Text of the determination
Determination | Case number: 529383 Page 1 of 10
Determination
Case number: 529383 10 May 2019
1 Determination overview
1.1 Complaint
The complainant holds a loan and construction loan with the financial firm (the bank)
and says the bank misled him, and caused delays in relation to:
his loan applications including:
> the refinance loans of his loans from another credit provider (the refina nce)
> construction finance (the construction loan)
the construction loan drawdown; and
the bank‟s promotional cash back offer.
According to the complainant‟s submissions he is seeking $33,000 for increased
construction costs and compensation for stress and inconvenience.
The case manager provided the parties with a recommendation on the issues in
dispute. The recommendation was in favour of the financial firm. A copy of the
recommendation is attached to this determination.
The complainant rejected the recommendation.
1.2 Issues and key findings
Were the findings of the recommendation correct?
The findings contained in the recommendation were partially correct and are
substantially adopted in this determination.
I also find that (as the Bank acknowledged) that there had been some delay on the
Banks part. While the delay did not result in financial loss it is clear that it caused the
consumer distress.
In those circumstances, I consider it appropriate to award the complainant an amount
of non-economic loss for the stress and inconvenience associated with the delay.
Determination | Case number: 529383 Page 2 of 10
1.3 Determination
This determination is partially in favour of the complainant. If the complainant accepts
it then the Bank is required to pay $3000.00 in compensation for non-financial loss to
the complainant to an account nominated by the complainant.
Determination | Case number: 529383 Page 3 of 10
2 Reasons for determination
2.1 Were the findings in the recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good industry
practice, codes of practice and previous AFCA decisions. I have taken into account all
the material submitted by the parties, both before and after the recommendation. I am
satisfied that the documentation I have relied on has been provided to both parties.
The recommendation findings are substantially correct
I am satisfied that the case manager‟s recommendation contains an accurate
summary of the complaint, any applicable paragraphs of the Terms of Reference and
any relevant law.
However, the complainant’s claims for delay are established
However, I consider that there is evidence of some delay on the part of the bank. As
can be seen from the time line in paragraph 3.2 below. The complainant first
approached his banker in July of 2016 and there are several delays until the loan is
finally lodged on the Banks system and is approved.
The Banks acknowledges this and provides complainant $5,000 compensation
toward the increased cost of the building contract on 7 March 2017 plus $1,500 cash
ba ck payment in relation to bank‟s marketing offer the complainant disputed as not
applied incorrectly.
It has not been shown the complainant has incurred any financial loss
The recommendation set out the anticipated building costs that show the increased
building costs claimed have not been incurred. I agree with this aspect of the
recommendation and note that as a result of the complainant finding another builder
to do the job for a lessor cost he has mitigated this loss.
The complainant has suffered non financial loss
The complainant claims and I accept that the delays caused him to incur stress and
inconvenience, this is evident from the correspondence between the Bank and the
complainant. This would include the stress and inconvenience of having to find
another builder to do the job at the lower cost because of the delay in obtaining
fianance.
In these circumstances I determine that the Bank should pay the complainant
$3,000.00 for non financial loss.
Determination | Case number: 529383 Page 4 of 10
2.2 Do the complainant’s rejection response change the outcome?
The complainant’s rejection comments do not change the outcome
In rejecting the recommendation the complainant criticised the simplicity of the
decision. This may be a response to the plain language that is used by AFCA. I have
also considered what the complainant has said in relation to the stress tha t the delay
has caused him, the fact that the Bank acknowledged the delay and provided
compensation for the increased building costs and have determined to award the
complainant non-financial loss.
Determination | Case number: 529383 Page 5 of 10
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with Financial Ombudsman Service (FOS).
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Extended timeline of key information
Record Key points
16 July 2016 Date complainant says he first interacted with the bank about refinancing
his loans from another financial institution (other bank).
