Home / Financial Firm (Unknown - Insurer) / Determination 531410
Determination 531410
Cash settlement versus insurer-completed kitchen repairs; adequacy of repairs
Summary
After a burst pipe the complainant disputed the insurer's repairs and sought a cash settlement for the kitchen. AFCA required the insurer to pay $17,084.25 for rectification and temporary accommodation, complete the kitchen repairs and replace the lower cabinet doors, and pay $500 for non-financial loss.
The policy lets the insurer choose repair over cash settlement, and once repairs were well advanced with components made, completing them was reasonable.
Issues
- Claim amount dispute primary · not upheld
“The insurer is entitled to complete the outstanding repairs to the kitchen ... The insurer is not required to cash settle the complainant for the cost of these repairs.”
- Poor claim handling secondary · not upheld
“the panel is satisfied that the insurer acted appropriately to try and resolve the complainant's concerns.”
- Repairs or contractors secondary · upheld
“the insurer is required to complete the repairs to the kitchen ... and is also required to replace the lower cabinet doors.”
Subjects and remedies
pay claimpay non financial lossrepair or rectify
Text of the determination
Determination | Case number: 531410 Page 1 of 8
Determination
Case number: 531410 8 January 2019
1 Determination overview
1.1 Complaint
The complainant is insured by the financial firm (insurer) under a residential strata
insurance plan. The complainant lodged a claim after a pipe burst in her kitchen on 23
October 2017. The insurer accepted the claim and arranged repairs.
The complainant has raised concerns about the adequacy of the repairs to t he
property carried out by the insurer’s contractors. She seeks payment for the cost of
undertaking rectification works and completing the outstanding repairs.
The insurer acknowledges that rectification works are required in some areas and has
offered to cash settle the complainant for the cost of these works. However, the
insurer says it should be entitled to complete the outstanding repairs to the kitchen
(rather than cash settling the complainant).
The complainant is also dissatisfied with the ins urer’s handling of her claim. She
seeks compensation for various financial and non-financial losses suffered as a
result.
1.2 Issues and key findings
What must the insurer do to fulfil its policy obligations?
The cash settlement of $17,084.25 offered by the insurer for rectification works and
temporary accommodation is fair and reasonable. The insurer is not required to
increase this amount.
The insurer is entitled to complete the outstanding repairs to the kitchen, given the
progress made to date. The insurer is not required to cash settle the complainant for
the cost of these repairs. However, the works undertaken should include the
replacement of the lower cabinet doors.
Is the complainant entitled to compensation?
The complainant is entitled to compensation for non-financial loss of $500.
Determination | Case number: 531410 Page 2 of 8
1.3 Determination
This determination is substantially in favour of the insurer.
The insurer is required to pay the complainant the amount of $17,084.25 for
rectification of the repairs (excluding the kitchen) and temporary accommodation.
The insurer is required to complete the repairs to the kitchen using the previously
manufactured components and is also required to replace the lower cabinet doors .
Alternatively, if the complainant elects to have the previously manufactured
components installed by her own repairer, then the insurer is to:
make the components available for collection by the complainant or her contractor
for at least 45 days, and
pay the complainant the cost of installing the already-manufactured components
plus the cost of replacing the lower cabinet doors (based on a quote to be obtained
from TBS).
The insurer is required to pay the complainant an additional amount of $500 as
compensation for non-financial loss.
Determination | Case number: 531410 Page 3 of 8
2 Reasons for determination
2.1 What must the insurer do to fulfil its policy obligations?
Complainant’s property was damaged by burst pipe
The complainant lodged a claim on 23 October 2017 saying a pipe under her kitchen
sink had burst that day. The insurer appointed:
‘SCG’, builders, who attended the prope rty on 26 October 2017
‘CC’, loss adjusters , who attended the property on 6 November 2017
‘TBS’, builders, who attended the property on 14 November 2017.
The insurer authorised repairs by TBS, in accordance with a scope of work prepared
by SCG and reviewed by CC. TBS commenced work in January 2018.
Complainant is dissatisfied with repairs
The complainant has raised concerns about the quality of the repairs completed by
TBS. She also says the scope of works approved by the insurer does not include all
of the water damage to the property caused by the burst pipe.
The complainant initially raised concerns about the repairs in March 2018, at which
stage the repairs to the kitchen had not yet been completed.
