Home / Financial Firm (Unknown - Insurer) / Determination 531402
Determination 531402
Alleged delays in supplying a replacement vehicle after a total loss, obstructed collection of belongings, and salvage dispute
Summary
After a total loss, the insured claimed compensation for delays, a missed collection of belongings and salvage problems. AFCA found the insurer handled the claim in a relatively timely manner, ordered nothing, and declined to determine the private salvage sale contract.
Delays were mostly caused by the insured's own registration and upgrade requests, the belongings confusion was an administrative error that did not warrant compensation, and the salvage sale is a private contract outside the policy.
Issues
- Delay primary · not upheld
“I am therefore satisfied the FSP managed the claim in a relatively timely manner and is not liable to pay compensation as a result.”
- Administrative error secondary · not upheld
“I accept this was simply an administrative error which the FSP took subsequent steps to address. The administrative error alone does not warrant any award of compensation.”
- Poor claim handling secondary · not upheld
“I am not satisfied the FSP has erred in its overall claim handling.”
Subjects and remedies
motor vehicle collisionno remedy
Text of the determination
Determination
Case No: 531402 Determination Page 1 of 9
Case number: 531402 21 September 2018
1 Overview
1.1 Dispute
The applicant lodged a claim under his motor vehicle insurance policy underwritten
by the financial services provider (FSP) following a collision with another vehicle.
The FSP accepted the claim and deemed the vehicle a total loss. As a result, the
applicant elected to have a replacement vehicle supplied by the FSP in line with the
terms of the policy. This vehicle has since been delivered to him.
However, the applicant seeks compensation from the FSP for financial / non-financial
loss on the basis that:
the FSP caused unnecessary delays in supplying the replacement vehicle
the FSP obstructed the collection of his belongings from the original vehicle
the original vehicle (which he purchased as salvage from the FSP) has items
missing from it and additional damage.
1.2 Issue and key findings
Is the FSP required to pay compensation to the applicant?
The FSP is not required to pay compensation to the applicant because:
the FSP was prevented from progressing the claim for approximately two weeks
due to a delay in receiving vehicle registration details from the applicant
the FSP was prevented from ordering a replacement vehicle for approximately
two weeks due to a request for an upgraded model mid-claim by the applicant
the FSP otherwise progressed the claim in a timely manner
whilst there was initial confusion regarding the location of the vehicle for the
applicant to collect his belongings, this was clarified with the applicant and
further access arranged, which the applicant declined to pursue.
With regards to the issues related to the applicant’s purchase of salvage from the
FSP, it is not appropriate for FOS to make a determination on these because:
the sale constitutes a private contract of sale between the applicant and the
FSP which is outside the terms of the policy being considered by FOS
there appears to be a question as to whether the applicant met the terms of that
private contract, so a matter to be resolved between the parties themselves.
1.3 Determination
This determination is in favour of the FSP.
The FSP is not required to pay compensation to the applicant.
Case No: 531402 Determination Page 2 of 9
2 Reasons for determination
2.1 Is the FSP required to pay compensation to the applicant ?
Timeline of events
A detailed timeline of events in relation to the overall claim is set out in Section 3 of
this determination. From a claim handling perspective, the following is the relevant
top-level timeline of events:
Date (2018) Ac ti vity
13 March Claim lodged and vehicle assessment booked.
28 March Vehicle is deemed a repairable write - off.
5 April Applicant advises he wishes to have a replacement vehicle supplied by the FSP
( as opposed to a cash settlement ) .
9 April Applicant calls to advise he is unable to access his vehicle at the auction yard to
collect his personal items . FSP advises they tried to contact him last week to
advis e of the vehicle’s location. A new appointment is booked for 11 Ap ril.
11 April Applicant fails to attend the appointment to collect his personal items.
16 April FSP advises it is still waiting on vehicle registration details from the applicant
(although the a pplicant maintains these had already been s upplied) .
18 Apr il Vehicle r egistration details received . The FSP is waiting on replacement vehicle
quotes .
23 April FSP advises it has received like - for - like quotes, but the applicant requests the
FSP source additional quot es for the upgraded ‘ limited - edition ’ model.
