Summary

After a burst pipe the complainant disputed the insurer's repairs and sought a cash settlement for the kitchen. AFCA required the insurer to pay $17,084.25 for rectification and temporary accommodation, complete the kitchen repairs and replace the lower cabinet doors, and pay $500 for non-financial loss.

The policy lets the insurer choose repair over cash settlement, and once repairs were well advanced with components made, completing them was reasonable.

Issues

Subjects and remedies

pay claimpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 531410 Page 1 of 8 Determination Case number: 531410 8 January 2019 1 Determination overview 1.1 Complaint The complainant is insured by the financial firm (insurer) under a residential strata insurance plan. The complainant lodged a claim after a pipe burst in her kitchen on 23 October 2017. The insurer accepted the claim and arranged repairs. The complainant has raised concerns about the adequacy of the repairs to t he property carried out by the insurer’s contractors. She seeks payment for the cost of undertaking rectification works and completing the outstanding repairs. The insurer acknowledges that rectification works are required in some areas and has offered to cash settle the complainant for the cost of these works. However, the insurer says it should be entitled to complete the outstanding repairs to the kitchen (rather than cash settling the complainant). The complainant is also dissatisfied with the ins urer’s handling of her claim. She seeks compensation for various financial and non-financial losses suffered as a result. 1.2 Issues and key findings What must the insurer do to fulfil its policy obligations? The cash settlement of $17,084.25 offered by the insurer for rectification works and temporary accommodation is fair and reasonable. The insurer is not required to increase this amount. The insurer is entitled to complete the outstanding repairs to the kitchen, given the progress made to date. The insurer is not required to cash settle the complainant for the cost of these repairs. However, the works undertaken should include the replacement of the lower cabinet doors. Is the complainant entitled to compensation? The complainant is entitled to compensation for non-financial loss of $500. Determination | Case number: 531410 Page 2 of 8 1.3 Determination This determination is substantially in favour of the insurer. The insurer is required to pay the complainant the amount of $17,084.25 for rectification of the repairs (excluding the kitchen) and temporary accommodation. The insurer is required to complete the repairs to the kitchen using the previously manufactured components and is also required to replace the lower cabinet doors . Alternatively, if the complainant elects to have the previously manufactured components installed by her own repairer, then the insurer is to:  make the components available for collection by the complainant or her contractor for at least 45 days, and  pay the complainant the cost of installing the already-manufactured components plus the cost of replacing the lower cabinet doors (based on a quote to be obtained from TBS). The insurer is required to pay the complainant an additional amount of $500 as compensation for non-financial loss. Determination | Case number: 531410 Page 3 of 8 2 Reasons for determination 2.1 What must the insurer do to fulfil its policy obligations? Complainant’s property was damaged by burst pipe The complainant lodged a claim on 23 October 2017 saying a pipe under her kitchen sink had burst that day. The insurer appointed:  ‘SCG’, builders, who attended the prope rty on 26 October 2017  ‘CC’, loss adjusters , who attended the property on 6 November 2017  ‘TBS’, builders, who attended the property on 14 November 2017. The insurer authorised repairs by TBS, in accordance with a scope of work prepared by SCG and reviewed by CC. TBS commenced work in January 2018. Complainant is dissatisfied with repairs The complainant has raised concerns about the quality of the repairs completed by TBS. She also says the scope of works approved by the insurer does not include all of the water damage to the property caused by the burst pipe. The complainant initially raised concerns about the repairs in March 2018, at which stage the repairs to the kitchen had not yet been completed. The complainant does not want the insurer’s builder (TBS) to complete the outstanding repairs to the kitchen. She says the insurer should cash settle her for the estimated cost of the repairs, based on a scope of works and quotation provided by her contractor (SS). No evidence of additional loss due to lack of moisture testing and drying The complainant says the insurer and its contractors did not undertake any moisture testing or install any drying equipment at the property to minimise further damage. However, the panel is not satisfied that the complainant has shown that the lack of moisture testing or drying caused any additional damage to the property. While the complainant referred to the cabinet doors having been damaged, it