The complainant does not want the insurer’s builder (TBS) to complete the
outstanding repairs to the kitchen. She says the insurer should cash settle her for the
estimated cost of the repairs, based on a scope of works and quotation provided by
her contractor (SS).
No evidence of additional loss due to lack of moisture testing and drying
The complainant says the insurer and its contractors did not undertake any moisture
testing or install any drying equipment at the property to minimise further damage.
However, the panel is not satisfied that the complainant has shown that the lack of
moisture testing or drying caused any additional damage to the property. While the
complainant referred to the cabinet doors having been damaged, it is likely this
damage occurred during the initial incident.
The complainant says her kitchen contractor (SS) advised that there may be mould
damage to the kitchen due to the excessive water. However, while SS’s quotation
confirms the kitchen carcases have been water damaged, it does not refer to any
mould damage. There is no evidence of mould growth in the photos provided.
Insurer has offered to pay for rectification and temporary accommodation
The complainant raised the following specific complaints about the insurer ’s repairs:
Determination | Case number: 531410 Page 4 of 8
the parquetry flooring showed signs of poor workmanship after repairs
the repairers allowed dust and sand to enter the central heating vents
the repairers did not clean up adequately after the repairs and left the walls dirty
and the door stop covered in polish.
The insurer has offered to resolve these issues by paying the following amounts:
Item Amount
Rectification work to parquetry flooring $1,980
Sanding and painting skirting boards $1,595
Inspection and cleaning of air ducts $477
Professional cleaning on completion of repairs $570
Door stop $1.25
TOTAL $ 4,623.25
The amounts offered by the insurer are based on quotes provided by the complainant.
Based on the available information, the panel is satisfied that the insurer ’s offer is
sufficient to complete the rectification works required.
Given the nature of these works, the panel does not consider that a separate
professional clean is required at each stage of the works (as requested by the
complainant).
The total cash settlement of $17,084.25 offered by the insurer also includes:
$10,176 for 24 nights ’ accommodation and car parking while the rectification works
are carried out
$1,317 for an additional 3 nights ’ accommodation while the outstanding repairs to
the kitchen are carried out (see below)
$968 for furniture removal and storage costs .
The panel notes that the amount offered for temporary accommodation covers a
period which is longer than the period for which accommodation was required while
the initial repairs were carried out.
The panel has considered whether the cash settlement amount should be increased
to take into account the absence of a lifetime guarantee where repairs are cash
settled, as well as the passage of time since the quotations were obtained.
Determination | Case number: 531410 Page 5 of 8
However, the panel is satisfied that the amount offered by the insurer is fair and
reasonable, after taking these factors into account. Accordingly, the insurer is not
required to increase the settlement amount for rectification works and temporary
accommodation.
Insurer is not required to cash settle complainant for kitchen repairs
The complainant asked the insurer to cash settle her for the cost of the outstanding
kitchen repairs in March 2018.
The insurer responded that it was not willing to cash settle the kitchen repairs. The
insurer noted that the replacement sections for the damaged cabinetry had already
been manufactured by TBS (to the specifications of the complainant’s kitchen) and
were ready to be installed.
Under the terms of the policy, the insurer has the discretion to choose whether to
repair the damage to the property or pay the complainant the cost of repairs.
The policy provides for a cash settlement where the policyholder does not want
repairs to be completed. However, in these circumstances the settlement amo unt is
reduced (to the amount required to reinstate the property to its condition prior to the
damage, rather than its condition when new).
The panel considers that the insurer acted reasonably in deciding to repair the water
damage to the complainant’s pr operty to the condition the property was in when new.
Further, once the repairs to the kitchen had commenced (including the manufacture of
replacement components), the insurer was entitled to complete these repairs as
intended, rather than cash settle the complainant for the cost of the outstanding
repairs. This is because:
most of the repair work had already been done when the complainant sought a
cash settlement
the insurer had incurred significant costs in relation to the manufacture of the
replacement carcasses, kickers, end panels, and benchtop
the components manufactured by TBS remained available and ready to be
installed.
The complainant says the fact that rectification works were required to the other
repairs shows that TBS cannot be relied upon to complete the kitchen repairs to an
adequate standard.
However, the panel is not satisfied this is the case, given the nature of the rectification
issues identified.
There is no information to show that the replacement components manufactured by
TBS are defective. Further, under the General Insurance Code of Practice, the insurer
Determination | Case number: 531410 Page 6 of 8
is required to guarantee repairs done on its behalf, and therefore would be required to
rectify any defective work by TBS.
