Home / Financial Firm (Unknown - Credit) / Determination 529144

Determination 529144

Bank released final construction progress payment before practical completion

FirmFinancial Firm (Unknown - Credit)
Decided2019-02-06
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$59,982
Non-financial loss—
Amount claimed$74,978
SourceAFCA PDF

Summary

The complainant's bank released the final construction progress payment of $74,977.50 while the home had not reached practical completion. AFCA ordered the loan reduced by $59,982 (80% of the payment) and interest refunded, because the complainant also bore 20% responsibility.

The bank's 2016 valuation failed to identify clear defects, but the complainant should have verified the builder's progress claim, so responsibility is shared 80/20.

Issues

Subjects and remedies

home or building damagedebt waiver or reductionpay interest

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination | Case number: 529144 Page 1 of 3 Determination Case number: 529144 9 January 2019 1 Determination overview 1.1 Complaint The financial firm (bank) provided the applicant and her co-borrower with a $650,000 home loan (loan) for construction of their home in Western Australia (WA). This dispute is about whether the bank incorrectly released the final progress payment of $74,977.50 on 17 October 2016 (final progress payment), as outstanding works remained uncompleted. 1.2 Issues and key findings Did the FSP make an error when it paid the final progress payment? Before processing the final payment, the bank had its valuer attend the property. The valuer said that the property had reached “Practical Completion”. It is apparent from some of the defects noted in a later valuation that the building had not reached Practical Completion. Should the complainant accept some responsibility for her loss The complainant signed an authority telling the bank to make payment and delayed complaining to the bank. The complainant should therefore accept some responsibility for the loss. 1.3 Determination The Determination is in mainly favour of the complainant. The bank should reduce the complainant’s loan by $59,982 being 80% of the final progress payment. In addition, the bank should refund the interest charged on the $59,982 from the date of payment until the date the refund is processed. Determination | Case number: 529144 Page 2 of 3 2 Reasons for determination 2.1 Did the FSP make an error when it paid the final progress payment? The valuer said the works had reached practical completion stage On 10 October 2016, the complainant signed an authority authorising the bank to make the final progress payment to the builder. The bank organised for its valuer to inspect the property. In the valuation dated 12 October 2016 the valuer said: “We confirm that the construction has reached Practical Completion.” The building contract says that Practical Completion is reached when the works are completed except for any omissions or defects which do not prevent the works from being reasonably capable of being used by the Client. While reaching practical completions stage does not mean that the building will be free of defects, a subsequent valuation conducted in early 2018 said that the building had been completed to a non-tradesperson standard. The 2018 valuation said: “ Non Tradesperson Standard - The dwelling is showing signs of structural defects (refer to the photographs). From our physical inspection it appears that the dwelling has not been completed to a non-tradesperson standard, with a number of defects noted. These include but are not limited to: - Repairs to external render; - Inconsistencies with internal painting; - Cracking/uneven slab work; - Eaves and gutters not flush with walls; - Drain pipes sticking out of the wall; - Plaster board to the alfresco not flush; - Repairs to window frames; - Window recess not wide enough for window treatments; and - Cabinetry poorly installed. ” It is clear from the 2018 valuation that the building was not at practical completion stage. If the 2018 valuation had been submitted to the bank in 2016 (rather than the one the bank received) then it is more likely than not that the bank would have:  gone back to the complainant  pointed out the defects identified by the valuation and Determination | Case number: 529144 Page 3 of 3  sought further instructions from the complainant about if she still wanted to proceed to make the final progress payment. It is more likely than not that the complainant would not have authorised payment if a proper valuation had been conducted in 2016. In my view, the bank should accept responsibility for its 2016 valuation not identifying what appear to be clear defects such that the property had not reached practical completion stage. It is therefore appropriate for the bank to refund the final payment and interest that has accrued on that amount, subject to the reduction of 20% discussed below. 2.2 Should the complainant accept some responsibility for her loss The terms of the loan contract and the payment authority signed by the complainant contains an acknowledgment that: I/we advise that the building being constructed for me/us by the Builder has been completed to the said construction stage to my/our satisfaction according to the builder's certificate and building contract. I/we authorise the Bank's agent to inspect the building works. l/we acknowledge that any inspection made on behalf of the Bank is done solely at the Bank's discretion for the Bank's security purposes only and is not construed as an inspection for or on behalf of me/us or the builder. I/we am/are aware that this payment will be made only after the Bank's requirements and loan conditions are met fully to its satisfaction In addition, the Government of WA Building Commission Building Contracts and Progress Payments Guide sets out information to guide owners by establishing a common understanding of what the progress payment claim stages may involve which states: It is important that you understand the significance of the progress payment system and that you verify for yourself or engage someone who can confirm that the claim being made by the builder for the next instalment represents a genuine claim for the actual work completed at that point. The bank was not acting as a project manager for the complainants. That is, the bank was not responsible for ensuring that the builder completed the works without defects. The complainant should also have taken active steps to protect her own interests by ensuring she was satisfied with the works or by engaging someone to inspect the works on her behalf. It is therefore appropriate in my view that the complainant accept some responsibility for the loss incurred. In addition, the complainant did not complain to the bank in writing until 20 March 2018. This delay has meant interest continued to accrue. For these reasons I think it fair in all the circumstances that the complainant accept responsibility for 20% of the final payment.