is likely this damage occurred during the initial incident. The complainant says her kitchen contractor (SS) advised that there may be mould damage to the kitchen due to the excessive water. However, while SS’s quotation confirms the kitchen carcases have been water damaged, it does not refer to any mould damage. There is no evidence of mould growth in the photos provided. Insurer has offered to pay for rectification and temporary accommodation The complainant raised the following specific complaints about the insurer ’s repairs: Determination | Case number: 531410 Page 4 of 8  the parquetry flooring showed signs of poor workmanship after repairs  the repairers allowed dust and sand to enter the central heating vents  the repairers did not clean up adequately after the repairs and left the walls dirty and the door stop covered in polish. The insurer has offered to resolve these issues by paying the following amounts: Item Amount Rectification work to parquetry flooring $1,980 Sanding and painting skirting boards $1,595 Inspection and cleaning of air ducts $477 Professional cleaning on completion of repairs $570 Door stop $1.25 TOTAL $ 4,623.25 The amounts offered by the insurer are based on quotes provided by the complainant. Based on the available information, the panel is satisfied that the insurer ’s offer is sufficient to complete the rectification works required. Given the nature of these works, the panel does not consider that a separate professional clean is required at each stage of the works (as requested by the complainant). The total cash settlement of $17,084.25 offered by the insurer also includes:  $10,176 for 24 nights ’ accommodation and car parking while the rectification works are carried out  $1,317 for an additional 3 nights ’ accommodation while the outstanding repairs to the kitchen are carried out (see below)  $968 for furniture removal and storage costs . The panel notes that the amount offered for temporary accommodation covers a period which is longer than the period for which accommodation was required while the initial repairs were carried out. The panel has considered whether the cash settlement amount should be increased to take into account the absence of a lifetime guarantee where repairs are cash settled, as well as the passage of time since the quotations were obtained. Determination | Case number: 531410 Page 5 of 8 However, the panel is satisfied that the amount offered by the insurer is fair and reasonable, after taking these factors into account. Accordingly, the insurer is not required to increase the settlement amount for rectification works and temporary accommodation. Insurer is not required to cash settle complainant for kitchen repairs The complainant asked the insurer to cash settle her for the cost of the outstanding kitchen repairs in March 2018. The insurer responded that it was not willing to cash settle the kitchen repairs. The insurer noted that the replacement sections for the damaged cabinetry had already been manufactured by TBS (to the specifications of the complainant’s kitchen) and were ready to be installed. Under the terms of the policy, the insurer has the discretion to choose whether to repair the damage to the property or pay the complainant the cost of repairs. The policy provides for a cash settlement where the policyholder does not want repairs to be completed. However, in these circumstances the settlement amo unt is reduced (to the amount required to reinstate the property to its condition prior to the damage, rather than its condition when new). The panel considers that the insurer acted reasonably in deciding to repair the water damage to the complainant’s pr operty to the condition the property was in when new. Further, once the repairs to the kitchen had commenced (including the manufacture of replacement components), the insurer was entitled to complete these repairs as intended, rather than cash settle the complainant for the cost of the outstanding repairs. This is because:  most of the repair work had already been done when the complainant sought a cash settlement  the insurer had incurred significant costs in relation to the manufacture of the replacement carcasses, kickers, end panels, and benchtop  the components manufactured by TBS remained available and ready to be installed. The complainant says the fact that rectification works were required to the other repairs shows that TBS cannot be relied upon to complete the kitchen repairs to an adequate standard. However, the panel is not satisfied this is the case, given the nature of the rectification issues identified. There is no information to show that the replacement components manufactured by TBS are defective. Further, under the General Insurance Code of Practice, the insurer Determination | Case number: 531410 Page 6 of 8 is required to guarantee repairs done on its behalf, and therefore would be required to rectify any defective work by TBS. The insurer has also offered to facilitate installation by the complainant’s preferred repairer (instead of TBS), should she prefer