Determination 529383

Delays in loan applications and drawdowns

FirmFinancial Firm (Unknown - Bank)
Decided2019-05-24
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed$33,000
SourceAFCA PDF

Summary

Complainant said the bank misled him and delayed his refinance, construction loan and drawdowns, seeking $33,000 for increased building costs. AFCA found some delay by the bank and ordered $3,000 for stress and inconvenience, but found no proven financial loss or misleading conduct.

Non-financial loss compensation is available for stress and inconvenience caused by the firm's delay, even where the claimed financial loss was not incurred.

Issues

Subjects and remedies

pay non financial loss

Related

All Financial Firm (Unknown - Bank) determinations · Find similar determinations

Text of the determination

Determination | Case number: 529383 Page 1 of 10 Determination Case number: 529383 10 May 2019 1 Determination overview 1.1 Complaint The complainant holds a loan and construction loan with the financial firm (the bank) and says the bank misled him, and caused delays in relation to:  his loan applications including: > the refinance loans of his loans from another credit provider (the refina nce) > construction finance (the construction loan)  the construction loan drawdown; and  the bank‟s promotional cash back offer. According to the complainant‟s submissions he is seeking $33,000 for increased construction costs and compensation for stress and inconvenience. The case manager provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the financial firm. A copy of the recommendation is attached to this determination. The complainant rejected the recommendation. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were partially correct and are substantially adopted in this determination. I also find that (as the Bank acknowledged) that there had been some delay on the Banks part. While the delay did not result in financial loss it is clear that it caused the consumer distress. In those circumstances, I consider it appropriate to award the complainant an amount of non-economic loss for the stress and inconvenience associated with the delay. Determination | Case number: 529383 Page 2 of 10 1.3 Determination This determination is partially in favour of the complainant. If the complainant accepts it then the Bank is required to pay $3000.00 in compensation for non-financial loss to the complainant to an account nominated by the complainant. Determination | Case number: 529383 Page 3 of 10 2 Reasons for determination 2.1 Were the findings in the recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. The recommendation findings are substantially correct I am satisfied that the case manager‟s recommendation contains an accurate summary of the complaint, any applicable paragraphs of the Terms of Reference and any relevant law. However, the complainant’s claims for delay are established However, I consider that there is evidence of some delay on the part of the bank. As can be seen from the time line in paragraph 3.2 below. The complainant first approached his banker in July of 2016 and there are several delays until the loan is finally lodged on the Banks system and is approved. The Banks acknowledges this and provides complainant $5,000 compensation toward the increased cost of the building contract on 7 March 2017 plus $1,500 cash ba ck payment in relation to bank‟s marketing offer the complainant disputed as not applied incorrectly. It has not been shown the complainant has incurred any financial loss The recommendation set out the anticipated building costs that show the increased building costs claimed have not been incurred. I agree with this aspect of the recommendation and note that as a result of the complainant finding another builder to do the job for a lessor cost he has mitigated this loss. The complainant has suffered non financial loss The complainant claims and I accept that the delays caused him to incur stress and inconvenience, this is evident from the correspondence between the Bank and the complainant. This would include the stress and inconvenience of having to find another builder to do the job at the lower cost because of the delay in obtaining fianance. In these circumstances I determine that the Bank should pay the complainant $3,000.00 for non financial loss. Determination | Case number: 529383 Page 4 of 10 2.2 Do the complainant’s rejection response change the outcome? The complainant’s rejection comments do not change the outcome In rejecting the recommendation the complainant criticised the simplicity of the decision. This may be a response to the plain language that is used by AFCA. I have also considered what the complainant has said in relation to the stress tha t the delay has caused him, the fact that the Bank acknowledged the delay and provided compensation for the increased building costs and have determined to award the complainant non-financial loss. Determination | Case number: 529383 Page 5 of 10 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with Financial Ombudsman Service (FOS). This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint claim claim 3.2 Extended timeline of key information Record Key points 16 July 2016 Date complainant says he first interacted with the bank about refinancing his loans from another financial institution (other bank). 8 August 2016 Complainant pays builder $2,500. 