structural support, such as a soil retention structure, will be
required to prevent future erosion of the damaged footing. This recommendation was
in addition to the reinstatement of a retaining wall that was previously on the site.
The complainant also provided a report from a geotechnical engineer (CF) who had
been instructed to:
carry out the geotechnical investigation and provide options for rehabilitation of the
damage, to reinstate lateral support to the affected footing of the dwelling.
CF provided two options for the “remediation of the lateral support to the corner
footing”. The options are as follows:
1. a gabion-style reinforced earth fill retaining wall; or
2. a panel and post-style retaining wall.
On this basis the complainant provided the insurer with a summary of works and cost
estimate for remediation using the gabion-style retaining wall method. The cost
estimate provided by quantity surveyors came to $147,895.51.
Determination | Case number: 534413 Page 4 of 11
The insurer says most of the cost relates to things that are excluded from cover
The insurer refused to accept the complainant‟s cost for repairs as it says the majority
of the works are associated with the installation of a retaining wall syste m and soil
restoration. These are excluded from cover under the policy. The insurer also says
this was noted in the determination of the complainant‟s earlier dispute with FOS.
The policy states it does not cover „garden retaining walls‟ or „soil‟ under h ome
insurance. Garden retaining walls are also specifically excluded under the insured
event of „storm‟.
The policy defines „garden retaining wall‟ as:
a wall, which is not part of the residential building, designed to hold back or prevent the
movement of earth.
The complainant says she is not claiming for a damaged garden retaining wall
The determination in the complainant‟s earlier dispute said, “the applicant accepts
that the replacement of the lost earth and the failure of the retaining wall are not
co vered”. The complainant says this related to her garden soil and garden retaining
wall that was there before the storm, not the repairs necessary for the successful
remediation of the covered storm damage.
The complainant does not dispute the exclusion of the garden retaining wall and says
she is not claiming for the damage to, or replacement of, that garden retaining wall.
The complainant says the proposed retaining structure is the prescribed remediation
solution required to stabilise the footing as recommended by two engineers. The
complainant says the proposed retaining wall is an “integral and critical component of
the footings of the affected pole”.
The complainant draws a distinction between the garden retaining wall that was
damaged by the landslide and a retaining structure required to support and repair the
damaged footings of the house following the landslide. The complainant says the
recommended support structure is a „surcharged‟ wall which does not fall within the
definition of „garden retaining wall‟ because it supports more than soil, it supports the
surcharged load of the insured building.
Complainant’s experts say retaining wall is part of the repair cost to post
CF‟s report states the two retaining wall options are “concepts for remediati on of the
lateral support of the corner footing”. This supports the complainant‟s position that it is
a critical element of the repair costs to the support post following the landslide. RA
also confirms that
Determination | Case number: 534413 Page 5 of 11
The retaining structure, recommended by [CF], the Geotechnical Engineers, is an
essential component of the rectification work required to stabilise the foundations of the
dwelling.
The policy is clear in that it excludes damage to garden retaining walls. However, this
is not the issue. The damage being claimed under the policy is to the support post.
This was caused by the landslide that significantly impacted this area of the property.
There is no dispute the support post is covered by the policy. In such circumstances,
the policy says the insurer is required to pay the cost to repair the support post.
In this context, the complainant‟s submissions are persuasive as the reports show the
construction of the proposed retaining wall forms a fundamental part of the repair
process and is distinct from the previous retaining wall.
Insurer’s engineer (NJ) also says repairs require a retaining wall
The insurer says its engineer (NJ) has confirmed repairs can be carried out without a
retaining wall.
NJ provided a report on 8 June 2018. In this report, NJ provided recommendations for
rectification of the damaged footing. NJ states:
we recommend reconstructing the footing founded to competent natural ground and
installing a new pole suitably fixed to the existing floor framing…It also includes the
implementation of anchor ties between the subject footing and adjacent footings in two
perpendicular directions to limit lateral movement to this footing in the future.
NJ also states its rectification works are not based on the construction of a gabion
style retaining wall, but it says notwithstanding this:
a suitable engineer designed retaining wall should be reinstated in conjunction with the
works specified by this office.
NJ then went on to say:
it would be prudent for the building owners to obtain a slope stability assessment report
and implement any recommendations made in the report.
When reading this, I do not agree NJ says the repairs can be conducted without a
retaining wall. In fact, NJ says the opposite. This is further reinforced when the insurer
quoted NJ‟s comments in its letter of 4 September 2018 where NJ states:
While not recommended, technically if the required surface levels can be achieved without
the retaining wall in place, the footing could be constructed first, however the timeframe
between this and retaining wall construction would need to be limited to commence as
soon as practically possible after footing construction.
If the footing is constructed and left for some time without stabilisation of the slope via a
retaining wall or other means then it leaves the footing at increased risk of movement
occurring.
Determination | Case number: 534413 Page 6 of 11
NJ‟s above statement confirms the proper repair of the post is conditional on the
prompt construction of a retaining structure. Significantly, NJ also stated:
It was specifically recommended in our report conclusions and recommendations that a
retaining wall be constructed and the slope stability assessed. We only highlighted the fact
that a gabion style retaining wall was not specifically required.