to adopt that approach. If the complainant elects to do so, then the insurer should:  pay the complainant the cost of installing the already-manufactured components  make the components available for collection by the complainant or her contractor for at least 45 days. Scope of works should be expanded to include lower cabinet doors The complainant says the scope of works approved by the insurer does not include all of the water damage to her property caused by the burst pipe. She says there is additional damage to the kitchen - in particular, the cabinet doors. The quotation provided by the complainant’s kitchen repairer (SS) states that most of the kitchen carcasses need to be replaced because of moisture damage and all of the doors need to be replaced to ensure a uniform appearance. Based on the various reports and photographs provided, the panel is not satisfied that all of the cabinetry needs to be replaced. There is no evidence that the upper shelving and doors were damaged by the water leak and the policy does not provide for the replacement of undamaged areas for matching purposes. However, based on the photographs provided by the complainant, the panel considers it likely that (at a minimum) the two doors on the cabinet under the kitchen sink need to be replaced. In these circumstances, it is appropriate that all the lower doors be replaced. In the event that the complainant elects to have the replacement components installed by her own contractor, the panel considers it is fair that the cash settlement amount be increased by the cost of replacing the lower cupboard doors. The insurer is to obtain a quote from TBS for this purpose. 2.2 Is the complainant entitled to compensation? We may award compensation for financial and non-financial loss The FOS Terms of Reference provides that we can award compensation for consequential financial loss (of up to $3,500) incurred by a complainant in connection with their claim. We can also award compensation for non-financial loss (of up to $3,000) where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with a complainant ’s expectation of enjoyment or peace of mind. Determination | Case number: 531410 Page 7 of 8 However, we adopt a conservative approach to the award of compensation for non- financial loss and expect a complainant to be moderately robust and tolerate a normal degree of inconvenience when making a claim. Complainant is dissatisfied with claims handling The complainant is dissatisfied with the manner in which the insurer has managed her claim. Among other things, the complainant says the insurer and its contractors:  failed to properly assess her claim and complete the repairs to an adequate standard  provided misleading and conflicting information during the claim process  were biased, inept, and did not follow proper processes  excessively delayed the settlement of her claim. The complainant says she has suffered stress, anxiety, and a lack of sleep due to the time spent dealing with the claim. She says she has also incurred medical and other costs as a result of the delays experienced during the claim process. Complainant is entitled to compensation of $500 The insurer says it has addressed the complainant ’s concerns in a timely manner, has apologised to the complainant in response to her service complaints, and has accepted fault where appropriate. The exchanged material confirms that the insurer has been in constant communication with the complainant since the claim was lodged. The insurer responded promptly to concerns raised by the complainant, and made reasonable offers to resolve the issues in dispute. Having reviewed the extensive correspondence between the parties, the panel is satisfied that the insurer acted appropriately to try and resolve the complainant’s concerns. Th ere is no evidence to suggest the insurer’s contractors were biased or failed to act in good faith. The panel accepts that the complainant suffered additional stress and inconvenience due to the issues with the initial repairs, which required rectification. However, the panel considers that the insurer was not responsible for the bulk of the delays which occurred. In the circumstances, the panel considers the complainant is entitled to compensation of $500. Determination | Case number: 531410 Page 8 of 8 3 Supporting information 3.1 The determination is made under FOS Terms of Reference AFCA has commenced managing disputes previously lodged with FOS. This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. The AFCA terms in this determination have the same meaning as the FOS term referenced and defined in the FOS Terms of Reference. FOS ter m AFCA term  applicant  complainant  financial services provider  financial firm  dispute  complaint 3.2 Our approach to this complaint This complaint has not been the subject of a recommendation. Due to the nature of the complaint, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this complaint based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice, and previous decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.