Home / Financial Firm (Unknown - Insurer) / Determination 532525
Determination 532525
Claim for stolen blocks and cost to demolish and rebuild wall denied
Summary
The complainant claimed $13,608.38 for demolishing and rebuilding a partly built wall after 100 blocks were stolen from its construction site. AFCA found no physical damage to the wall and that the claimed loss was excluded consequential loss.
The wall was not physically damaged, and the rebuild cost is consequential loss from the theft, which the policy clearly excludes.
Issues
- Claim denial primary · not upheld“The complainant has not established a prima facie claim, and the insurer is entitled to deny the claim.”
- Product terms interpretation secondary · not upheld“I am satisfied the policy terms are clear and unambiguous... the insurer is not liable for consequential loss.”
Subjects and remedies
no remedy
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case number: 532525 21 February 2019
1 Determination overview
1.1 Complaint
The complainant lodged a claim with the financial firm (insurer) for 100 stolen blocks
from a construction site.
The insurer accepted the theft occurred but denied the claim because there was no
physical loss or damage to the partly built existing wall. Further, it relied on policy
exclusions regarding consequential loss and undiscovered theft.
The complainant disagrees with the insurer’s decision and seeks the insurer
indemnify it for the costs of demolishing and rebuilding the wall.
The case analyst provided the parties with a recommendation on the issues in
dispute. The recommendation was in favour of the insurer.
As the complainant did not accept the recommendation, the complaint has been
referred to me for determination .
1.2 Issues and key findings
Is the insurer entitled to deny the claim?
The available information establishes on the balance of probabilities there has been
no physical loss or damage to the blocks which were not stolen and no physical loss
or damage to the partly built wall. While the concrete works include the wall, the wall
has not been damaged. As the complainant has not established a prima facie claim,
the insurer is entitled to deny the claim.
Further, the insurer is not liable for any losses consequent upon the insured loss,
being the theft of 100 blocks. As consequential loss is excluded under the policy, the
insurer is also entitled to rely on this policy exclusion to deny the claim.
Determination | Case number: 532525 Page 2 of 7
1.3 Determination
This determination is in favour of the insurer.
The insurer is entitled to deny the complainant’s claim and is not required to take any
further action in relation to the complaint or the claim.
Determination | Case number: 532525 Page 3 of 7
2 Reasons for determination
I have decided this case on its merits, having regard to the relevant law, good industry
practice, codes of practice and previous decisions. I have considered all the material
submitted by the parties, both before and after the recommendation. I am satisfied the
documentation I have relied on has been provided to both parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
The complainant is represented. Reference in this determination to the complainant
includes reference to the complainant’s representative.
No new material provided after the recommendation
After the recommendation was rejected, the complainant made further submissions in
which it essentially reiterated its position. No new material was provided.
2.1 Is the insurer entitled to deny the claim?
Complainant must establish a prima facie or valid claim
The complainant must establish on the balance of probabilities it has suffered a loss
caused by an event to which the policy responds. This is known as a valid or prima
facie claim.
Once so established, the onus shifts to the insurer to prove on the balance of
probabilities an exclusion applies if it seeks to deny or limit its liability for the loss.
The complainant’s claim
The complainant claims $13,608.38 as set out in the claim form. This is said to be the
cost of demolishing a partly constructed wall and supply of new blocks.
The available material establishes 516 blocks were delivered to the complainant on
14 August 2017. In the claim form, the complainant says:
the blocks were delivered to a secure site, so it could construct three feature walls
and a column
it was not until it started to build the structures on or about 29 January 2018, that it
realised some of the blocks had been stolen
516 blocks were ordered and delivered, and it estimated 100 blocks were stolen
it did not have enough blocks to finish the wall because it could not obtain more
blocks in the same colour
to complete the wall, it must demolish the wall and order a new batch of blocks.
Determination | Case number: 532525 Page 4 of 7
The insurer’s submissions
The insurer does not dispute 100 blocks were stolen. However, it argues the policy
does not respond. The insurer says:
the insuring clause has not been triggered as there is no physical loss, destruction
or damage to the wall as per the policy definition of damage
there is no cover for the cost to demolish and rebuild the partially built (but
undamaged) wall when the wall cannot be completed due to the lack of matching
blocks
the policy does not respond to the cost of replacing blocks because others of t he
same colour are not available
the inability to complete the wall is a consequence of the theft
the policy terms exclude consequential loss
the loss was not discovered until about five months after delivery of the blocks
undiscovered theft is also excluded under the policy
while the stolen blocks are covered because this is a physical loss, the cost to
replace the 100 stolen blocks ($509) falls under the applicable policy excess
($1,000) and so there is no claim under the policy.
