Home / Financial Firm (Unknown - Credit) / Determination 529144
Determination 529144
Bank released final construction progress payment before practical completion
Summary
The complainant's bank released the final construction progress payment of $74,977.50 while the home had not reached practical completion. AFCA ordered the loan reduced by $59,982 (80% of the payment) and interest refunded, because the complainant also bore 20% responsibility.
The bank's 2016 valuation failed to identify clear defects, but the complainant should have verified the builder's progress claim, so responsibility is shared 80/20.
Subjects and remedies
home or building damagedebt waiver or reductionpay interest
Text of the determination
Determination | Case number: 529144 Page 1 of 3
Determination
Case number: 529144 9 January 2019
1 Determination overview
1.1 Complaint
The financial firm (bank) provided the applicant and her co-borrower with a $650,000
home loan (loan) for construction of their home in Western Australia (WA).
This dispute is about whether the bank incorrectly released the final progress
payment of $74,977.50 on 17 October 2016 (final progress payment), as outstanding
works remained uncompleted.
1.2 Issues and key findings
Did the FSP make an error when it paid the final progress payment?
Before processing the final payment, the bank had its valuer attend the property. The
valuer said that the property had reached “Practical Completion”. It is apparent from
some of the defects noted in a later valuation that the building had not reached
Practical Completion.
Should the complainant accept some responsibility for her loss
The complainant signed an authority telling the bank to make payment and delayed
complaining to the bank. The complainant should therefore accept some
responsibility for the loss.
1.3 Determination
The Determination is in mainly favour of the complainant. The bank should reduce the
complainant’s loan by $59,982 being 80% of the final progress payment. In addition,
the bank should refund the interest charged on the $59,982 from the date of payment
until the date the refund is processed.
Determination | Case number: 529144 Page 2 of 3
2 Reasons for determination
2.1 Did the FSP make an error when it paid the final progress payment?
The valuer said the works had reached practical completion stage
On 10 October 2016, the complainant signed an authority authorising the bank to
make the final progress payment to the builder. The bank organised for its valuer to
inspect the property. In the valuation dated 12 October 2016 the valuer said:
“We confirm that the construction has reached Practical Completion.”
The building contract says that Practical Completion is reached when the works are
completed except for any omissions or defects which do not prevent the works from
being reasonably capable of being used by the Client.
While reaching practical completions stage does not mean that the building will be
free of defects, a subsequent valuation conducted in early 2018 said that the building
had been completed to a non-tradesperson standard. The 2018 valuation said:
“ Non Tradesperson Standard - The dwelling is showing signs of structural defects
(refer to the photographs). From our physical inspection it appears that the
dwelling has not been completed to a non-tradesperson standard, with a number
of defects noted. These include but are not limited to:
- Repairs to external render;
- Inconsistencies with internal painting;
- Cracking/uneven slab work;
- Eaves and gutters not flush with walls;
- Drain pipes sticking out of the wall;
- Plaster board to the alfresco not flush;
- Repairs to window frames;
- Window recess not wide enough for window treatments; and
- Cabinetry poorly installed. ”
It is clear from the 2018 valuation that the building was not at practical completion
stage.
If the 2018 valuation had been submitted to the bank in 2016 (rather than the one the
bank received) then it is more likely than not that the bank would have:
gone back to the complainant
pointed out the defects identified by the valuation and
Determination | Case number: 529144 Page 3 of 3
sought further instructions from the complainant about if she still wanted to proceed
to make the final progress payment.
It is more likely than not that the complainant would not have authorised payment if a
proper valuation had been conducted in 2016.
In my view, the bank should accept responsibility for its 2016 valuation not identifying
what appear to be clear defects such that the property had not reached practical
completion stage. It is therefore appropriate for the bank to refund the final payment
and interest that has accrued on that amount, subject to the reduction of 20%
discussed below.
2.2 Should the complainant accept some responsibility for her loss
The terms of the loan contract and the payment authority signed by the complainant
contains an acknowledgment that:
I/we advise that the building being constructed for me/us by the Builder has been completed
to the said construction stage to my/our satisfaction according to the builder's certificate and
building contract.
I/we authorise the Bank's agent to inspect the building works. l/we acknowledge that any
inspection made on behalf of the Bank is done solely at the Bank's discretion for the Bank's
security purposes only and is not construed as an inspection for or on behalf of me/us or the
builder.
I/we am/are aware that this payment will be made only after the Bank's requirements and
loan conditions are met fully to its satisfaction
In addition, the Government of WA Building Commission Building Contracts and
Progress Payments Guide sets out information to guide owners by establishing a
common understanding of what the progress payment claim stages may involve
which states:
It is important that you understand the significance of the progress payment system and that
you verify for yourself or engage someone who can confirm that the claim being made by
the builder for the next instalment represents a genuine claim for the actual work completed
at that point.
The bank was not acting as a project manager for the complainants. That is, the bank
was not responsible for ensuring that the builder completed the works without defects.
The complainant should also have taken active steps to protect her own interests by
ensuring she was satisfied with the works or by engaging someone to inspect the
works on her behalf. It is therefore appropriate in my view that the complainant
accept some responsibility for the loss incurred.
In addition, the complainant did not complain to the bank in writing until 20 March
2018. This delay has meant interest continued to accrue.
For these reasons I think it fair in all the circumstances that the complainant accept
responsibility for 20% of the final payment.