Determination 526418

Partial claim decline for pool leak and ground movement cracking

FirmFinancial Firm (Unknown - Insurer)
Decided2019-05-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer accepted 20% of the pool leak damage and declined the rest as ground movement. AFCA did not decide the cause and ordered the insurer, at its cost, to arrange further geotechnical assessment and reassess the claim.

The proximate cause of the building and paving damage must be established by further geotechnical and footing investigation before the insurer's obligations under the policy can be determined.

Issues

Subjects and remedies

home or building damagereassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 526418 Page 1 of 12 Determination Case number: 526418 8 March 2019 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). On 7 February 2017, the complainant lodged a claim with the insurer after he noticed a leak in his concrete swimming pool. The complainant says that the leak caused damage to the property’s pool pavers as well as internal and external cracking damage to the property. Following assessments of the property, the insurer advised that it would settle 20% of the claimed damage consistent with the escape of liquid. However, the insurer says that the majority of the cracking damage is the result of ground movement which is excluded from cover under the policy. 1.2 Issues and key findings What is the extent of the insurer’s obligations to the complainant under the terms of the policy? Having reviewed all of the exchanged material, the panel is not satisfied there is sufficient information to reach a conclusion as to the full extent of the insurer’s obligations to the complainant under the policy. The insurer is, upon acceptance of this determination by the complainant, to undertake the further steps detailed within the determination. 1.3 Determination This determination is substantially in favour of the insurer. Upon acceptance of this determination b y the complainant, the insurer is to take the steps detailed within the determination. Determination | Case number: 526418 Page 2 of 12 Should the complainant not accept this determination, the insurer is to reinstate its offer which would be open for acceptance by the complainant for a period of 14 days. The insurer will not be required to take any further action with regard to the claim or the complaint. Determination | Case number: 526418 Page 3 of 12 2 Reasons for determination 2.1 What is the extent of the insurer’s obligations to the complainant under the terms of the policy? Evidence of an insured event at the property There is no dispute that the complainant’s property was damaged because of an escape of liquid. This occurred from a leak in the complainant’s concrete swimming pool. The complainant says this has caused resultant damage to th e property’s pool pavers, as well as internal and external cracking damage. As the policy covers escape of liquid from swimming pools, the panel accepts that there is evidence of an insured event. The insurer has advised that it will accept 20% of the claimed damage and has offered to settle the claim on that basis. The insurer says that the majority of the cracking damage was from factors excluded from cover under the policy. Insurer says majority of cracking damage was caused by excluded factors The insurer says that the majority of the cracking damage was the result of ground movement and not due to the leak in the swimming pool. The policy excludes loss or damage arising from ground movement. In order to be entitled to deny the balance of claim (80%), the insurer must show that the proximate cause of the damage was one or more of the excluded factors under the policy. It is well established at law that the proximate cause is not necessarily the first or the last or the sole cause of the damage. It is the dominant or effective or operative cause. In any particular case, the proximate cause of the loss is a question of fact to be determined based on the evidence and surrounding circumstances. Where there are several causes operating, each must be examined for the qualities of predominance and efficacy in relation to the resultant damage. Conflicting opinions regarding internal and external cracking The insurer appointed a builder (HR) who inspected the site and provided an initial repair assessment which confirmed their view that the leak to the swimming pool contributed only 20% to the resultant damage of the home and the remaining 80% of the damage is a result of gradual deterioration caused by differential movement of the structure on the inadequately compacted site fill material. Determination | Case number: 526418 Page 4 of 12 Significantly, within the initial repair assessment, HR advised that geotechnical investigation into the nature of the fill onsite would provide a profile of the founding material and the potential for further consolidation. In addition, HR advised that further destructive investigation into the footings of the building and the structural design of the swimming pool must be carried out prior to establishing a method of repair. In a subsequent report dated 5 December 2017, HR advised that due to the discrepancy of information in its report and that provided in the letter from the insured, HR recommended that a Geotechnical engineer be engaged to excavate several boreholes adjacent to the footings in order to confirm the depth and nature of the footings system. Furthermore, HR called for a site classification, and founding material and depth should also be established. The insurer appointed an engineer (IL) who conducted a site inspection of the insured property on 31 March 2017. IL submitted a report dated 3 July 2017. IL reported that damaged drainage, a leaking pool shell and the absence of sufficient roof flashing had exacerbated already existing damage. IL concluded that the primary cause of cracking and movement of the building and paving was the consolidation of the fill material upon which the structures have been founded. IL stated that geotechnical investigation into the nature of the fill on the site, together with investigation into the footing system by excavating boreholes