30 April FSP confirms receipt of additional quot es , but the applicant is unsure if he
wishes to proceed . He will consider and advis e accordingly.
1 May FSP calls to confirm whether the applicant wis hes to proc eed with the upgrade.
The applicant advises he is still trying to arrange associated finance.
7 May FSP calls applicant to follow up. Applicant advises financ e should be approved
tomorrow.
9 May FSP places order for the upgraded vehicle.
29 May Vehicle delivered to applicant.
Applicant seeks compensation for financial / non-financial loss
The applicant maintains the FSP erred in its claim handling saying:
the FSP took three months to source a replacement vehicle which was too long
he has incurred losses of $5,000 to $6,000 during this period consisting of
alternative transport arrangements, loss of employment and interest accrued
against his vehicle finance
Case No: 531402 Determination Page 3 of 9
he did not have a single point of contact at the FSP, and spent extended
periods of time on-hold
the FSP failed to arrange for him to collect his personal items from the original
vehicle.
He therefore expects the FSP to provide compensation for associated financial / non-
financial loss.
FOS may award compensation for financial / non-financial loss
Under its Terms of Reference, FOS may award compensation (capped at $3,300) for
consequential financial loss suffered by an applicant in connection with their claim if
this stems from an error made by an insurer.
FOS can also award up to $3,000 for non-financial loss if the FSP caused the
applicant to suffer an unusual degree or extent of inconvenience, delay or
interference.
It is important to note that such an award is based on an unusual degree or extent.
This would not encompass the normal degree of inconvenience a person would
suffer when lodging an insurance claim or in a dispute with their insurer.
FOS takes a conservative approach when considering any award of compensation.
FOS may consider an apology (if warranted) is appropriate in the circumstances.
FSP maintains it has not erred in its claim handling
The FSP says it has not erred in its claim handling.
With regards to the timeframes within which the replacement vehicle was provided, it
notes:
the claim was lodged on 13 March and the vehicle deemed a total loss on 28
March
there was an initial delay (5 April to 18 April) in the applicant providing his
vehicle registration details
like-for-like replacement quotes were received on 26 April
the applicant then requested an upgraded model, the associated quote being
received on 2 May
there was then a delay (2 May to 9 May) whilst the applicant arranged additional
finance, following which the upgraded replacement vehicle was ordered and
delivered on 29 May
the policy allows the FSP 90 days to provide a replacement vehicle and despite
some delays on the applicant’s part, the vehicle was delivered within 82 days.
With regards to the applicant collecting his personal items from the original vehicle,
the FSP accepts there was some initial confusion as to the location of the vehicle and
attempted (unsuccessfully) to contact the applicant to advise of this prior to his
attendance at the auction house.
It says it subsequently arranged for the applicant to collect the items two days later,
but the applicant failed to attend the appointment and did not pursue the matter any
further.
Case No: 531402 Determination Page 4 of 9
With regards to the applicant being able to contact the person handling the claim, the
FSP submits in instances where that person was unavailable, calls were returned in
a timely manner.
The FSP therefore maintains it has not erred in its claim handling. Whilst accepting
the applicant may have experienced a degree of inconvenience and incurred some
expenses during the course of the claim, the FSP refers to the following policy
provision:
You are not covered under any section of this policy for damage, loss, cost or legal
liability that is caused by or arises from or involves:
Consequential losses or extra costs following an incident covered by your policy
consequential losses (financial and non-financial loss) or extra costs following an incident
covered by your policy, such as:
loss of income or wages;
the cost of your time (e.g. inconvenience);
travel costs;
any costs not covered by your policy.
Therefore, the FSP maintains the loss being claimed by the applicant constitutes
consequential loss for the purpose of the policy, so specifically excluded from cover.
FSP is not required to pay compensation to the applicant
With regards to the FSP’s timeliness in its claim handling, I note:
the FSP was prevented from progressing the claim for approximately two weeks
due to a delay in receiving vehicle registration details from the applicant
the FSP was in a position to order a like-for-like vehicle on 23 April, but the
applicant then requested the FSP source quotes for an upgraded model which
caused a further approximate two-week delay in the ordering of a replacement
vehicle
accepting the FSP cannot reasonably be held liable for these two delays, it
otherwise progressed the claim in a timely manner.