8 August 2016 Complainant pays builder $2,500.
22 September 2016 Bank notes say complainant originally receives a quote from the builder on
this date for building costs of $337, 534 (Quote expiry 18 February 2017)
20 October 2016 Complainant signs privacy consent for construction loan application.
Complainant says all bank‟s required documents for construction loan
provide d on this date including building contract.
28 October 2016 Complainant pays builder $7,500.
18 November 2016 Complainant signs pri vacy consent form for refinance of land loan
application.
2 December 2016 Refinance application for $680,000 input into bank’ s system.
- Completed Customer Requirements Objective form completed by
complainant (investment).
15 December 2016 Complainant says the bank requested new bank statements.
15 December 2016 Refinance application for $680,000 input into bank’ s system.
- Completed Customer Requirements Objective form completed by
Determination | Case number: 529383 Page 6 of 10
Record Key points
complainant purpose outlined: payout loan for investment housing –
amended to include LMI.
Complainant says provided bank with rental statements.
As per complainant notes – bank emails c omplainant requesting home loan
account statements. Complainant provides account statements.
Available information suggests the complainant provided the bank copies of:
- account statements for his existing home loan with another credit
provider for the pr evious three months
- account statements for his personal account for September –
October 2016
- August, September and October 2016 rental income receipts
- two payslips for October 2016, and
- PAYG payment summary for year ending 30 June 2016.
23 January 2017 – 28
February 2017
Applicable timeframe for the bank‟s marketing offer for a $1,500 bonus for
eligible home loan and banking bundles to apply.
Offer important information:
This offer is limited to a single $1,500 bonus per customer and per
home loan application. This means, if there is more than one
applicant and one applicant receives the $1,500 bonus, all
applicants are deemed to have received the bonus. Apply by 28
February 2017. Not withstanding this special promotional offer, [the
bank] reserves t he right to offer a $1500 bonus at any time,
including beyond the expiry date, independent of this promotion.
31 January 2017 Publication date of an online article provided by the complainant outlining
details about the bank‟s marketing offer for a $1,500 bonus as :
“[Bank] power b rokers have been b usy over the b reak putting together some
fantastic benefits and pricing for our clients.
$1500 Cash Back offer
· Applicable on [bank] Tailored home loan, Choice package and Base Variable
(Homeplus not applicab le)
· Home Loans $250k and over
· For applications b etween 1 January 2017 and 28 Feb ruary 2017 – drawn prior to
31 May 2017
· Clients must take out a [bank] credit card and make [b ank] their main transaction
account
· A pplicable on purchases and refinances from outside [b ank] group.
First year annual fee waived ($395) on [bank] Choice Package
· [Bank] is waiving the first year annual fee for Broker originated Choice Package
loan applications
· This offer can b e used in conjunction with the Cash Back promotion of $1500
11 February 2017 Bank request updated payslips from complainant.
18 February 2017 Builder quot e dated expires.
Determination | Case number: 529383 Page 7 of 10
Record Key points
22 February 2017 Publication date of an online article provided by the complainant outlining
the applicable timeframe for the bank‟s marketing offer for a $1,500 bonus
as:
“For applications between 1 January 2017 and 28 Feb ruary 2017 – drawn prior to
31 May 2017”
26 February 2017 Complainant signs discharge authority with another financial firm to
“refinance to another institution” and send the unregistered Discharge or
Mortgage via registered post to him.
7 March 2017 Builder advises complainant of increase to building contract of $6,000 due
to expiry of previous quote on 18 February 2017.
23 – 31 March 2017 Complainant says banker advises will go on leave and a new banker will
be assigned in his absence.
*(The complainant has provided information that there were many text
messages and email corres pondences between himself and the banker
during this period)
24 March 2017 Bank contact notes says: [complainant] is doing construction on property
building contract has updated.
3 April 2017 Valuation of property.
14 April 2017 Complainant sends supporting information for refinance of land loan
application to bank.