22 September 2016 Bank notes say complainant originally receives a quote from the builder on this date for building costs of $337, 534 (Quote expiry 18 February 2017) 20 October 2016 Complainant signs privacy consent for construction loan application. Complainant says all bank‟s required documents for construction loan provide d on this date including building contract. 28 October 2016 Complainant pays builder $7,500. 18 November 2016 Complainant signs pri vacy consent form for refinance of land loan application. 2 December 2016 Refinance application for $680,000 input into bank’ s system. - Completed Customer Requirements Objective form completed by complainant (investment). 15 December 2016 Complainant says the bank requested new bank statements. 15 December 2016 Refinance application for $680,000 input into bank’ s system. - Completed Customer Requirements Objective form completed by Determination | Case number: 529383 Page 6 of 10 Record Key points complainant purpose outlined: payout loan for investment housing – amended to include LMI. Complainant says provided bank with rental statements. As per complainant notes – bank emails c omplainant requesting home loan account statements. Complainant provides account statements. Available information suggests the complainant provided the bank copies of: - account statements for his existing home loan with another credit provider for the pr evious three months - account statements for his personal account for September – October 2016 - August, September and October 2016 rental income receipts - two payslips for October 2016, and - PAYG payment summary for year ending 30 June 2016. 23 January 2017 – 28 February 2017 Applicable timeframe for the bank‟s marketing offer for a $1,500 bonus for eligible home loan and banking bundles to apply. Offer important information: This offer is limited to a single $1,500 bonus per customer and per home loan application. This means, if there is more than one applicant and one applicant receives the $1,500 bonus, all applicants are deemed to have received the bonus. Apply by 28 February 2017. Not withstanding this special promotional offer, [the bank] reserves t he right to offer a $1500 bonus at any time, including beyond the expiry date, independent of this promotion. 31 January 2017 Publication date of an online article provided by the complainant outlining details about the bank‟s marketing offer for a $1,500 bonus as : “[Bank] power b rokers have been b usy over the b reak putting together some fantastic benefits and pricing for our clients. $1500 Cash Back offer · Applicable on [bank] Tailored home loan, Choice package and Base Variable (Homeplus not applicab le) · Home Loans $250k and over · For applications b etween 1 January 2017 and 28 Feb ruary 2017 – drawn prior to 31 May 2017 · Clients must take out a [bank] credit card and make [b ank] their main transaction account · A pplicable on purchases and refinances from outside [b ank] group. First year annual fee waived ($395) on [bank] Choice Package · [Bank] is waiving the first year annual fee for Broker originated Choice Package loan applications · This offer can b e used in conjunction with the Cash Back promotion of $1500 11 February 2017 Bank request updated payslips from complainant. 18 February 2017 Builder quot e dated expires. Determination | Case number: 529383 Page 7 of 10 Record Key points 22 February 2017 Publication date of an online article provided by the complainant outlining the applicable timeframe for the bank‟s marketing offer for a $1,500 bonus as: “For applications between 1 January 2017 and 28 Feb ruary 2017 – drawn prior to 31 May 2017” 26 February 2017 Complainant signs discharge authority with another financial firm to “refinance to another institution” and send the unregistered Discharge or Mortgage via registered post to him. 7 March 2017 Builder advises complainant of increase to building contract of $6,000 due to expiry of previous quote on 18 February 2017. 23 – 31 March 2017 Complainant says banker advises will go on leave and a new banker will be assigned in his absence. *(The complainant has provided information that there were many text messages and email corres pondences between himself and the banker during this period) 24 March 2017 Bank contact notes says: [complainant] is doing construction on property building contract has updated. 3 April 2017 Valuation of property. 14 April 2017 Complainant sends supporting information for refinance of land loan application to bank. 18 April 2017 Bank advises complainant there was a problem receiving the attachments and requests he resends separately. 26 April 2017 Application for refinance ($550,000) of land loan submitted. 4 May 2017 Loan contract documents for refinanced land loan issued ($550,000). 11 May 2017 Complainant accepts bank’ s offer for refinance of land loan ($550, 000). Builder building contract provided to complainant – contract price $369,889. 12 May 2017 Bank contact notes show call to complainant to assist him with a quote for investor insurance. 15 May 2017 Building insurance certificate issued – notes building cont ract price $369,889. 8 June 2017 Expiry of building quote provided 7 March 2018. 30 June 2017 Bank „follow - up‟ call complainant. 13 July 2017 Bank call to complainant about $1,500 cash back done. Determination | Case number: 529383 Page 8 of 10 Record Key points 14 July 2017 Bank SMS to complainant about complaint about interest rates, package fees and Direct debit. 15 July 2017 Bank refunds complainant $395 as good will payment. 19 July 2017 Construction loan application input into system. Application system - declined. 