I am therefore satisfied the FSP managed the claim in a relatively timely manner and
is not liable to pay compensation as a result.
With regards to the applicant collecting his belongings from the original vehicle, I
accept there was some initial confusion as to the vehicle’s locatio n. The available
evidence suggests the FSP attempted to contact the applicant prior to his attendance
at the auction house, but was unsuccessful in doing so.
The FSP subsequently arranged another appointment two days later which it
appears the applicant failed to attend. I note the applicant then indicated he would no
longer seek to collect the items.
Whilst the initial confusion regarding the location of the vehicle was unfortunate, I
accept this was simply an administrative error which the FSP took subsequent steps
to address. As the applicant then failed to attend the subsequent appointment and
then indicated he would no longer seek to collect his belongings, I am not satisfied
Case No: 531402 Determination Page 5 of 9
the FSP has erred in this regard. The administrative error alone does not warrant any
award of compensation.
With regards to the applicant’s experience in contacting his claim handler, I note
there were a significant number of inbound calls by the applicant to the FSP, so it is
understandable the claim handler would not always be available. The claim file notes
suggest the FSP made reasonable efforts to address the reasons for the applicant’s
calls on occasions when the claim handler was unavailable, or arranged for a return
call to be made.
I accept the applicant suffered some inco nvenience in this regard. However, I am not
satisfied this inconvenience exceeded that normally expected during the course of an
insurance claim.
For these reasons, I am not satisfied the FSP is required to pay compensation for
financial / non-financial loss because:
it has not erred in its overall claim handling
the losses claimed are consequential in nature , so specifically excluded from
cover under the policy.
Not appropriate for FOS to make a determination regarding salvage
There is no dispute the applicant ultimately decided he wished to purchase the
original vehicle in its damaged state from the FSP as salvage.
Whilst the vehicle has since been delivered to him, he seeks compensation / an
allowance be made because:
the engine cover is missing
the petrol tank (or petrol tank pipe) has a hole in it which was unrelated to the
collision
the keys are missing.
It is clear from the available information that the sale of the salvage to the applicant
constituted a contract of sale between the applicant and the FSP, and outside the
terms of the policy being considered by FOS.
Further, the FSP has more recently raised a query as to whether the applicant has
provided the agreed consideration for the vehicle i.e. transfer of funds to the FSP.
This is an issue that needs to be addressed between the applicant and the FSP
themselves as parties to the contract of sale.
For these reasons, it is not appropriate for FOS to make a determination in relation to
the salvage issues raised by the applicant (and more recently the FSP).
Case No: 531402 Determination Page 6 of 9
3 Supporting information
3.1 Timeline of events
Date (2018) Ac ti vity
13 March Claim lodged and vehicle assessment booked.
28 March Vehicle is deemed a repairable write - off.
1 April FSP processes claim noting the applicant also has the replacement vehicle
option ( RVO ) .
3 April FSP unsuccessful attempt to call applicant.
5 April Applicant calls FSP and confirms he would like to proceed with the RVO.
FSP to await vehicle financ e payout figure and associated det ails to process the
RVO.
Applicant advises he would like to retain salvage. FSP advises of $2,000
salvage cost. Applicant says he is due to attend the auction house on 9 April
and will advise whether he wishes to proceed wit h this. FSP advises it will
arrange to tow the vehicle to his address if he wishes to proceed.
6 April FSP discovers vehicle still located at the holding yard.
FSP confirms applicant is eligible for a replacement vehicle.
FSP tries to contact applicant t o confirm re the above, but is unsuccessful.
9 April Applicant calls to advise he is unable to access his vehicle at the auction yard.
FSP advises they tried to contact him last week. New appointment booked for
11 April.
The applicant raises a complaint r elated to being unable to collect his personal
items on Monday.
10 April Applicant calls to enquire if he can attend the auction yard today. FSP advises
this is not possible, so appointment remains for tomorrow.
12 April Applicant calls to speak with cla ims team.
Applicant raises issue with not being able to collect his belongings on Monday.