The insurer has also offered to facilitate installation by the complainant’s preferred
repairer (instead of TBS), should she prefer to adopt that approach. If the complainant
elects to do so, then the insurer should:
pay the complainant the cost of installing the already-manufactured components
make the components available for collection by the complainant or her contractor
for at least 45 days.
Scope of works should be expanded to include lower cabinet doors
The complainant says the scope of works approved by the insurer does not include all
of the water damage to her property caused by the burst pipe. She says there is
additional damage to the kitchen - in particular, the cabinet doors.
The quotation provided by the complainant’s kitchen repairer (SS) states that most of
the kitchen carcasses need to be replaced because of moisture damage and all of the
doors need to be replaced to ensure a uniform appearance.
Based on the various reports and photographs provided, the panel is not satisfied that
all of the cabinetry needs to be replaced. There is no evidence that the upper shelving
and doors were damaged by the water leak and the policy does not provide for the
replacement of undamaged areas for matching purposes.
However, based on the photographs provided by the complainant, the panel
considers it likely that (at a minimum) the two doors on the cabinet under the kitchen
sink need to be replaced. In these circumstances, it is appropriate that all the lower
doors be replaced.
In the event that the complainant elects to have the replacement components
installed by her own contractor, the panel considers it is fair that the cash settlement
amount be increased by the cost of replacing the lower cupboard doors. The insurer
is to obtain a quote from TBS for this purpose.
2.2 Is the complainant entitled to compensation?
We may award compensation for financial and non-financial loss
The FOS Terms of Reference provides that we can award compensation for
consequential financial loss (of up to $3,500) incurred by a complainant in connection
with their claim.
We can also award compensation for non-financial loss (of up to $3,000) where there
has been an unusual amount of physical inconvenience, time taken to resolve a
situation, or interference with a complainant ’s expectation of enjoyment or peace of
mind.
Determination | Case number: 531410 Page 7 of 8
However, we adopt a conservative approach to the award of compensation for non-
financial loss and expect a complainant to be moderately robust and tolerate a normal
degree of inconvenience when making a claim.
Complainant is dissatisfied with claims handling
The complainant is dissatisfied with the manner in which the insurer has managed her
claim. Among other things, the complainant says the insurer and its contractors:
failed to properly assess her claim and complete the repairs to an adequate
standard
provided misleading and conflicting information during the claim process
were biased, inept, and did not follow proper processes
excessively delayed the settlement of her claim.
The complainant says she has suffered stress, anxiety, and a lack of sleep due to the
time spent dealing with the claim. She says she has also incurred medical and other
costs as a result of the delays experienced during the claim process.
Complainant is entitled to compensation of $500
The insurer says it has addressed the complainant ’s concerns in a timely manner, has
apologised to the complainant in response to her service complaints, and has
accepted fault where appropriate.
The exchanged material confirms that the insurer has been in constant
communication with the complainant since the claim was lodged. The insurer
responded promptly to concerns raised by the complainant, and made reasonable
offers to resolve the issues in dispute.
Having reviewed the extensive correspondence between the parties, the panel is
satisfied that the insurer acted appropriately to try and resolve the complainant’s
concerns. Th ere is no evidence to suggest the insurer’s contractors were biased or
failed to act in good faith.
The panel accepts that the complainant suffered additional stress and inconvenience
due to the issues with the initial repairs, which required rectification. However, the
panel considers that the insurer was not responsible for the bulk of the delays which
occurred.
In the circumstances, the panel considers the complainant is entitled to compensation
of $500.
Determination | Case number: 531410 Page 8 of 8
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
AFCA has commenced managing disputes previously lodged with FOS.
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. The AFCA terms in this
determination have the same meaning as the FOS term referenced and defined in the
FOS Terms of Reference.
FOS ter m AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
3.2 Our approach to this complaint
This complaint has not been the subject of a recommendation. Due to the nature of
the complaint, it has been referred directly to a panel for determination, in line with the
Operational Guidelines to the FOS Terms of Reference. The panel consists of an
Ombudsman and two representatives with consumer and insurance experience.
The panel has decided this complaint based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice, and
previous decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other.
The panel has reviewed and considered all of the material provided by the parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination the panel has restricted its commentary to those issues that it
considers directly relevant to the outcome only.