24 July 2017 Construction loan application ($385,000) input into system. 25 July 2017 Construction loan conditionally approved by credit, initial decline overridden. Extended building contract required before unconditional approval can be granted. 27 July 2017 Valuation of property ordered. 30 August 2017 Bank „follow - up‟ call to complainant. 14 September 2017 Bank contacts builder to follow up on building contract. Builder advises bank they are waiting on complainant to come in and sign the cont ract. 19 September 2017 Complainant signs building contract ($369,889). 20 September 2017 Executed building contract provided to bank. 22 September 2017 Complainant pays builder $8,494.45. 27 September 2017 Approval letter for construction loan ($385,000) to complainant. 3 October 2017 Cont ract and offer for construction loan issued ($385,000). 5 October 2017 Complainant signs construction loan contract. The construction loan opened and ready for progressi ve drawdowns to be made. Complainant lodges internal complaint with bank. 1 December 2017 Complainant emails bank about complaint. Bank emails complainant confirming compensation (t otal $6,500) to be provided in relation to the complaint raised and refunds annual fee of $395. 4 December 2017 Bank provides complainant $5,000 compensation toward the increas ed cost of the building cont ract on 7 March 2017 plus $1,500 cash back payment in relation to bank‟s marketing offer the complainant disputed as not applied incorrectly. 8 December 2017 Bank emails complainant about request to fix interest rate at 3.69% explaining available interes t rates they can offer. Complainant emails bank requesting interest of 3.89%. 11 December 2017 Bank emails complainant about interest rat e complaint. 12 December 2017 Bank emails complainant requesting call back. Determination | Case number: 529383 Page 9 of 10 Record Key points 15 December 2017 Loan application update input into bank’s system (interests rate change). 18 December 2017 Bank emails complainant about interest rat e: I have fixed your loan account xxxxx1888 @3.89% for 3 years, will call you tomorrow to discuss 27 December 2017 Complainant emails bank about interest rate: I have spoken with [bank staff member]. I was told that the rate on loan 876671888 is still 4.39 and is not 3.89% as promised. 8 January 2017 Bank contact notes say complainant proceeding with loan and first drawdown request expected in February. 10 January 2018 Council grants conditional approval for development of property. 22 January 2018 Complainant submits first drawdown request for construction loan, however for demolition costs ($2,484.50) outside building contract terms. 30 January 2018 Building quote for expires. 2 February 2018 Bank email to complainant explaining cost of demolition not included in construction loan: Please note the total build cost is $392,889 and the loan is $385,000, leaving a difference of $8,309 - which you need to pay. 6 February 2018 Bank contact notes show policy waiver to allow payment of demolition cost claimed. Demolition cost $3,113.35 paid no fe e charged. 7 February 2018 Complainant submits se cond drawdown request for construction loan, however for demolition costs ($2,067.50) outside building finance terms. 8 - 20 February 2018 Bank contact notes show waiting for invoice/ receipts for drawdown request. 28 February 2018 Bank pays $2,067.50 to builder’s account. 18 March 2018 Complainant submits third drawdown request for construction loan, however for demolition costs ($17,755.65) outside building finance terms. 4 April 2018 Bank pays $17,755.65 to builder’s account. 18 April 2018 Building contract increase of $32,000 due to ex piry of previous quote with revis ed expiry of 18 July 2018 granted. 18 May 2018 Complainant contacts bank about complaint, bank offers to lodge int ernal complaint, complainant refuses bec ause customer servic e person could not predict outcome, complainant advis es will lodge with FOS. Determination | Case number: 529383 Page 10 of 10 Record Key points 25 May 2018 Complaint lodges with FOS. 4 June 2018 Bank receives claim from demolition company however it cannot accept claim or contact. Banker to follow - up with complainant. 2 July 2018 Bank emails complainant about complaint lodged. 4 September 2018 Bank receives new builder contract with lower build however needs to obtain approval or application to reprocess. 14 September 2018 AFCA Conciliation conference call held between the complainant and the bank. 12 October 2018 Bank receives new builder c ontract with lower build cost further to new construction loan application. 25 October 2018 Construction loan with new builder conditionally approved. 1 November 2018 Complainant signs loan contracts for new construction loan for new builder costs. 11 November 2018 Complainant submits first drawdown request for construction loan for new builder costs. Recommendation Case number: 529383 28 February 2019 4 Overview 4.1 Complaint The complainant holds a loan and construction loan with the financial firm (the bank). The complainant says the bank misled him about, and caused delays in relation to:  his application to refinance loans from another credit provider (the refinance)  his application for construction finance (the construction loan)  the construction loan drawdown payments; and  the promotional cash back offer. The complainant is seeking $33,000 for increased construction costs and compensation for stress and inconvenience. 