18 April 2017 Bank advises complainant there was a problem receiving the attachments
and requests he resends separately.
26 April 2017 Application for refinance ($550,000) of land loan submitted.
4 May 2017 Loan contract documents for refinanced land loan issued ($550,000).
11 May 2017 Complainant accepts bank’ s offer for refinance of land loan ($550, 000).
Builder building contract provided to complainant – contract price
$369,889.
12 May 2017 Bank contact notes show call to complainant to assist him with a quote for
investor insurance.
15 May 2017 Building insurance certificate issued – notes building cont ract price
$369,889.
8 June 2017 Expiry of building quote provided 7 March 2018.
30 June 2017 Bank „follow - up‟ call complainant.
13 July 2017 Bank call to complainant about $1,500 cash back done.
Determination | Case number: 529383 Page 8 of 10
Record Key points
14 July 2017 Bank SMS to complainant about complaint about interest rates, package
fees and Direct debit.
15 July 2017 Bank refunds complainant $395 as good will payment.
19 July 2017 Construction loan application input into system. Application system -
declined.
24 July 2017 Construction loan application ($385,000) input into system.
25 July 2017 Construction loan conditionally approved by credit, initial decline overridden.
Extended building contract required before unconditional approval can be
granted.
27 July 2017 Valuation of property ordered.
30 August 2017 Bank „follow - up‟ call to complainant.
14 September 2017 Bank contacts builder to follow up on building contract. Builder advises bank
they are waiting on complainant to come in and sign the cont ract.
19 September 2017 Complainant signs building contract ($369,889).
20 September 2017 Executed building contract provided to bank.
22 September 2017 Complainant pays builder $8,494.45.
27 September 2017 Approval letter for construction loan ($385,000) to complainant.
3 October 2017 Cont ract and offer for construction loan issued ($385,000).
5 October 2017 Complainant signs construction loan contract. The construction loan
opened and ready for progressi ve drawdowns to be made.
Complainant lodges internal complaint with bank.
1 December 2017 Complainant emails bank about complaint.
Bank emails complainant confirming compensation (t otal $6,500) to be
provided in relation to the complaint raised and refunds annual fee of $395.
4 December 2017 Bank provides complainant $5,000 compensation toward the increas ed cost
of the building cont ract on 7 March 2017 plus $1,500 cash back payment in
relation to bank‟s marketing offer the complainant disputed as not applied
incorrectly.
8 December 2017 Bank emails complainant about request to fix interest rate at 3.69%
explaining available interes t rates they can offer.
Complainant emails bank requesting interest of 3.89%.
11 December 2017 Bank emails complainant about interest rat e complaint.
12 December 2017 Bank emails complainant requesting call back.
Determination | Case number: 529383 Page 9 of 10
Record Key points
15 December 2017 Loan application update input into bank’s system (interests rate
change).
18 December 2017 Bank emails complainant about interest rat e:
I have fixed your loan account xxxxx1888 @3.89% for 3 years, will
call you tomorrow to discuss
27 December 2017 Complainant emails bank about interest rate:
I have spoken with [bank staff member]. I was told that the rate on
loan 876671888 is still 4.39 and is not 3.89% as promised.
8 January 2017 Bank contact notes say complainant proceeding with loan and first
drawdown request expected in February.
10 January 2018 Council grants conditional approval for development of property.
22 January 2018 Complainant submits first drawdown request for construction loan,
however for demolition costs ($2,484.50) outside building contract
terms.
30 January 2018 Building quote for expires.
2 February 2018 Bank email to complainant explaining cost of demolition not included in
construction loan:
Please note the total build cost is $392,889 and the loan is $385,000,
leaving a difference of $8,309 - which you need to pay.
6 February 2018 Bank contact notes show policy waiver to allow payment of demolition cost
claimed. Demolition cost $3,113.35 paid no fe e charged.