The insurer provided a further submission dated 15 October 2018 where NJ outlines
the minimum retaining support required. NJ stated:
any low height retaining wall constructed to facilitate the construction of the new pole
footing would be generally at risk of failure (similar risk to wall that failed). If such a wall
was built, it would need to be clearly understood that the wall was a temporary
construction wall (to aid construction).
Not only does this statement confirm a retaining wall is required for the construction of
the new pole footing, but it supports CF and RA‟s proposed repair method of an
additional support structure separate and distinct to the garden retaining wall.
It also supports the finding that the requirement of this retaining wall was due to the
landslide that occurred.
The insurer says the complainant would receive a betterment
The insurer says the complainant‟s property had pre-existing stabilisation issues and
she is looking for the cost of site stabilisation to be covered. The insurer says a four-
meter retaining wall was not present before the loss. Therefore, the insurer says that
if it is required to cover all these costs, it will place the complainant in a significantly
better position.
I disagree.
The evidence clearly shows that without the proposed retaining wall, the
complainant‟s property is in a substantively worse position than prior to the loss.
The purpose of the policy is to indemnify the complainant for loss or damage caused
by an insured event. I am satisfied the current information shows the site is unstable
due to the significant landslide that occurred. Therefore, if the insurer was to exclude
the cost of the retaining wall, it would result in an outcome:
contrary to the purpose of the policy
inconsistent with the policy which says the insurer will repair the property to the
same standard, specification or quality as it was when it was new, and
unfair in all the circumstances.
There is no evidence to show the site had previous stabilisation issues. The
complainant notes the property was constructed in 1993 and had no previous issues
prior to the landslide that occurred about 24 years later.
Determination | Case number: 534413 Page 7 of 11
Even if it is arguable that the retaining wall is betterment, the policy does not exclude
this if it is necessary to the repair cost of insured damage.
Gabion style retaining wall to be included in the scope of works
The insurer has said that if a retaining wall is required, the previously damaged one
should be reinstated. This is based on RA‟s previous report as well as a report
provided by the insurer‟s engineer (JH) that was first engaged.
The current evidence shows this is not an option. Reports from RA and JH preceded
CF‟s report. Following CF‟s report and analysis, both RA and NJ agree that the
reconstruction of the previous retaining wall would be inadequate. NJ, as quoted in
the insurer‟s submission dated 15 October 2018, said:
The minimum retaining wall that would allow the footing re-construction would be a similar
retaining wall to that was previously present. … If such a wall was built, it would need to
be clearly understood that the wall was a temporary construction wall (to aid construction),
with a wall designed to stabilise the overall slope required to be built in front of the
temporary wall as soon as possible
The report from CF provided two different support structures, a gabion style
reinforced earth fill retaining wall and a panel and post style retaining wall.
CF provided a qualitative comparison of the two options. CF stated:
It is our opinion that the panel and post retaining system is more appropriate for this site,
given the lesser temporary works disturbance.
RA disagreed and advised the gabion style wall is preferred for the following reasons:
comparable construction costs
a four-meter panel and post wall will require council approval – this will likely delay
the process, particularly given at least one neighbour is likely to object
ease of access and construction
is amenable to landscaping and would not have a negative impact on the
property‟s value .
CF, in a letter dated 3 October 2018, acknowledged RA‟s opinion and provided no
objection. CF simply stated that works should commence as soon as possible.
NJ does not state a preference about which option should be used. NJ suggests there
may be a cost saving for a panel and post wall but is uncertain. NJ also does not
comment on RA‟s concern that a panel and post wall would require an application to
Council and give rise to a possible objection from neighbours.
Given this, I accept RA‟s recommendation to be reasonable. The works should
proceed with a gabion style retaining wall.
Determination | Case number: 534413 Page 8 of 11
Insurer is to pay the complainant the cost estimate from the quantity surveyor
The complainant provided a summary of works from RA as well as a cost estimate
from a quantity surveyor based on these works. The cost estimate totalled
$147,895.51.
The insurer has objected to this noting that the summary of works is not a detailed
scope and contains no plans or drawings. Further, the cost estimate is provided by a
quantity surveyor who specialises in tax related work and cost estimates.
However, the insurer has not provided any costing for the full repairs. NJ‟s rep ort and
the quote from its builder is inadequate as it does not account for the construction of a
retaining wall or any other works necessary.
Therefore, based on the available information, it is only the complainant‟s documents
that sets out the cost to restore the property to its pre-incident condition. Further, I
consider the estimate to be reliable given:
it is based on RA‟s recommendation who is well familiar with the site
RA is a qualified civil and structural engineer
a quantity surveyor is appropriately qualified to estimate the costs of construction
given this is their field of expertise
The previous determination provided the insurer with the option to either repair the
damage or cash settle the complainant. However, I do not consider it is fair in all the
circumstances that this remains given:
this claim has been the subject of a second determination
the property has been at risk of further structural damage for a long period of time
there should be finality to this dispute given the history of this claim
Therefore, it is my opinion that it is fair in all the circumstances that this claim be
resolved by the insurer paying the complainant the sum of $147,895.51 minus any
policy deductions owing (e.g. excess). The insurer is also to pay interest on the
amount payable pursuant to section 57 of the Insurance Contracts Act 1984 . Interest
is payable from 10 May 2017, being two weeks after the insurer received this
estimate, until payment is made.
