1 Determination overview
1.1 Complaint
This dispute concerns claims made by the complainant that her financial firm
(insurer), via its loss adjuster (C) and contractors, failed to identify, report, manage
and remove asbestos containing material (ACM) from her house following a storm
event in December 2016.
While the insurer has paid for the storm related damages, the complainant says it is
responsible to pay for the removal of the ACM, contents replacement, and
consequential / non-financial loss. On advice from an A Class asbestos removalist,
the complainant and her family have not lived at the house since October 2017.
1.2 Issues and key findings
Is the insurer entitled to deny the claim for asbestos removal?
The panel is satisfied there was systemic mismanagement of the ACM risk from the
outset, and the insurer should remove all the ACM from the house and pay for
subsequent cleaning and testing.
Is the insurer liable to pay the complainant’s sum insured for contents?
The complainant has not currently proved this loss has occurred. Testing is needed to
confirm levels of contamination on contents. The insurer s hould provide three testing
company options to the complainant. The test results should be considered when
deciding what this settlement, if any, would consist of.
Is the insurer bound to issue letters, apologise and conduct investigations?
AFCA is not an insurance regulator. We do not have the power to review a general
practice unless the practice breaches a specific duty or obligation, or it is not
consistent with industry practice. However, the Panel does have the power under 9.3
of the Terms of Reference to direct an insurer to make an apology but does not find
that it is appropriate to do so in this dispute.
Is the complainant entitled to compensation?
The insurer is required to pay the complainant the amount of $3,000 compensation for
non-financial loss, temporary accommodation costs (on receipt of invoice or by mutual
Determination | Case number: 531761 Page 2 of 13
agreement) while the ACM removal works are underway, and the cost of a hygienist
report post works.
The insurer is not required to pay costs / expenses the complainant would have
incurred had she remained at the house. These costs include:
reimbursement of insurance premiums from January 2017 to now
payment of council rates and associated utilities
mortgage repayments.
1.3 Determination
This determination is partially in favour of the complainant.
Within 14 days of the complainant accepting this determination, the insurer is to:
instruct its loss adjuster to commence removal of all ACM
provide the complainant with three asbestos testing companies to assess and test
as many claimed contents as is practicable
pay the complainant $3,000 for non-financial loss
confirm in writing it will reimburse the complainant for temporary accommodation
costs while ACM removal works are undertaken, and pay for a further hygienist
report post works.
Determination | Case number: 531761 Page 3 of 13
2 Reasons for determination
There has been a full exchange of material between the parties and each party has
had the opportunity of addressing the issues arising from the material exchanged.
This determination is made by a panel consisting of an ombudsman, a representative
with extensive experience in the insurance industry and a representative with
extensive experience in consumer claims.
Whilst all information exchanged has been considered, only the information relevant
to the final outcome will be referred to within this determination.
This determination follows consideration of all information exchanged and is based on
what is fair in the circumstances, having regard to the relevant legal principles, terms
of the policy, good industry practice and where applicable, prior determinations.
The complainant wants several matters considered to resolve her complaint, which
are detailed in section 3 of this determination.
2.1 Is the insurer entitled to deny the claim for asbestos removal?
Circumstances of the loss
On 29 December 2016 the complainant lodged a claim with the insurer for storm
damage to her house sustained the same day. Water had entered the house due to a
guttering overflow, causing damage to the upstairs ensuite, walk-in robe and
downstairs study.
The insurer appointed a loss adjustor C to manage the building and contents loss. A
building consultant (T), reported to C on 7 February 2017 that the guttering was too
small for the roof area and needed to be replaced / upgraded, and internal repairs
could commence after this had been done.
C advised the insurer of this on 7 February 2017. It also advised the insurer there was
mould in the walk-in robe and study. C appointed property service consultant (O) who
subsequently appointed a cleaning and restoration firm (P) to conduct mould
remediation works.
The complainant says she approached P’s lead technician in February 2017 to query
the presence of asbestos (revealed by removed plasterboard and flooring). She says
P advised her it looked like asbestos, but there was no cause for concern, as it had
not been disturbed. She accepted his professional opinion and continued to live in the
house with her husband and two young children while repairs continued.