7 February 2018 Complainant submits se cond drawdown request for construction loan,
however for demolition costs ($2,067.50) outside building finance
terms.
8 - 20 February 2018 Bank contact notes show waiting for invoice/ receipts for drawdown request.
28 February 2018 Bank pays $2,067.50 to builder’s account.
18 March 2018 Complainant submits third drawdown request for construction loan,
however for demolition costs ($17,755.65) outside building finance
terms.
4 April 2018 Bank pays $17,755.65 to builder’s account.
18 April 2018 Building contract increase of $32,000 due to ex piry of previous quote with
revis ed expiry of 18 July 2018 granted.
18 May 2018 Complainant contacts bank about complaint, bank offers to lodge int ernal
complaint, complainant refuses bec ause customer servic e person could not
predict outcome, complainant advis es will lodge with FOS.
Determination | Case number: 529383 Page 10 of 10
Record Key points
25 May 2018 Complaint lodges with FOS.
4 June 2018 Bank receives claim from demolition company however it cannot accept
claim or contact. Banker to follow - up with complainant.
2 July 2018 Bank emails complainant about complaint lodged.
4 September 2018 Bank receives new builder contract with lower build however needs to
obtain approval or application to reprocess.
14 September 2018 AFCA Conciliation conference call held between the complainant and the
bank.
12 October 2018 Bank receives new builder c ontract with lower build cost further to new
construction loan application.
25 October 2018 Construction loan with new builder conditionally approved.
1 November 2018 Complainant signs loan contracts for new construction loan for new
builder costs.
11 November 2018 Complainant submits first drawdown request for construction loan for new
builder costs.
Recommendation
Case number: 529383 28 February 2019
4 Overview
4.1 Complaint
The complainant holds a loan and construction loan with the financial firm (the bank).
The complainant says the bank misled him about, and caused delays in relation to:
his application to refinance loans from another credit provider (the refinance)
his application for construction finance (the construction loan)
the construction loan drawdown payments; and
the promotional cash back offer.
The complainant is seeking $33,000 for increased construction costs and
compensation for stress and inconvenience.
4.2 Issues and key findings
Did the bank cause unreasonable delays?
The available information does not show the bank delayed either loan application or
the release of drawdown payments. The bank responded in a reasonable time, after it
received the relevant information, to process the loan applications and drawdown
payments.
Did the bank mislead the complainant?
It has not been shown the bank misled the complainant. The bank requested relevant
documents and made several attempts to obtain the building contract. The bank
provided the loan contract terms to the complainant and explained the requirements
for drawdown payments to be made.
Should the bank pay the compensation claimed?
The bank has already provided the complainant with some compensation. It has not
been shown the complainant incurred any further loss due to an error or breach by
the bank. The bank should not be required to pay the complainant compensation.
Recommendation | Case number: 529383 Page 2 of 11
4.3 Recommendation
This recommendation is in favour of the bank. The bank is not required to take any
further action.
Recommendation | Case number: 529383 Page 3 of 11
5 Reasons for recommendation
5.1 Did the bank cause unreasonable delay?
The bank did not cause unreasonable delay
A credit provider will only be liable to compensate a customer if it has caused
unreasonable delay assessing the loan application. A credit provider should assess a
loan application and provide its response to a customer within a reasonable time
frame. The assessment of a loan application might be delayed for different reasons,
and some of these may be outside the control of the credit provider. For example, the
credit provider may be waiting for documents from a customer or a third party.
The bank did not cause unreasonable delay because:
it had to wait for relevant instructions and information from the complainant to
progress the loan applications
the complainant did not provide a signed building contract until September 2017
the bank processed the loan applications within a reasonable time when it did
receive the required information
even though the drawdown payments requested in early 2018 were outside the
construction loan terms, the bank processed payment within a reasonable time.