must be carried out prior to establishing a method of repair. The complainant engaged his own e ngineer (ONG), to provide an opinion on the structural damage to the swimming pool and surrounding tile pool concourse. ONG carried out a site inspection on 6 July 2018 and submitted a report dated 16 July 2018. ONG says it observed noticeable tilting of the pool of about 30mm over approximately 14m of the pool length, together with cracking to the pool tiles adjacent to the pool crack zone. ONG was provided with water bills by the complainant indicating that over a three-month period from November 2016 to February 2017, the pool was leaking some 1,000 litres per day into the clay bearing soils. ONG concluded that it was the amount of water that had caused the softening of the bearing clays in this area and primarily caused the pool to tilt. ONG estimated the pool damage to be approximately 80% attributable to the leak. In relation to the dwelling, ONG was of the opinion that the cracking and damage caused by the pool leakage was to a lesser extent responsible, approximately 40%, as the property is supported on steel driven piles. ONG submitted a supplementary structural report based on some additional information the complainant obtained from the local council, as well as two Determination | Case number: 526418 Page 5 of 12 photographs taken on 14 February 2017, after the pool leak. The information from the local council, which is annexed to the supplementary report, includes a soil report and indicates that the depth of the fill is estimated up to 2.1m, being at the pool’s southern end. A building inspection report on the pool is also included, indicating that the piers or footings under the pool were deemed to be satisfactory. The photographs show cracking to the upper floor plasterboard and concourse tiling lifted at the pool leakage zone. ONG reiterated that in its view the damage to the swimming pool and surrounding tiled pool concourse has occurred primarily from the pool leakage event and not as a result of long term consolidation of the fill material. ONG further stated the cracking that occurred to the ceiling of the house after the pool leakage was primarily caused by the settlement having occurred adjacent to the pool cracked zone. ONG explained that the subsidence could not simply be attributed to settlement caused by long term reduction of the moisture content of the soils. If so, the sout hern end of the pool which has the most amount of fill would have settled more than anywhere else, however, this area has not subsided. Rather, subsidence has occurred at the northern end of the pool which is exactly where the pool leak has occurred and the large volume of water infiltrated the subsoil. The complainant says that no cracks have appeared during the 23 years since the house was built and the pool remained level for this entire period. The insurer arranged for IL to review the material provided by the complainant and ONG Within a report dated 17 September 2018, IL pointed to the fact that conflicting and inconsistent information had been provided in relation to the soil content and footing systems employed at the site. Based on what it says are the inconsistencies in the information provided, IL called for further exploratory works to be carried out in order to establish an accurate assessment of the site conditions and therefore the impact for the leaking swimming pool. IL called for further information regarding the footings system together with geotechnical studies. The insurer advised that it was happy to appoint a geotechnical engineer to excavate boreholes adjacent to the footings of the swimming pool and dwelling, in order to confirm the depth and nature of the footing system. Determination | Case number: 526418 Page 6 of 12 Further, the insurer suggested a site classification and recommended founding material and depth should also be established. The insurer is willing to meet this cost. The insurer also advised that if any pavers are damaged during this process it would replace the damaged pavers to the closest possible match to the existing ones. Finally, the insurer advised that it was prepared to retract the claim decline until the additional investigations take place. The complainant seeks to rely upon the information already provided to support his position. Further, the complainant says that the existing tiles are unavailable and this would mean that all of the tiles would have to be replaced at a cost in excess of $40,000 which the insurer has not committed to. The complainant says that there are existing opinions from certified structural engineers as to the likely causes and cost of repairs. Discussion Having reviewed all of the exchanged material, the panel is not satisfied that it is in a position to make an accurate assessment of the cause of the damage at the complainant’s property. As stated, in order to determine the extent of the insurer’s obligations to the complainant, it is necessary to determine the proximate cause of the loss. Whilst the panel is conscious of the parties’ desire to resolve this matter, the panel is convinced that further information by way of geotechnical survey together with site classification and founding material depth should be established before any conclusion is reached regarding the proximate cause of the loss and thus the insurer’s obligation s to the complainant under the terms of the policy. The result is that upon acceptance of this determination by the complainant the insurer is, at its cost, to arrange for the further assessment as detailed within the report from IL dated 17 September 2018. As to the complainant’s concerns regarding damage to the property and in particular the tiles, as a result of the further assessment, the Product Disclosure Statement (PDS) details at pages 45 and 46: How we settle building claims If we agree to pay a claim for loss, theft or damage to the building, we will decide if we will: • repair damage to the building; Determination | Case number: 526418 Page 7 of 12 • rebuild the building; • pay you what it would cost us to repair or rebuild the building; • pay you the building sum insured shown on your certificate of insurance; Note: This does not apply if you have selected the Complete Replacement Cover® option. • give you a voucher, store credit or stored value card for the amount it would cost us to repair or rebuild an item. If we rebuild (or pay you what it would cost us to rebuild), we will do so on a `new for old’ basis. If we repair (or pay you what it would cost us to repair), we will at our option do so on a `new for old’ basis or repair to a similar condition to what the building was in before the loss or damage occurred. Unless we tell you otherwise, we will deduct any amounts you owe us from any amount we owe you. We will not: • pay more than the relevant sum insured (unless you have the Complete Replacement Cover® option) or policy limit; • pay extra to repair or rebuild the building to a better standard, specificat ion or quality than it was before the loss or damage occurred except as stated in the meaning of ‘new for old’; • fix a fault that existed before the loss or damage occurred. ‘New for old’ means: • New materials, new items we rebuild or repair with new items or new materials that are available at the time of replacement or repair from Australian suppliers. • New for old, regardless of age we rebuild or repair regardless of age, with no allowance for depreciation. • Same type, standard and specification as when new we replace or repair to the same type, standard and specification (but not brand) as when new. If the same is not available, it means of a similar type, standard and specification (but not brand) when new. We can replace with a different brand. ‘New for old’ does not: • include paying the extra cost of replacing or purchasing an extended warranty on any item; • mean of a better standard, specification or quality than when new. … When we authorise the repair or rebuilding of the building If we need to source material in order to repair or rebuild the building, we will do our best to obtain new materials that are the same type, standard and specification. If the same is not available, we will use new materials of a similar type, standard and specification that are commercially available and compliant with current building regulations. We may enter into any building contract with the selected repairer and/or supplier on your behalf. We will oversee the repairs and keep you informed of their progress. If you decide not to repair or replace the building, or do not commence repair or replacement within 6 months of the date the loss or damage occurred, we will only Determination | Case number: 526418 Page 8 of 12 compensate you for what it would have cost to repair or replace the building at the date of the loss or damage. When we cannot match materials If we cannot find new materials to match undamaged parts, we will use the closest match available to us. If you are not satisfied with the materials we find as the closest match before we repair the building: If we agree, you can pay the extra cost of replacing undamaged parts of the building to achieve a uniform appearance. Or we will pay you what it would have cost us to repair or rebuild the damaged part. Repairing or rebuilding damaged parts We will only repair or rebuild the parts that are damaged in the incident covered by your policy. You cannot claim to replace undamaged parts of the building to create a uniform appearance, such as when: • one garage door is damaged we will only replace or repair the damaged one, not other doors. • roof tiles are damaged we will only replace the damaged ones, not the undamaged tiles, even if the undamaged tiles are faded and do not match the new ones used for repairs. • roof sheeting is damaged we will only replace the damaged roof sheeting, not the undamaged roof sheeting, even if the closest match available to us is a different shade, colour, finish, material or profile to the undamaged roof sheeting. In respect of any damage caused by the further assessment, the insurer is to meet its obligations to the complainant in regard to that damage under the terms and conditions of the policy. The parties are requested to work together cooperatively in regard to the further assessment and to the resolution of the question of any further damage which may be caused during the course of that assessment. Having completed the further assessment, the insurer is to reassess its position with regard to the complainant’s claim and to ad vise the outcome of that reassessment within 14 days of having received the additional information required. In the event that the complainant does not accept this determination the insurer is to reinstate its offer for a period of 14 days. In the event that the complainant does not accept the reinstated offer, the insurer is not required to take any further action with regard to this matter. Determination | Case number: 526418 Page 9 of 12 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with F inancial O mbudsman S ervice (FOS) . This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint claim claim 3.2 AFCA approach to this complaint This dispute has not been the subject of a recommendation. Due to the nature of the dispute, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this case based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. The panel has reviewed and considered all of the material provided by the parties. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. Determination | Case number: 526418 Page 10 of 12 3.3 Relevant policy terms Escape of liquid (page 22 of PDS) We cover Loss or damage to the building caused by liquid leaking, overflowing or bursting from any of the following: …  swimming pools or spas; … What we do not cover - general exclusions (pages 35-40 of PDS) You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: … Ground movement erosion, vibration, subsidence, landslip, landslide, mudslide, collapse, shrinkage or any other earth movement, but we will cover landslide or subsidence that is specifically covered under the following insured events: • ‘Storm’; • ‘Flood’ (but only if you have cover for insured event ‘Flood’); • ‘Earthquake and Tsunami’; • ‘Explosion’. 