To speed up the repairs process the complainant requested a cash settlement for the
balance of quotes (including the guttering) at the end of June 2017. The insurer
processed payments of $26,750 (building repairs) and $15,630.04 (contents) on
Determination | Case number: 531761 Page 4 of 13
9 October 2017 (a previous cash settlement of $2,839.17 for contents havi ng been
paid on 7 July 2017). The insurer subsequently reimbursed the complainant $1,650
for her own hygienist report.
Risk assessment firm (PR) attended on 5 July 2017 to issue a mould clearance
certificate. Again, the complainant raised the issue of the ACM, with the consultant
(R) stating it did look like asbestos, but was not a concern if left undisturbed.
Complainant was advised to engage an asbestos specialist
On advice from her builder, the complainant engaged a Class A asbestos removalist
(K) to assess the asbestos in the area of repairs, who attended on 25 October 2017.
K reported:
S uspected pieces of asbestos fibre cement sheeting present (in wall cavity ma ster
wardrobe and ceiling cavity in downstairs bedroom) appeared to be in poor and
deteriorated conditio n, with unsealed and broken edges .
An absence of appropriate control measures for controlling asbestos risk including:
> no sealing/PVA spray of broken e xposed edge, unsealed asbestos
> no labelling present alerting anyone to the asbestos present on site
> plastic containments inadequate for containment
> exposure pathways including unsealed heating vent, doorways, ceilings and wall
cavities .
Given the conditio n of the suspected asbestos materials present there was:
> potential for further bits of asbestos or asbestos contaminate debris and dust in
the ceiling when the contractors took the ceiling down
> potential for disturbance to the asbestos present given the nature of the mould /
demolition work and the proximity to which they had been working to the
unsealed broken edges of asbestos
> potential for there to be asbestos contaminated dust and debris in the area when
the work was being done. If there was loose asb estos or contaminated dust in
the area then these could have been made airborne and there was the potential
for it to spread beyond the work area due to lack of containment measures in
place.
The report concluded (in part) there was a lack of segregation p rocedures, whereby
the complainant and her family were told they could access the repairs area during
and after works. They were even specifically instructed to enter the area every day to
empty water buckets connected to the evaporative dryers.
Further, it stated no access should be gained to affected areas until made safe, or a
clearance certificate issued.
Determination | Case number: 531761 Page 5 of 13
The complainant also submitted a report from the builder (S) she was going to use for
maintenance repairs. In his opinion the following should have been considered to
adhere to Occupational Health and Safety Guidelines, and Worksafe Victoria
Compliance Codes:
A competent person should identify the ACM.
A person with management of control of the workplace must ensure the presence
and location of the ACM identified is clearly indicated (labelled or signed).
The area should have been deemed an increased risk due to the poor condition of
the ACM.
Access should have been restricted and an asbestos management plan put into
place.
On receiving the advice from the asbestos removalist, the complainant immediately
contacted the insurer, and then called G (state manager for C), citing her concerns
regarding asbestos exposure and breaches in Worksafe procedures. G told the
complainant he was not aware there was any asbestos on the site, and it had not
been reported. The complainant advised G she had been told by P’s lead technician
in February there was ACM present, but that it was not a problem.
G arranged for a risk assessor PR to attend and report on 28 October 2017. PR had
previously attended the site to issue a mould clearance certificate on 7 July 2017.
PR’s technician spray sealed the ACM sheets as an interim measure to reduce the
risk of any airborne fibres being released. The complainant was advised no one
should enter the impacted areas until further notice. Testing found airborne fibres in
some of the samples taken, however, the immediate health risks were considered to
be low.
Insurer / loss adjuster deny mishandling discovery and reporting of asbestos
The director of PR called the complainant later that day to advise the air samples
were within safe levels. Asbestos dust had been found, but it was his opinion the
exposure risk was low as the remaining pieces had been sealed.
The complainant disputed this advice, stating ACM in the repairs area had not been
sealed for 10 months, and proper reporting / management guidelines had not been
followed. The director of PR offered an environmental clean the next day. The
complainant refused, saying she would seek legal advice.
The complainant then received a call from G confirming the test results. It was at this
point the complainant raised the issue that PR was the same company which issued
the clearance certificate in July, and she had serious concerns about their impartiality
given the advice the ACM was safe. The complainant then called the insurer to lodge
a complaint about C’s management of the claim. On 30 October 2017 the
complainant received a call from T (the manager of property services at C). This
Determination | Case number: 531761 Page 6 of 13
conversation was recorded by the complainant without the knowledge of T, but
deemed admissible by AFCA legal counsel.