The bank assessed the refinance loan application within a reasonable time
The complainant says he:
fulfilled all requirements for refinancing as early as October 2016 and that refinancing of all
these loans should have been finalised within 4 to 6 week s
On 18 November 2016 the complainant signed a privacy consent form for the
refinance application. He says he expected the applications to be finalised within four
to six weeks. The bank says at first the complainant wanted to refinance his land loan
and b orrow funds to purchase a new investment property using the equity in existing
the property. The bank has provided customer requirement objective forms completed
by the complainant on 2 and 15 December 2016 to support this.
On 11 February 2017 the bank requested further payslips to assess the refinance
application. It appears the bank was waiting for the complainant to provide additional
information after his instructions had changed. On 14 April 2017 the complainant
provided further documents and on 4 May 2017 the bank offered the refinance loan.
The complainant signed loan documents a week later.
The bank assessed the refinance loan within three weeks after it received the
required information from the complainant.
Recommendation | Case number: 529383 Page 4 of 11
The bank required a signed building contract to assess the construction loan
On 20 October 2016, the complainant signed a privacy consent form for the
construction loan application and says he provided all the required documents for the
bank to assess the application. However, the complainant did not sign a building
contract until 19 September 2017. This was provided to the bank on 20 September
2017 and the bank approved the construction loan application a week later.
A signed building contract is an essential document for potential credit p rovider‟s
assessment of a construction loan application. The complainant says he provided the
bank a building quote as early as October 2016. However, this was not sufficient
information for the construction loan application to be assessed as it did not show:
the agreed total building costs between the complainant and the builder
the terms of the construction contract
the details of the licensed contractor for progressive drawdown payments.
Considering:
the building contract is an essential document, and
contact notes show the bank requested it on several times even contacting the
builder directly before it was provided
it is more likely the bank requested the building contract. Until the complainant signed
the building contract and a copy was provided to the bank, the construction loan
application could not be assessed.
The bank provided compensation for some increased costs
On 5 October 2017 the construction loan was provided and the complainant made a
formal complaint to the bank about the delay. He claimed he had incurred a loss of
$6,000 for increased building costs. Although the bank did not agree that it caused
the delay and loss claimed, it responded by providing the complainant:
$5,000 towards the increased construction costs
$1,500 towards the promotional cash back offer the complainant says should have
been applied to his loans
an interest rate reduction, and
reversal of the bank‟s $395 annual account fee.
This shows, if it was established bank did delay the loan applications, is has already
provided reasonable compensation for any applicable loss for that period.
Recommendation | Case number: 529383 Page 5 of 11
The bank did not delay release of drawdown payments
In early October 2017, the construction loan was approved and ready for drawdown
requests. On 22 January 2018 the complainant made the first drawdown request to
pay a demolition invoice. The bank explained to the complainant the drawdown
requested was outside the loan terms and drawdown payments must be paid to the
builder further to the building contract.
Contact notes show, after the complainant made several repeated requests and
expressed the urgency of payment, the bank waived its internal policy to allow the
drawdown payments to the demolition cost into the builder‟s account. In doing so it
also waived some of the applicable drawdown fees.
In these circumstances, the bank did not delay payment of the drawdown requests as
they were outside the loan terms and the bank made efforts to express this to the
complainant. Nevertheless, the bank provided each payment within three weeks of
receiving corresponding the drawdown request. Also, since the complaint was lodged,
the bank has approved the complainant‟s application for a new construction loan with
a new builder. The bank processed the complainants requested drawdown payment
to the new builder without delay.
5.2 Did the bank mislead the complainant?
There is no information to show the bank mislead the complainant
The complainant says the bank misled him about the documents required for the
refinance and construction loan application. However, other than to make the claim,
he has not shown that the bank misled him about the documents required. The bank‟s
contact notes show the bank followed up with the complainant on several occasions
about what was required to progress the application.
