Home / Financial Firm (Unknown - Insurer) / Determination 530932
Determination 530932
Refusal to indemnify cockatoo damage
Summary
The applicant's home insurer erected scaffolding for a covered roof repair, which was left unused for about two months. Cockatoos then chewed the exterior timber, and the FSP denied liability. AFCA ordered the FSP to repair the damage or pay the reasonable cost, and reimburse shade cloth expenses.
Damage caused by the scaffolding attracting cockatoos and left in place for an unreasonably long time is fair to indemnify despite the animal-damage exclusion.
Issues
- Claim denial primary · upheld
“On the balance of probabilities, I am satisfied the property was damaged by cockatoos because the FSP erected scaffolding and left it in place for an unreasonably long time.”
- Delay secondary · upheld
“The FSP acknowledges there were delays in commencing repairs and accepts the damage was recent and was caused by cockatoos.”
Subjects and remedies
home or building damagepay claimrepair or rectify
Text of the determination
Determination
Case No: 530932 Determination Page 1 of 5
Case number: 530932 5 September 2018
1 Overview
1.1 Dispute
The applicant holds a home and contents insurance policy with the financial services
provider (FSP).
The FSP erected scaffolding at the applicant‟s house to carry out repairs. The
applicant says the scaffolding attracted cockatoos. The cockatoos caused extensive
damage by chewing on the house.
The policy does not cover damage caused by animals pecking, scratching or
chewing. The applicant says the FSP should cover the damage outside the terms of
the policy because the scaffolding attracted the cockatoos and caused the damage.
The FSP has denied liability for the damage, as it does not accept the scaffolding
attracted the cockatoos.
1.2 Issues and key findings
Is the FSP liable for the damage caused by the cockatoos?
The most probable reason for the cockatoos damaging the property is that they were
attracted by the scaffolding, which the FSP erected and left in place for an
unreasonably long time.
Therefore, it is fair in the circumstances the FSP indemnify the applicant for the
damage caused by the cockatoos.
1.3 Determination
This determination is in favour of the applicant.
The FSP must repair the damage caused by the cockatoos or pay the applicant the
reasonable cost of repairs.
The applicant is to provide the FSP with an invoice for the work done and materials
used to erect the shade cloth after the scaffolding was removed. Upon receipt of
proof of this expense, the FSP is to reimburse the applicant for this expense.
Case No: 530932 Determination Page 2 of 5
2 Reasons for determination
2.1 Is the FSP liable for the damage caused by the cockatoos?
Applicant says scaffolding attracted cockatoos
The applicant lodged a claim after her roof was damaged by a falling branch. The
FSP accepted the claim and decided to repair the damage.
The FSP erected scaffolding in preparation for repairs. The scaffolding remained at
the property for about two months. The applicant says after about one month,
cockatoos started chewing the house‟s exterior timber. The applicant thinks they did
this because they were attracted by the scaffolding.
The applicant says she has lived at the property for about eight years, and it had not
attracted cockatoos before. The FSP agrees the damage is recent. The applicant
says the timber chewed by the cockatoos had been in place since the house was
built in about 1960 and was in good condition both when she purchased the house in
about 2010 and before the scaffolding was erected in early 2018.
FSP says cause of cockatoo attack unknown
The FSP appointed „JR‟, assessor, who inspected the property on 21 March 2018.
He noted the scaffolding had been installed in January 2018, yet works still had not
commenced.
JR confirmed the house had been damaged by cockatoos chewing on the exterior
cedar timbers. JR said the damage was recent. This conclusion is supported by
photographs showing freshly broken timber on the house and shards of timber all
over the balcony underneath.
JR‟s report says he is “not sure why the cockatoos attacked the home”, and “cannot
be sure” that it was because of the scaffolding. He queries whether it was something
which would have happened without the scaffolding because of the proximity of trees
to the home coupled with the perching spots on the house. He points out the damage
is widespread, not restricted to the part where scaffolding was installed.
The FSP acknowledges there were delays in commencing repairs and accepts the
damage was recent and was caused by cockatoos. The FSP says cockatoos are
known for attacking wood on houses.
W hile acknowledging its repairer‟s delays, the FSP does not accept the applicant‟s
theory that the scaffolding attracted the cockatoos. The case manager asked the
FSP if it could offer an alternative explanation. In response, the FSP stated:
The FSP cannot explain why the cockatoos attacked the insured property however, it is
well documented that experts are unable to explain why the birds attack specific areas at
specific times. A google search of „cockatoo destruction‟ confirm numerous cases of
cockatoos randomly attacking properties without explanation. There is no documentary
evidence that establishes the birds are attracted to scaffolding.