4.2 Issues and key findings Did the bank cause unreasonable delays? The available information does not show the bank delayed either loan application or the release of drawdown payments. The bank responded in a reasonable time, after it received the relevant information, to process the loan applications and drawdown payments. Did the bank mislead the complainant? It has not been shown the bank misled the complainant. The bank requested relevant documents and made several attempts to obtain the building contract. The bank provided the loan contract terms to the complainant and explained the requirements for drawdown payments to be made. Should the bank pay the compensation claimed? The bank has already provided the complainant with some compensation. It has not been shown the complainant incurred any further loss due to an error or breach by the bank. The bank should not be required to pay the complainant compensation. Recommendation | Case number: 529383 Page 2 of 11 4.3 Recommendation This recommendation is in favour of the bank. The bank is not required to take any further action. Recommendation | Case number: 529383 Page 3 of 11 5 Reasons for recommendation 5.1 Did the bank cause unreasonable delay? The bank did not cause unreasonable delay A credit provider will only be liable to compensate a customer if it has caused unreasonable delay assessing the loan application. A credit provider should assess a loan application and provide its response to a customer within a reasonable time frame. The assessment of a loan application might be delayed for different reasons, and some of these may be outside the control of the credit provider. For example, the credit provider may be waiting for documents from a customer or a third party. The bank did not cause unreasonable delay because:  it had to wait for relevant instructions and information from the complainant to progress the loan applications  the complainant did not provide a signed building contract until September 2017  the bank processed the loan applications within a reasonable time when it did receive the required information  even though the drawdown payments requested in early 2018 were outside the construction loan terms, the bank processed payment within a reasonable time. The bank assessed the refinance loan application within a reasonable time The complainant says he: fulfilled all requirements for refinancing as early as October 2016 and that refinancing of all these loans should have been finalised within 4 to 6 week s On 18 November 2016 the complainant signed a privacy consent form for the refinance application. He says he expected the applications to be finalised within four to six weeks. The bank says at first the complainant wanted to refinance his land loan and b orrow funds to purchase a new investment property using the equity in existing the property. The bank has provided customer requirement objective forms completed by the complainant on 2 and 15 December 2016 to support this. On 11 February 2017 the bank requested further payslips to assess the refinance application. It appears the bank was waiting for the complainant to provide additional information after his instructions had changed. On 14 April 2017 the complainant provided further documents and on 4 May 2017 the bank offered the refinance loan. The complainant signed loan documents a week later. The bank assessed the refinance loan within three weeks after it received the required information from the complainant. Recommendation | Case number: 529383 Page 4 of 11 The bank required a signed building contract to assess the construction loan On 20 October 2016, the complainant signed a privacy consent form for the construction loan application and says he provided all the required documents for the bank to assess the application. However, the complainant did not sign a building contract until 19 September 2017. This was provided to the bank on 20 September 2017 and the bank approved the construction loan application a week later. A signed building contract is an essential document for potential credit p rovider‟s assessment of a construction loan application. The complainant says he provided the bank a building quote as early as October 2016. However, this was not sufficient information for the construction loan application to be assessed as it did not show:  the agreed total building costs between the complainant and the builder  the terms of the construction contract  the details of the licensed contractor for progressive drawdown payments. Considering:  the building contract is an essential document, and  contact notes show the bank requested it on several times even contacting the builder directly before it was provided it is more likely the bank requested the building contract. Until the complainant signed the building contract and a copy was provided to the bank, the construction loan application could not be assessed. The bank provided compensation for some increased costs On 5 October 2017 the construction loan was provided and the complainant made a formal complaint to the bank about the delay. He claimed he had incurred a loss of $6,000 for increased building costs. Although the bank did not agree that it caused the delay and loss claimed, it responded by providing the complainant:  $5,000 towards the increased construction costs  $1,500 towards the promotional cash back offer the complainant says should have been applied to his loans  an interest rate reduction, and  reversal of the bank‟s $395 annual account fee. This shows, if it was established bank did delay the loan applications, is has already