T HE LOAN CONTRACT SET OUT THE INTEREST ONLY PERIOD
During the conciliation held for this case the complainant claimed he was not
informed, in the contract or otherwise, that principle and interest repayments would be
payable after one year. The interest only period is set out on the first page of the loan
contract in details disclosed on 27 September 2017. The contract says, “the interest
only period of one year and zero months from the settlement date”. Settlement date is
defined in the contract terms as the date of the first transaction on the account.
The complainant signed the loan contract on 5 October 2017. In these circums tances,
the bank did not mislead the complainant about how long the interest only period
would apply for.
Recommendation | Case number: 529383 Page 6 of 11
The bank explained what costs drawdown request payments could cover
The complainant says the bank misled him about the construction loan drawdown
payments and that they would be paid only to the builder he signed the building
contract with.
When the complainant made his first drawdown request to cover demolition costs, the
bank wrote to him explaining what costs were payable under the loan and what costs
he needed to pay himself.
Despite this, the complainant made further drawdown requests to cover similar
demolition costs. When the complainant chose to use a different builder, the bank
worked with the complainant to provide the new construction loan to cover the costs
in line with his needs.
The bank told the complainant what costs could be covered and did not mislead him
that the new builder‟s cost could be paid under the original construction loan.
The $1,500 cash back offer applied once per customer per loan application
The complainant says he should have received a promotional offer of $1,500 for each
of the loans he applied for and the bank should pay him for a further four of his
accounts.
The bank has provided information about the promotional offer advertised:
This offer is limited to a single $1,500 bonus per customer and per home loan application. This
means, if there is more than one applicant and one applicant receives the $1,500 bonus, all
applicants are deemed to have received the bonus. Apply by 28 February 2017.
Although the application was not fully submitted until April 2017, the bank paid the
complainant $1,500 in December when he complained he did not receive the offer.
The bank‟s offer was limited to a single bonus per customer and the complainant has
not provided any information to counter the bank‟s information showing he should
receive $1,500 for each account.
5.3 Should the bank pay the complainant compensation?
The complainant has not incurred the loss claimed
It has not been shown the bank made any error or breached an obligation owed to the
complainant. When the complaint was lodged the complainant sought compensation
for $33,000 in increased building costs (including $1,000 not yet compensated by the
bank in relation to the earlier $6,000 increase), and stress and inconvenience.
In October 2018 the complainant engaged a new builder for a lower cost avoiding the
increased building costs claimed as compensation. The anticipated building costs
have been outlined in section 3.2 of this recommendation. The construction loan was
provided in October 2017 and on 22 January 2018 the complainant made his first
Recommendation | Case number: 529383 Page 7 of 11
drawdown request, however for demolition cost not the builder‟s. The building
contract price expired on 30 January 2018 and the b uilder sought to increase costs in
April 2018. For this reason, the $32,000 building cost increase relates to a period of
delay in which the complainant was free to make drawdown requests to pay the
builder but didn‟t.
Recommendation | Case number: 529383 Page 8 of 11
6 Supporting information
6.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with Financial Ombudsman Service (FOS).
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
a pplicant complainant
financial services provider financial firm
dispute complaint
claim claim
6.2 Anticipated building costs
Date provided Builder contract details
2016 Builder Quot e
$343,528
Expiry 18 February 2017
7 March 2017 Builder Quote
$349,528
Expiry 11 May 2017
(original quot e plus $6,000 for expiry of quote)
11 May 2017 Builder contract
$369,889
Expiry 30 January 2018, revised expiry 18 July 2018
(original quot e plus $6,000 for expiry of quote, $26, 355 for requested variations)
18 April 2018 Building contract increase of $32,000 due to ex piry of previous quote with
revis ed expiry of 18 July 2018 granted.
October 2018 New builder contract
$346,889
(per new loan contract – anticipated building cost)
Recommendation | Case number: 529383 Page 9 of 11
6.3 Key dates
Date Key information
20 October 2016 Complainant signs pri vacy consent for construction loan application.
18 November 2016 Complainant signs pri vacy consent form for refinance of land loan
application.