FSP re - iterates it attempted to contact him the prior week and sent an
associated letter. FSP confirmed next available appointment is on 16 April.
Applicant declines this and says he will not worry about his items.
Applicant also queried a vehicle accessory. FSP transfers applicant to relevant
area. Applicant says he would like to retain salvage so long as the front bar and
lights are still in the vehicle. FSP also adv ised the vehicle may have been
further damage if moved via a forklift, but the applicant simply wants the
associated salvage quot e.
Applicant calls back to say the front bar and lights have been removed, so
would like a discount ed salvage. FSP provides assessor’s contact details to
discuss.
FSP advises it is still waiting on payout details from the finance company.
Applicant asks for associated details.
Applicant’s wife calls to confirm the bank account det ails that the total loss
payout should be deposi ted into.
Case No: 531402 Determination Page 7 of 9
16 April Applicant calls for update. FSP advises it has finance information, but still
requires vehicle registration information. Applicant says this has already been
provided and requests matter be escalated to a supervisor. Applicant maintains
the information has already been sent, but FSP advises no associated email
received.
18 April Applicant advises the front grill e and some screws and bolts are missing from
the vehicle. FSP advises it is willing to consider a minor salvage adjustment for
the screws and bolts.
FSP waiting on quotes for a replacement vehicle now registration details
received .
19 April Applicant believes the FSP is delaying things by requesting multiple vehicle
replacement quotes. FSP apologises for delays, but it needs to c onfirm
applicant’s preferred dealer is the most competitive.
20 April Applicant calls regarding timeframes. FSP advises applicant of 90 - day
timeframe. Applicant requests claim be progressed as quickly as possible.
Applicant calls again, but FSP advises it is still waiting on quotes. Applicant
says he will follow - up.
23 April FSP advises the applicant of quotes received. Applicant says he is disappointed
the FSP did not obt ain quotes for the limited edition model. FSP says the quotes
are a like - for - like, b ut it can source an associated quote.
Applicant calls twice again, but FSP says it is still awaiting the limited edition
quote.
24 April Applicant raises issue with the claim timeframe. FSP advises it is ready to
proceed on the like - for - like quote, but the applicant is requesting the upgrade
and waiting on the associated quote. Applicant requests cash settlement based
upon the replacement quote. FSP advises any cash settlement would be in line
with the agreed value of $21,000.
25 April Applicant calls t o obtain value of the three replacement quotes received.
26 April FSP obtains details regarding availability of limited edition model, but still
waiting on some loc al supply confirmation. Applicant will also follow up any local
supply options.
27 April D ealership calls FSP and advises it will confirm availability.
Applicant says he has contacted new dealers who can supply a limited edition
model. FSP advises if they contact new dealers, this will re - set the quoting
process. Applicant confirms he understan ds and accepts this.
Applicant calls again for an update. FSP confirms it is still waiting on further
quotes. FSP advises the contract of sale provided by him is not acceptable for
the RVO process.
Applicant calls again for an update. FSP advis es it is sti ll waiting on further
quotes and it cannot do anything until these are received.
30 April FSP confirms receipt of additional quot es. Applicant queries if the quote
includes weathershield/paint protection. FSP says if the paint protection can be
confirmed, this will be taken into account in purchase order or later cash
payment.
Applicant calls saying the FSP should pay for the weathershield and requests
Case No: 531402 Determination Page 8 of 9
compens ation for delays. FSP advises of the 90 - day settlement timeframe.
Applicant is unsure whether he wishes to proceed with the RVO. He will
consider and advise accordingly.
FSP reviews claim noting claim lodged 13 March / vehicle written - off 28 March /
documentation requested from applicant to progress claim / registration
documents received 18 April / r eplacement vehicle quotes received 26 April /
applicant requests upgraded model 27 April. On this basis, it deemed no undue
delays and the applicant can either accept a cash settlement of wait for a
replacement vehicle.
Applicant queries how he is going to pay for the upgraded model. FSP advises
he should not proceed in this manner if he does not have the funds. Applicant
will consider and advise.