3.4 Relevant expert reports Record Key points Insurer’s expert (IL ) Engineering Report 3 July 2017  Visual inspection carried out on 31 March 2017  Cracking was sight ed to the external render finish along the rear of the east elevation of the dwelling. A horizontal crack was located between the ground and upper floor and wa s approximately 3 - 5mm wide.  Further movement to this part of the dwelling was visible to the pavers throughout the rear courtyard.  Internal inspection of the dwelling found cracking and movement to the plasterboard lining to the upper floor through the middle of the dwelling. Cracks were approximately 3 - 5mm wide.  Minor cracks to plasterboard were visible to the south - west side of the building where diagonally cracking emanating from corners of door openings was sighted.  Hydrostatic measurements confirmed floor levels were very uneven with uniform settlement from east to west and north to south across the property. The south west side of the dwelling was found to be the lowest section of the building, Determination | Case number: 526418 Page 11 of 12 Record Key points with over 80mm of fall recorded across the footprint of the building. Similarly, uniform settlement was recorded to the swimming pool shell and the pool was found to fall towards the north end of the pool.  IL concluded t hat based on b ased on the vis ual inspection and information obtained t o date, th e y confir m damaged drainage, a leaking swimming pool shell and the abs ence of sufficient roof flas hing have all contributed to the cracking and movement of the building and paving, however these are deemed to have only exacerbated t he damage. The primary cause of m ovement to the structure and swimming pool is consolidation of founding fill material upon which the dwelling has been founded.  Geotechnical investigation into the nat ure of the fill on site would provide a profile of t he founding material and the potentia l for further consolidation.  Damaged drainage, insufficient flashing to the roof and a leaking swimming pool shell have exacerbated already existing damage. (20%)  The primary cause of damage to the dwelling and swimming pool is consolidation of the fill ma terial upon which the structures have been founded. (80% ) Complainant’s expert ( ON G ) Structural Inspection Report 16 July 2018  Visual inspection carried out on 6 July 2018  Observed noticeable tilting of the pool of some 30mm over a distance of approx. 14m of the pool length, which has occurred north to south end of the pool. Also observed was the settlement of the tiles adjacent to where the pool had cracked, as pointed out by the owner, and the cracking of the pool concourse tiles in this vicinity.  W ithout physically taking levels of this area, ON G said it appears that between the family/meals area and about 6 to 7 metres south of this now, this area of the pool concourse has suffered a settlement in the surfac e.  ON G concluded the amount of water t hat has leak ed (some 1000 litres per day over the period of 8 November 2016 to Feb 2017) int o the clay bearing soils, has in their opinion totally caused the softening of the bearing clays in t his area and primarily c aused t he pool t o tilt. ON G estimate the pool damage to be approximately 80% account able.  Since the pool was repaired, the pool concourse tiles also immediat ely adjacent to pool crack zone have recently cracked, most probably due to the area drying out beneath t he concrete slab supporting the tiled pavement.  With respect to the dwelling, as it is support ed on steel driven piles, (as informed by the Owner), ON G is of the opinion that, the damage caused by the pool leakage is to a lesser extent and is also depende nt upon the driven depth of the piles. From our observation and in viewing of photographic evidence provided by the owner, ON G is of Determination | Case number: 526418 Page 12 of 12 Record Key points the opinion t hat the cracking and damage caused by the pool leakage approximately 40% accountable. Complainant’s expert ( O N G ) Supplement ary Structural Inspection Report 25 S eptember 2018  Subsidence has occurred at t he northern end of the pool which is exactly where t he pool leak has occurred and the large volume of water infiltrated the subs oil. This subsidence cannot simply be attribut ed to settlement caused by long term reduction of the moisture content of the soils as suggested by the Insurer in their assessment report.  The insured has also forwarded two photographs that were taken on 14 th February 2017, after the po ol leak, which show the concourse tiling having lifted and cracked in the vicinity where the pool was leaking. ON G said the damage in their opinion has occurred primarily from the pool leakage event and not as a result of the long - term consolidation of the fill material.  Given the amount of water that leaked over the period of 8 November 2016 to February 2017, into the clay bearing soils ON G said this is in their opinion t he primary cause of the softening of the clays and also caused th e pool to tilt. The major weather event in December 2016 was also in their opinion a cont ributing factor both to the crack emerging and to water flowing under the pool.  With respect to the house, quite clearly, the cracking that occurred to the ceiling of the house after the pool leakage was primarily caused by the settlement having occurred adjacent to the pool cracked zone.  The subsidence cannot simply be attributed to settlement caused by long term reduction of the moisture content of the soils as sugges ted by the Insurer in the assessment report.  Were this to be the cas e, the s outhern end of the pool where t here is the most amount of fill would have settled more than any where else but in fact, this area has not subsided. ON G is of t he opinion that in ord er to achieve a reinstatement as “built condition” to both the pool and the house, relevelling of both the pool and the house should be carried out by experienced companies dealing specifically with these issues.  As the leaking of the pool resulted in subs idence and subsequent damage to both the pool concourse add to the house, all costs associated with repairs including re - levelling should be considered as part of this claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.