During this call T advised the complainant it is:
not best practice that the asbestos, when it was revealed, at whatever time it was
revealed, behind whatever it was behind …it is not best practice in my world to
have not alerted and identified that...and there were a number of opportunities for
people to raise it as an issue…we’ve now rolled forward and there are doubts all
over the place…
T also advised the complainant it was his honest belief the risk of exposure was
extremely low, but agreed there is no safe level. T recommended the complainant
engage her own hygienist / specialist to carry out further testing. E carried this out on
1 December 2017. A total of 17 samples were taken, two of which were found to
contain asbestos.
These were from cement sheets in the upstairs wardrobe and downstairs bedroom.
The air sampling showed all levels to be below the detection limit. Twelve dust swabs
and one vacuum bag sample showed no asbestos readings. The report concludes the
risk to occupants was low, if the ACM is not disturbed.
On 3 November 2017 the complainant received an email from G at the loss adjuster
denying any liability to her. It states their scope did not extend to arranging for
removal of pre-existing ACM. Further, it states it was advised by the contractor O that
it did not cut, drill, move or disturb any ACM. It re- iterates the findings of PR’s report
from 27 October 2017, stating all res ults showed reading ‘below the detectable limits’.
However, C did offer to meet the cost of asbestos removal and to reimburse the
complainant for temporary accommodation. C also offered to cover the cost of a
hygienist report post these works.
The panel is satisfied the ACM should have been reported (and management plans
put into place) in February 2017, when P first discussed the possibility of its existence
with the complainant.
Serious concerns raised about the conduct of the loss adjuster
Under the Privacy Act, the complainant requested all internal file notes, reports and
emails from the insurer, C, P, PR and O. While the complainant advised numerous
emails have been withheld, she forwarded an email written by P to the loss adjuster
on 20 December 2017, in response to the question from the insurer:
Why did P, when they removed the wall lining and saw what could have been
asbestos, not simply board it back up again. I suppose they to an extent
answered this in their undated letter to T, but please put this specific question to
them.
Determination | Case number: 531761 Page 7 of 13
The full email response was:
Hi [T], as mentioned previously,
The identification was purely an oversight, the house appeared to have had
several renovations and was updated in a few ways which may not have triggered
the usual instincts of “this house is old, let’s be weary of any possible ACM” and
was also not the of the highest priority to the tech in relation to the task he was
conducting. The area of concern (identified ACM) was outside our defined work
area and as stated in previous documentation during the works conducted by P
no ACM was cut, drilled, moved or destroyed. [sic]
The email was edited by T, and sent to the insurer as:
Hi T, as mentioned previously,
The area of concern (identified ACM) was outside our defined work area and as
stated in previous documentation during the works conducted by P no ACM was
cut, drilled, moved or destroyed.
The act of omitting the first sentence of P’s response when sending it to the insurer
would appear to be an attempt to cover up the lack of appropriate action taken when
the ACM was first identified by P.
Of relevance, the loss adjuster advises T recently left their employment, but was
contacted by telephone where he stated having no recollection of making a change to
the email. However, the loss adjuster made their own enquiries and confirmed the
email was sent in its edited form. C further states:
We have previously outlined our position in terms of this matter, and whilst we do
not believe this statement alters the exposure to asbestos, we regret the email
appears to have been edited prior to submission to you.
On 9 September 2018 the insurer advised this matter had been referred internally to
its National Manager of Assessing Services. At the time of writing, the insurer has not
advised the outcome.
The panel considers the deliberate omission of the first sentence in the email can only
be construed as an attempt by the loss adjuster to misrepresent the true
circumstances of why the ACM was not reported initially. It constitutes a serious
breach of conduct on the part of the loss adjuster.
The insurer is not entitled to deny the claim for asbestos removal
The panel is satisfied there was systemic mismanagement of the ACM risk from the
outset, and the insurer should remove all the ACM from the house, and pay for
Determination | Case number: 531761 Page 8 of 13
subsequent cleaning and testing. This obligation extends to removal and clearing of
all the ACM discovered and exposed by the event and the insurer’s restorations – not
simply spraying or sealing. The house must be absolutely cleaned so that it does not
expose a risk to the complainant and her family.