2.2 Is the insurer liable to compensate the complainant further?
The complainant says the insurer has caused unreasonable delays
Under 9.3 of FOS Terms of Reference (TOR), compensation for non-financial loss
may be awarded in certain limited circumstances. That includes for situations where
there has been an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the complainant‟s expectation of enjoyment
or peace of mind.
Determination | Case number: 534413 Page 9 of 11
The complainant says from the date of the claimed event throughout the entire claims
proces s and two disputes, the insurer‟s conduct has caused her an extreme level of
stress and impacted her life greatly.
The complainant says she has suffered loss of income, her health has suffered as a
result of the stress and the insurer‟s delay in handling the matter appropriately has
caused further instability and damage to the site itself.
Throughout both disputes the engineers and builders involved have advised that it is
imperative to remediate the damage as soon as possible to prevent any further
landslip and damage to the house. The complainant has clearly attempted to do so
having to engage engineers and builders to report on the damage and authorising
make safe works. In addition, she has spent time during wet days trying to clear the
site of water.
T herefore, the insurer‟s decisions to first deny the claim and then attempt to offer a
substantively reduced settlement would have significantly impacted her. Particularly
given she was required to successfully challenge both decisions after providing
numerous expert evidence and submissions in support.
Further, the complainant was reasonably entitled to expect the insurer to attend to her
claim with a manner of urgency and in a professional and reliable manner. Although
there were matters which required action by the complainant herself, she still had the
avoidable additional upset and concern caused by the insurer‟s handling of her claim
and appearance that it was not taking the risk of further damage seriously.
Therefore, given all this, it is fair in the circumstances that the insurer pays the
complainant $2,500 as compensation for this.
The insurer is to reimburse the complainant for the remaining invoices
Under 9.4 of FOS TOR an insurer may be liable for the complainant‟s costs in
pursuing the matter.
The complainant has provided further invoices for expert reports that have not yet
been reimbursed by the insurer. That is, the report from CF of 3 October 2018
($577.50) and the email and report from RA dated 25 June 2018 and 21 September
2018 ($506). I accept these reports assisted her position and were relevant to the
issues in dispute. The insurer is to reimburse the complainant for these costs.
Determination | Case number: 534413 Page 10 of 11
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
3.2 Relevant terms of the policy
Product disclosure statement
Page Key points
Definitions
Page 3
garden retaining wall - a wall, which is not part of the
residential building, designed to hold back or prevent the
movement of earth.
Insured event
Storm and rainwater
We will not cover
Page 10
loss or damage to :
o fences and gates that are not structurally sound or
well maintained
o artificial grass or turf
o garden retaining walls
How We Settle Claims
Page 36
If we agree to pay a claim for loss, theft or damage to your
home, contents or personal effects, we will decide whether to:
repair the damaged property to the same standard,
specification or quality as it was when it was new, or
replace the damaged property with the nearest equival ent
property available, or
pay you the amount it would cost us to repair or replace
the property to “as new” condition.
Determination | Case number: 534413 Page 11 of 11
3.3 Expert reports
Report Key points
Geotechnical Investigation
(CF)
26 March 2018
to carry out the geotechnical investigation and provide
options for rehabilitation of the damage, to reinstate
lateral support to the affected footing of the dwelling
we provide two concepts for remediation of the lateral
support to the corner footing
a gabion style reinforced earth fill retaining wall and a
panel and post style retaining wall
surcharge loads were incorporated, the point load from
the corner footing, uniformly distributed load, ground
water loads
the panel and post retention option will have the benefit
of the lesser need for temporary excavations and
affecting existing footings
qualitative comparison – it is our opinion the panel and
post retaining system is more appropriate for this site,
given the lesser temporary works disturbance.
Consul ting engineers (NJ)
8 June 2018
to provid e recommendations for rectification of the pier
footing
significant soil loss occurred adjacent to the pier footing
of the timber pole at the deck‟s rear left corner
we recommend reconstructing the footing founded to
competent natural ground and installin g a new pole
suitably fixe d to the existing floor framing
It also includes the implementation of anchor ties
between the subject footing and adjacent footings in
two perpendicular directions to limit lateral movement to
this footing in the future.
the rect ification works specified by this office are not
based on the construction of a gabion retaining wall to
ensure future stability of the footing system
notwithstanding this fact it is evident due to the failure
of the retaining wall that it was not sufficie nt to cater for
the loading conditions present and a suitable engineer
designed retaining wall should be reinstated in
conjunction with the works specified by this office.
RA supplementary report
21 September 2018
the retaining structure recommended by CF the
geotechnical engineers is an essential component of
the rectification work required to stabilise the
foundations of the dwelling
the construction of the retaining wall should be
expedited without further delay. With the onset of the
wet season, expe cted between Dec & April 2019 and
the precarious situation of the house as it is now.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.