provided reasonable compensation for any applicable loss for that period. Recommendation | Case number: 529383 Page 5 of 11 The bank did not delay release of drawdown payments In early October 2017, the construction loan was approved and ready for drawdown requests. On 22 January 2018 the complainant made the first drawdown request to pay a demolition invoice. The bank explained to the complainant the drawdown requested was outside the loan terms and drawdown payments must be paid to the builder further to the building contract. Contact notes show, after the complainant made several repeated requests and expressed the urgency of payment, the bank waived its internal policy to allow the drawdown payments to the demolition cost into the builder‟s account. In doing so it also waived some of the applicable drawdown fees. In these circumstances, the bank did not delay payment of the drawdown requests as they were outside the loan terms and the bank made efforts to express this to the complainant. Nevertheless, the bank provided each payment within three weeks of receiving corresponding the drawdown request. Also, since the complaint was lodged, the bank has approved the complainant‟s application for a new construction loan with a new builder. The bank processed the complainants requested drawdown payment to the new builder without delay. 5.2 Did the bank mislead the complainant? There is no information to show the bank mislead the complainant The complainant says the bank misled him about the documents required for the refinance and construction loan application. However, other than to make the claim, he has not shown that the bank misled him about the documents required. The bank‟s contact notes show the bank followed up with the complainant on several occasions about what was required to progress the application. T HE LOAN CONTRACT SET OUT THE INTEREST ONLY PERIOD During the conciliation held for this case the complainant claimed he was not informed, in the contract or otherwise, that principle and interest repayments would be payable after one year. The interest only period is set out on the first page of the loan contract in details disclosed on 27 September 2017. The contract says, “the interest only period of one year and zero months from the settlement date”. Settlement date is defined in the contract terms as the date of the first transaction on the account. The complainant signed the loan contract on 5 October 2017. In these circums tances, the bank did not mislead the complainant about how long the interest only period would apply for. Recommendation | Case number: 529383 Page 6 of 11 The bank explained what costs drawdown request payments could cover The complainant says the bank misled him about the construction loan drawdown payments and that they would be paid only to the builder he signed the building contract with. When the complainant made his first drawdown request to cover demolition costs, the bank wrote to him explaining what costs were payable under the loan and what costs he needed to pay himself. Despite this, the complainant made further drawdown requests to cover similar demolition costs. When the complainant chose to use a different builder, the bank worked with the complainant to provide the new construction loan to cover the costs in line with his needs. The bank told the complainant what costs could be covered and did not mislead him that the new builder‟s cost could be paid under the original construction loan. The $1,500 cash back offer applied once per customer per loan application The complainant says he should have received a promotional offer of $1,500 for each of the loans he applied for and the bank should pay him for a further four of his accounts. The bank has provided information about the promotional offer advertised: This offer is limited to a single $1,500 bonus per customer and per home loan application. This means, if there is more than one applicant and one applicant receives the $1,500 bonus, all applicants are deemed to have received the bonus. Apply by 28 February 2017. Although the application was not fully submitted until April 2017, the bank paid the complainant $1,500 in December when he complained he did not receive the offer. The bank‟s offer was limited to a single bonus per customer and the complainant has not provided any information to counter the bank‟s information showing he should receive $1,500 for each account. 5.3 Should the bank pay the complainant compensation? The complainant has not incurred the loss claimed It has not been shown the bank made any error or breached an obligation owed to the complainant. When the complaint was lodged the complainant sought compensation for $33,000 in increased building costs (including $1,000 not yet compensated by the bank in relation to the earlier $6,000 increase), and stress and inconvenience. In October 2018 the complainant engaged a new builder for a lower cost avoiding the increased building costs claimed as compensation. The anticipated building costs have been outlined in section 3.2 of this recommendation. The construction loan was provided in October 2017 and on 22 January 2018 the complainant made his first Recommendation | Case number: 529383 Page 7 of 11 drawdown request, however for demolition cost not the builder‟s. The building contract price expired on 30 January 2018 and the b uilder sought to increase costs in April 2018. For this reason, the $32,000 building cost increase relates to a period of delay in which the complainant was free to make drawdown requests to pay the builder but didn‟t. Recommendation | Case number: 529383 Page 8 of 11 6 Supporting information 6.