2.2 Is the insurer liable to pay the complainant’s sum insured for contents?
The complainant has not yet substantiated the loss for contents as claimed
The complainant seeks settlement for the sum insured for her contents of $182,325,
however, this amount is for the policy commencing March 2018 – March 2019. The
sum insured for contents at the date of loss was $165,375.
The analytical report by PR confirmed 10 dust samples had been taken from strategic
locations (ground and first floor) around the house using the lift tape method.
Asbestos was detected in one sample, this being the ceiling cavity of the walk-in
wardrobe within the containment area.
The analytical report provided by E comprised 17 samples, 12 of which were dust
swabs from the ground and first floor. As per the findings of PR’s report, asbestos
was found in the internal cavity cement sheeting. No asbestos was detected in the
dust swabs, and all air monitoring results were below the detectable limit of 0.01
fibres per millilitre.
Given these findings, the panel does not consider the insurer is currently liable to pay
the complainant the sum insured for replacement of contents, as the loss has not yet
been substantiated.
Fair in the circumstances further testing be undertaken
However, given the circumstances of this complaint, the panel deems it fair in the
circumstances that the insurer identifies three qualified asbestos risk assessment
companies, and gives the complaina nt the choice of which one to carry out specific
contents testing.
It must be an independent assessor who was not previously involved in the complaint.
Further, the insurer needs to provide him/her with all previous reports to review and
consider.
Upon receipt of these details, the complainant is to advise the insurer within 14 days
by return email of their preferred assessor.
Upon receipt of the complainant’s advice as to her preferred assessor, the insurer is
to:
arrange for this expert to complete its inspection and assessment of the asbestos
levels within 28 days
Determination | Case number: 531761 Page 9 of 13
within 14 days of the inspection, ensure its test results are made available to both
parties
within 14 days of the inspection, advise its recommendations as to contents
removal / replacement, where and if required.
2.3 Is the insurer bound to issue letters, apologise and conduct investigations?
AFCA is not a regulator of the insurance industry
The panel accepts there has been at least one documented instance of serious
misconduct on the part of the loss adjuster. The panel has the power under 9.3 of the
Terms of Reference to direct an insurer to make an apology. However, it does not find
that it would be appropriate in the circumstances of this matter to require the insurer
to issue letters of apology, undertake fuller investigations, provide public liability
insurance details to the complainant, or write letters of exposure to all the employees
on the site.
The complainant may wish to seek separate legal counsel in this regard.
2.4 Is the complainant entitled to compensation?
Majority of non-financial loss claimed has not been incurred by the complainant
Non-financial loss includes claims for stress or inconvenience caused by an error of
the insurer. The maximum amount AFCA can award for non-financial loss is $3,000
for each claim of loss.
AFCA will only award this type of compensation if there has been an unusual degree
or extent of inconvenience. We will not award compensation for loss that a
complainant may incur because of pursuing a complaint or rectifying an insurer’s
error.
When assessing whether the circumstances are of an unusual nature we will review:
the degree or extent of physical inconvenience suffered
the general time taken to resolve the complaint
the extent to which the insurer’s actions interfered with the complainant ’s
expectation of enjoyment or peace of mind.
Given the nature of this dispute and the potential impact upon the complainant and
her family, the panel considers an award of $3,000 non-financial loss compensation
appropriate in the circumstances.
Complainant would have incurred expenses irrespective of claim
The panel can only award compensation where a direct financial loss has been
suffered as a result of the insurer’s actions. As such, the insurer is not responsible for
Determination | Case number: 531761 Page 10 of 13
costs and expenses that would have been incurred had the claim not occurred, such
as insurance premiums, mortgage repayments and utilities.
Determination | Case number: 531761 Page 11 of 13
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Details of what complainant wants to resolve complaint
Issue Resolution/Rea son
Asbe stos related The insurer to continue home owners’ insurance coverage unoccupied
until the whole house is made safe in and honour current policy
coverage period.
As the o ccupants of house have been referred to the National
Asbestos Registry for Exposure , they require copies of all public
li ability insuranc e details for C and the contractors they hired who
have exposed them to asbestos contaminated dust and materials over
an extended period.