2 December 2016 Refinance application amended in system to reflect Customer Requirements
Objective form changes.
15 December 2016 Refinance application amended in system to reflect Customer Requirements
Objective form changes.
23 January 2017 –
28 February 2017
Timeframe for the bank‟s marketing offer for a $1,500 bonus for eligible
home loan and banking bundles to apply.
4 May 2017 Letter of Offer on refinanced issued ($550,000).
11 May 2017 Complainant accepts bank’ s offer for refinance ($550,000).
25 July 2017 Construction loan conditionally approved by credit. Extended building
contract required before unconditional approval can be granted.
14 September 2017 Bank contacts builder to follow up on building contract. Builder advises bank
they are waiting o n complainant to come in and sign the cont ract.
19 September 2017 Complainant signs building contract ($369,889).
20 September 2017 Signed building cont ract provided to bank.
27 September 2017 Letter of Offer for construction loan issued ($385,000).
5 October 2017 Complainant signs construction loan contract. The construction loan
opened and ready for progressi ve drawdowns to be made.
Complainant lodges internal complaint with bank.
4 December 2017 Bank provides complainant $5,000 compensation toward the increas ed cost
of the building contract on 7 March 2017 plus $1,500 cash back payment in
relation to bank‟s marketing offer the complainant disputed as not applied
incorrectly.
15 December 2017 Ban k applied interest rate change to complainant‟s loans further to
complaint.
22 January 2018 Complainant submits first drawdown request for demolition costs
($2,484.50).
30 January 2018 Building quot e for expires.
2 February 2018 Bank email to complainant explaining cost of demolition not included in
construction loan .
6 February 2018 Bank contact notes show policy waiver to allow payment of demolition cost
claimed. Demolition cost $3,113.35 paid no fee charged.
Recommendation | Case number: 529383 Page 10 of 11
Date Key information
7 February 2018 Complainant s ubmits second drawdown request for demolition costs
($2,067.50) .
8 - 20 February 2018 Bank contact notes show waiting for invoice/ receipts for drawdown request.
28 February 2018 Bank pays $2,067.50 to builder‟s account.
18 March 2018 Complainant sub mits third drawdown request for demolition costs
($17,755.65).
4 April 2018 Bank pays $17,755.65 to builder‟s account.
18 April 2018 B uilder seeks to increase b uilding contract costs by $32,000 due to expiry of
previous quot e on 30 January 2018. R evised expiry of 18 July 2018 granted.
12 October 2018 Bank receives new builder contract with lower build cost further to new
construction loan application.
25 October 2018 Construction loan with new builder conditionally approved.
1 November 2018 Complainant signs loan contracts for new construction loan with new
builder.
11 November 2018 Complainant submits first drawdown request for construction loan for new
builder costs.
6.4 How we assess complaints
When we assess complaints, we consider available documents, the recollections of
the parties, and all relevant circumstances. We give more weight to contemporaneous
documentary information. If there is no relevant documentation, we will decide what is
most likely to have occurred based on the information provided to us. If there are
conflicting recollections and these are evenly weighted, we may find that a claim
cannot be established.
6.5 Not considered in this complaint
Loss of reputation
The complainant sa ys the bank‟s alleged conduct has damaged his reputation. We
are not able to award compensation for loss of reputation or a general claim that a
financial firm has defamed the complainant. This is because we do not have the
power to take evidence under oath, and any compensation for defamation would
depend on evidence given on oath regarding the effect of the financial firm‟s action on
the complainant‟s reputation. For this reason, we consider that the court is a more
appropriate place to consider a claim for loss of reputation.
Recommendation | Case number: 529383 Page 11 of 11
6.6 Supporting documents
Complainant submissions
Email correspondence
Letters of offer and loan contracts
Loan terms and conditions
Building contracts
Building quote
Drawdown request forms and provided invoices
Bank contact notes
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.