The complainant’s s ubmissions
The complainant contends:
the theft of the blocks (building materials) is a sudden physical loss of building
materials and so the claim falls under the definition of damage in the policy
the contract works (which include the wall) have been damaged by the theft of the
blocks because the partly built wall cannot be completed as the matching blocks
are not available
to complete the contract works, the wall must be demolished and rebuilt
the theft is to an item specified in the contract, so the theft is not consequential loss
it is not sufficient to merely state consequential losses are excluded, the categories
of loss must be expressly defined
a proper analysis of the consequential loss exclusion means the claim cannot be
denied
it is moot to rely on the undiscovered theft exclusion because if the stolen blocks
had been above the excess the insurer would have covered the difference
it was only when the matter came to AFCA, the insurer denied the claim relying on
both policy exclusions.
Complainant has not established a prima facie or valid claim
The policy provides cover for material damage. The insurer will indemnify the
complainant for damage to the insured contract works from any cause not excluded,
occurring at the contract site during the construction period.
Determination | Case number: 532525 Page 5 of 7
It is not in dispute there was theft of 100 blocks from the contract site during the
construction period.
The insurer does not dispute the theft of the blocks is a physical loss and the policy
responds to the claim for 100 stolen blocks. However, this admission is not
determinative of the outcome. This is because the dispute relates to the cost to
replace all blocks required to rebuild the wall and the cost of demolishing the wall, so
the wall can be rebuilt.
There has been no physical loss or damage to the blocks which were not stolen.
There has been no physical loss or damage to the partly built wall. In the
circumstances, I do not accept there has been damage to the contract works. I accept
the concrete works include the wall, but the wall has not been damaged.
I am not satisfied the complainant has established a prima facie claim.
Insurer is not liable for consequential loss
Even if I were to accept a valid claim exists, the policy says the insurer shall not be
liable for consequential loss.
The complainant argues a proper analysis of the consequential loss exclusion and
case law means the insurer cannot rely on this policy exclusion.
However, I am satisfied the policy terms are clear and unambiguous. The insurer is
not liable for several losses including consequential loss.
In other words, the insurer is not liable for any losses consequent upon the insured
loss. The insured loss was the theft of the 100 blocks. Because of the theft, the
complainant had to replace the 100 blocks to complete the wall. The complainant
could replace the 100 stolen blocks, but they would not match the blocks in the partly
completed wall.
In consequence of the theft and inability to simply replace the 100 stolen blocks, the
complainant is required to dismantle the wall and buy new blocks to rebuild the wall.
Insurer is entitled to deny the claim
I am satisfied this claimed loss is sustained because of the theft of the 100 blocks. I
am satisfied the claimed loss is consequential loss. As consequential loss is clearly
excluded from the cover, the i nsurer is entitled to deny the claim.
Application of the other policy exclusion is not determinative of the outcome
The insurer also says it is entitled to deny the claim because it shall not be liable for
undiscovered theft. The policy says the insurer shall not be liable for damage
discovered only at the time an inventory is taken.
Determination | Case number: 532525 Page 6 of 7
The complainant says the insurer cannot rely on this exclusion as it only raised this
exclusion when the complaint came to AFCA. However, the insurer relied on this
policy term in its final decision letter.
It is not in dispute the theft was discovered some several months after the blocks
were delivered to the complainant. However, on my analysis of the policy response,
this policy exclusion is applicable to the theft of the 100 blocks only. And as the policy
deductible is greater than the cost to replace the 100 stolen blocks, the application of
this policy exclusion is not relevant to the outcome of the claim which is to replace all
the blocks, demolish the wall and rebuild the wall.
Determination | Case number: 532525 Page 7 of 7
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Our Approach
It is an accepted principle of general insurance law that the insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.3 Relevant policy extracts
The relevant policy extracts are referred to in the correspondence between the
parties, the parties’ submissions and in the insurer’s Notice of Response dated 10
July 2018. Both the policy document and the Notice have been exchanged with the
complainant.
3.4 Other relevant material considered and relied on
parties’ submissions and emails both before and after the recommendation
correspondence between the parties
claim form, photographs, correspondence between the complainant and the
supplier of the blocks
policy schedule.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.