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with Financial Ombudsman Service (FOS). This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term a pplicant complainant financial services provider financial firm dispute complaint claim claim 6.2 Anticipated building costs Date provided Builder contract details 2016 Builder Quot e $343,528 Expiry 18 February 2017 7 March 2017 Builder Quote $349,528 Expiry 11 May 2017 (original quot e plus $6,000 for expiry of quote) 11 May 2017 Builder contract $369,889 Expiry 30 January 2018, revised expiry 18 July 2018 (original quot e plus $6,000 for expiry of quote, $26, 355 for requested variations) 18 April 2018 Building contract increase of $32,000 due to ex piry of previous quote with revis ed expiry of 18 July 2018 granted. October 2018 New builder contract $346,889 (per new loan contract – anticipated building cost) Recommendation | Case number: 529383 Page 9 of 11 6.3 Key dates Date Key information 20 October 2016 Complainant signs pri vacy consent for construction loan application. 18 November 2016 Complainant signs pri vacy consent form for refinance of land loan application. 2 December 2016 Refinance application amended in system to reflect Customer Requirements Objective form changes. 15 December 2016 Refinance application amended in system to reflect Customer Requirements Objective form changes. 23 January 2017 – 28 February 2017 Timeframe for the bank‟s marketing offer for a $1,500 bonus for eligible home loan and banking bundles to apply. 4 May 2017 Letter of Offer on refinanced issued ($550,000). 11 May 2017 Complainant accepts bank’ s offer for refinance ($550,000). 25 July 2017 Construction loan conditionally approved by credit. Extended building contract required before unconditional approval can be granted. 14 September 2017 Bank contacts builder to follow up on building contract. Builder advises bank they are waiting o n complainant to come in and sign the cont ract. 19 September 2017 Complainant signs building contract ($369,889). 20 September 2017 Signed building cont ract provided to bank. 27 September 2017 Letter of Offer for construction loan issued ($385,000). 5 October 2017 Complainant signs construction loan contract. The construction loan opened and ready for progressi ve drawdowns to be made. Complainant lodges internal complaint with bank. 4 December 2017 Bank provides complainant $5,000 compensation toward the increas ed cost of the building contract on 7 March 2017 plus $1,500 cash back payment in relation to bank‟s marketing offer the complainant disputed as not applied incorrectly. 15 December 2017 Ban k applied interest rate change to complainant‟s loans further to complaint. 22 January 2018 Complainant submits first drawdown request for demolition costs ($2,484.50). 30 January 2018 Building quot e for expires. 2 February 2018 Bank email to complainant explaining cost of demolition not included in construction loan . 6 February 2018 Bank contact notes show policy waiver to allow payment of demolition cost claimed. Demolition cost $3,113.35 paid no fee charged. Recommendation | Case number: 529383 Page 10 of 11 Date Key information 7 February 2018 Complainant s ubmits second drawdown request for demolition costs ($2,067.50) . 8 - 20 February 2018 Bank contact notes show waiting for invoice/ receipts for drawdown request. 28 February 2018 Bank pays $2,067.50 to builder‟s account. 18 March 2018 Complainant sub mits third drawdown request for demolition costs ($17,755.65). 4 April 2018 Bank pays $17,755.65 to builder‟s account. 18 April 2018 B uilder seeks to increase b uilding contract costs by $32,000 due to expiry of previous quot e on 30 January 2018. R evised expiry of 18 July 2018 granted. 12 October 2018 Bank receives new builder contract with lower build cost further to new construction loan application. 25 October 2018 Construction loan with new builder conditionally approved. 1 November 2018 Complainant signs loan contracts for new construction loan with new builder. 11 November 2018 Complainant submits first drawdown request for construction loan for new builder costs. 6.4 How we assess complaints When we assess complaints, we consider available documents, the recollections of the parties, and all relevant circumstances. We give more weight to contemporaneous documentary information. If there is no relevant documentation, we will decide what is most likely to have occurred based on the information provided to us. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established. 6.5 Not considered in this complaint Loss of reputation The complainant sa ys the bank‟s alleged conduct has damaged his reputation. We are not able to award compensation for loss of reputation or a general claim that a financial firm has defamed the complainant. This is because we do not have the power to take evidence under oath, and any compensation for defamation would depend on evidence given on oath regarding the effect of the financial firm‟s action on the complainant‟s reputation. For this reason, we consider that the court is a more appropriate place to consider a claim for loss of reputation. Recommendation | Case number: 529383 Page 11 of 11 6.6 Supporting documents  Complainant submissions  Email correspondence  Letters of offer and loan contracts  Loan terms and conditions  Building contracts  Building quote  Drawdown request forms and provided invoices  Bank contact notes