Case No: 530932 Determination Page 3 of 5
Scaffolding likely attracted cockatoos
The exchanged information indicates not long after the erection of scaffolding,
cockatoos began to cause extensive damage to the house in a short period of time.
Prior to this, the house stood for over 50 years without incurring this or any similar
kind of damage.
I am satisfied the applicant‟s position is cons istent with all available evidence. No
alternative explanation has been offered. Having considered the information provided
by both parties, I am satisfied the damage caused by the cockatoos probably
occurred due to the presence of the scaffolding.
Scaffolding in place for unreasonably long time
The FSP‟s notes establish the following timeline:
Date Event
25 January 2018 R oofer requested scaffolding .
5 February 2018 „IR‟, roofing experts appointed by FSP, found scaffolding and rail in place but
scaffolding required on the opposite side of the roof.
19 February 2018 Applicant engaged roof plumber who advis ed no maintenance issues. Applicant
advis ed FSP.
17 March 2018 Applicant called FSP complaining about delays.
18 March 2018 A pplicant called FSP , said cockatoos were damaging the house and she thought
the scaffolding was attracting them .
19 March 2018 FSP appointed alternative builder.
21 March 2018 Inspection by JR and new builder.
29 March 2018 FSP confirmed repairs complet ed and scaffolding removed.
8 April 2018 Applicant installed shade cloth over the house and carport and damage by
cockatoos stopped.
IR‟s report estimated the repair time at only six hours plus two hours to source
insurable materials. And yet, JR reported, as of 21 March 2018, “repairs have not
started”.
The FSP says repairs were delayed because it discovered an additional leak and
maintenance issues at the property. The applicant engaged a roof plumber who said
there were no maintenance issues. The applicant advised the FSP. The FSP
acknowledges there were delays in attending to repairs and the timeframe could
have been lessened by a more proactive approach by the repairer.
The scaffolding was in place for about two months. For almost all of this time, it was
not being used by tradespeople. The applicant says tradespeople would have
deterred any birds attracted to the scaffolding, and the cockatoos did not start their
perching behaviour and chewing damage to the house until the scaffolding had been
in place for about a month.
Case No: 530932 Determination Page 4 of 5
On balance, I accept the damage would not have occurred if repairs had been
commenced and completed, and the scaffolding removed, within a reasonable time.
Applicant entitled to cover outside policy
On the balance of probabilities, I am satisfied the property was damaged by
cockatoos because the FSP erected scaffolding at the property and left it in place
(and not in use) for an unreasonably long time.
Therefore, I am satisfied it is fair in all the circumstances the FSP indemnify the
applicant for the damage caused by the cockatoos.
Evidence does not establish cost of repairs
JR says the timbers affected by chewing have been damaged beyond repair and
require replacement. He estimated the cost of replacing the damaged timber at
$50,000. Neither party has obtained a quote for repairs.
The available evidence is not sufficient to determine the cost of repairing the damage
caused by the cockatoos.
The FSP must indemnify the applicant for the damage by repairing the damage
caused by the cockatoos, or by paying the applicant the reasonable cost of repairs.
After the scaffolding was removed, the applicant arranged for shade cloth to be
erected to protect the house. The applicant is to provide the FSP with an invoice for
the work done and materials used to erect the shade cloth. Upon receipt of proof of
this expense, the FSP is to reimburse the applicant.
Case No: 530932 Determination Page 5 of 5
3 Supporting information
3.1 FOS Approach
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this determination.
This dispute has been decided on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
3.2 Relevant policy extracts
The relevant policy extracts are referred to in the FSP‟s Notice of Response d ated 27
June 2018. Both the policy document and the Notice have been exchanged with the
applicant.
3.3 Other relevant material considered and relied on
Parties‟ submissions, emails and photographs.
Correspondence between the parties.
FSP‟s claim file notes.
F SP‟s reports and photographs from the roofer, builder and assessor.
3.4 Other matters
The applicant complained about the adequacy of repairs by the FSP‟s builder. Upon
inspection by the builder and JR on 17 July 2018, the FSP accepted liability for
further re pairs as set out in JR‟s reinspection report dated 17 July 2018.
As the FSP accepted liability and agreed to further repairs, the available information
establishes there is no dispute regarding this issue about the adequacy of repairs.
Therefore, this determination does not deal with this issue.