Applicant calls back expecting the FSP to cover the upgrade cost. FSP advised
he can either take out a loan for the upgrade, accept a like - for - like vehicle or
accept a cash settlement. Applicant says the FSP delays mean he missed out
on a special offer that had been available, but now has to pay an extra $1,990
for the same model as the offer has ended. Applicant r eferred to IDR process.
1 May FSP calls to confirm whether the applicant wis hes to proc eed with the upgrade.
The applicant advises he is still trying to arrange associated finance.
3 May Per 1 May.
7 May FSP calls applicant to follow up. Applicant advis es financ e should be approved
tomorrow.
9 May FSP places order for upgraded vehicle. Estimated delivery date of 25 May.
16 May Applicant calls to ask if vehicle can be delivered sooner. FSP advises 25 May
s till appears to be the scheduled delivery date.
Applicant requested the dealership invoice be paid today, but FSP says it can
only do t his five days prior to scheduled delivery. In addition, there was an error
on the invoice which is being addressed.
Applicant is advised the excess remains outstanding.
21 May Applicant is advised an amended dealership invoice will be paid tomorrow , but
the vehicle will not be released without excess payment.
22 May Applicant calls regarding what the upgrade cost is. FSP advises this is the
additional cost due to the vehicle upgrade requested by him, and for which he is
liable.
Applicant calls to advise he wishes to change dealer because he is not being
given the weather shields which ot her dealers offered. FSP advises it will not be
doing this and this was all discuss ed with him prior to the order being placed.
Applicant calls to query registration costs. FSP says this will be accounted for
and asks the applicant to confirm costs with the relevant transport authority.
Applicant agrees to do this.
23 May Applicant call s to advise the transport authority is unable to provide a quote.
FSP advises this will then need to be addressed once registration has been
paid. Applicant unhappy with this. He will again attempt to get a written quote for
the FSP to action.
FS P indemnif ies the applicant for the estimated registration costs. If the amount
is less than the actual costs, the applicant can claim this from the FSP.
Case No: 531402 Determination Page 9 of 9
25 May Revised delivery dat e to 28 May / early next week as the dealer is waiting on a
courier.
The applicant q ueries the upgrade cost. Cost confirmed plus the required
excess due to be paid to the dealer.
29 May Vehicle delivered to applicant.
30 May Applicant calls advising he may still wish to retain salvage. FSP advises salvage
$2,000 and non - negotiable, and confirmation required by 4.30PM on 31 May or
vehicle will be released.
31 May FSP attempts to contact the applicant two times to follow up his salvage
decision.
1 June No contact received from the applic ant, so FSP releases salvage.
7 June Applicant ca lls to query if it is still possible to retain salvage. FSP advises
salvage has been released as of 1 June because the applicant did not respond
by the 31 May deadline des pite attempts to contact him. The FSP suggests the
applicant contact the auction hous e to see if he can purchase the salvage direct
from them. Applicant remains dissatisfied.
8 June Applicant calls to re - iterate his dissatisfaction regarding the salvage and wants
the FSP to sell it direct to him. The FSP again suggests the applicant cont act
the auction house.
15 June FSP arranges for applicant to view the salvage at 11AM on 18 June. The FSP
advis es that should the applicant fail to keep the appointment or contact the
FSP on the day to confirm his intention, the vehicle would be auctioned .
Salvage is $2,000, non - negotiable.
FSP emails the purc hase condition to the applicant.
19 June IDR review confirms the applicant failed to attend the auction house on 18 June
or contact the FSP, so the vehicle will be auctioned.
Applicant makes contact to advise he wishes to purchase the vehicle, and he
had been sick yesterday. FSP advises per above and suggests he contact the
auction house.
26 June FSP discusses a further option for the applicant to purchase salvage for $2,000
with the originally discu ssed parts missing and any further damage that may
have been caused to the vehicle whilst in storage. The FSP says it appears the
keys are still with the vehicle, but this was not a deciding factor for the applicant.
12 July FSP offers final opportunity f or the applicant to purchase salvage and requires
confirmation by 4PM 19 July.
20 July FSP says it is arranging for the salvage to be delivered to the applicant on 23
July.
3 August Applicant advises the salvage has the engine cover missing, a hole in the petrol
tank and no keys.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.