The insurer to write a letter of exposure covering all members of the
family living at the property at time of exposure.
The insurer to write a letter of exposure to all the employee s that were
on site at the property.
An apology from the ins urer for initial exposure, acknowledgement of
the misconduct that has occurred .
The insurer to conduct a full investigation into how this situation has
been handled and to inform the complainant of the outcome , and key
procedural cha nges that will be implement ed to ensure ot her families
are not put at risk of exposure to as bestos during repairs works.
The insurer to p ay the homeowners for the cost of removal of ex posed
asbestos in the related repair area and whole house to be cleaned by
Class A asbestos removal ist costing between $165,000 - $169,200 .
To p ay the home owners for temporary accommodation costs while the
Determination | Case number: 531761 Page 12 of 13
Issue Resolution/Rea son
whole house is being decontaminated and cleaned (2 - 3 weeks)
$3,000.
To p ay the homeowners for contents which needs to be ap propriately
discarded and replaced as of current date being $182,325 .
Expense s R eimbursement of insuranc e premium payments from when the initial
claim was made until present. $4,482.41 (Jan 2017 - Nov 2018) .
P ayment of council rates ($1981.11), associated f ees for utilities
($3056.47) and mortgage ($31,757.34) while the property has not
been lived in ( Oct ober 2017 to November 2018 ) .
Cost of board while living with extended family at rate of $250 per
week ($13,250).
Non - financial
compensation
Physical inconvenience – living away from home for over 12 months
Extra travel time to and from kinder.
Healt h – exposure to unsafe asbestos.
Loss of enjoyment / peace of mind – distress caused, not being able
to have another child as planned.
Financial pressure – extra expenses involved in living away from
home, re - purchasing items already owned.
Poor management / delay in claims handling, insurer refusal to
investigate complaints.
Injured feelings and humiliation – lack of good faith by insurer.
The complainant is aware of the maximum amount claimable under the FOS
monetary limits.
The complainant has withdrawn the claim for the cost of board.
3.3 Expert reports and submissions
Record Key points
Insurer’s ri sk asse ssor (PR)
Mould Analysi s
Report
14 - 07 - 2017
No mention made of ACM despite complainant stating this was
discussed with the technician RM.
Complainant’s builder (S )
Site Minutes
Report
25 - 10 - 2017
Claims ACM sheeting in poor ‘ripped, unsealed’ condition could be
clearly seen.
Claims area should have been deemed an increased risk.
Claims access should have been restricted.
Claims ACM should have been reported to Worksafe.
Complainant’s cla ss A
asbe stos removalist report
(K )
ACM sheets in wall and ceiling cavity appear to be in poor /
deteriorated condition.
Absence of any control / segregation measures.
Determination | Case number: 531761 Page 13 of 13
Record Key points
Report
25 - 10 - 2017
No sealing of broken unsealed edges.
Potential for previous works to have disturbed the ACM.
Insurer’s ri sk asse ssor (PR )
Asbe stos inve stigation
Report (date of attendance 28 -
10 - 2017)
30 - 10 - 2017
Cannot comment on whether ACM was disturbed during mould
remediation works.
Four out of five samples from cement sheeting in cavity of study
room positive for asbestos.
The inspected fibre cement fragments were noted to be bonded,
bu t because some were broken, they were deemed to be in poor
condition.
The cement sheet products are non - friable, although it is noted
some of the fragments are broken.
10 dust samples taken, asbestos identified in one.
Cement sheets sprayed and sealed.
Dis turbance potential stated to be low.
Immediate health risk stated to be low.
Ongoing management of the ACM will depend on whether the
materials are to be disturbed as part of the re - instatement works.
Restoration Firm (P ) letter to
Loss Adjustor
Letter
17 - 11 - 2017
States no ACM was cut, drilled, moved or disturbed.
States the ACM was outside its scope of works.
Refers to PR’s image of the ACM showing it has not been
touched.
States their technician is certain only listed materials were
removed.
Insurer’s property
consultant (O )
Report
19 - 11 - 2017
States complainant advised P’s technician there was ACM in the
roof, but does not say when.
States P believes it did not disturb the ACM.
States PR did not identify ACM in their July report.
States neither builder appointed by insurer identified ACM in the
wardrobe area.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.