Determination 525898
Overall management of fire damage claim and delay in paying repair costs
Summary
A landlord's fire damage claim was initially declined, then accepted on internal review, but repair cost reimbursement was delayed and the claim was poorly managed. AFCA ordered payment of the outstanding repair invoices and $250 for non-financial loss.
The insurer delayed settlement of the claimed costs beyond what was reasonable, causing an unusual degree of interference with peace of mind that warrants non-financial loss compensation under the Terms of Reference.
Subjects and remedies
home or building damagepay claimpay non financial loss
Text of the determination
Determination
Case No: 525898 Determination Page 1 of 4
Case number: 525898 27 September 2018
1 Overview
1.1 Dispute
The applicant holds a landlord insurance policy (the policy) with the financial services
provider (FSP) covering the insured property. On 22 February 2018, the applicant
lodged a claim for fire damage to the insured property which the FSP declined.
However, this decision was reversed through the FSP’s internal dispute resolution
process.
The applicant remains dissatisfied with t he FSP’s overall management of the claim
as well as seeks reimbursement of repairs costs he has incurred in authorising
assessment of and repairs to the insured property.
1.1 Issues and key findings
Has the FSP’s management of the applicant’s claim been reaso nable?
The available information establishes, although the FSP has now agreed to cover the
applicant for the costs incurred/claimed in line with the policy, its overall management
of the claim has been less than ideal.
Is the applicant entitled to compensation under the claim?
The FSP is to arrange payment of $250 to the applicant by way of compensation for
non-financial loss in line with the with the FOS Terms of Reference (TOR).
1.2 Determination
This determination is substantially in favour of the applicant.
The FSP’s overall management of the claim has been less than ideal. The FSP, in
addition to the applicant’s claim entitlements, is to arrange payment of $250 by way
compensation for non-financial loss.
Case No: 525898 Determination Page 2 of 4
2 Reasons for determination
2.1 Has the FSP’s management of the claim been reasonable?
The FSP’s overall management of the claim has been less than ideal
I note, at the time this dispute was lodged with FOS, there were several concerns
raised by the applicant regarding the claim lodged with the FSP. I am satisfied
several of these concerns have since been resolved between the parties over the
course this dispute. Therefore, in providing this determination, consideration will be
limited to only those matters that remain unresolved.
Having considered the available information, I am satisfied on the balance of
probabilities it establishes the following:
the insured property suffered fire damage for which the applicant lodged a claim
the claim was declined by the FSP however on further review through its
internal dispute resolution process, the claim was accepted
the FSP appointed consultants ‘H’ to assess and provide a quote for the cost of
repairs to be completed under the claim
the applicant raised several concerns regarding the accuracy of H’s assessment
and conduct
the applicant provided the FSP with quotes and invoices for repairs he had
authorised relating to the claim which remained unpaid until such time the
dispute was brought to FOS
the FSP has now agreed to pay and confirmed payment in the amounts of
$2,050.62 and $308 have been prepared to the applicant as claimed
the FSP has consistently maintained through the FOS dispute process it is
prepared to arrange payment but could not do so until the applicant provides
information (quotes/invoice) to support the claimed loss
the applicant says this information was provided to the FSP months prior
however again provided the requested information via FOS on 9 September
2018.
I am satisfied the available information establishes the applicant’s experience under
the claim has been less ideal than from the start (claim initially declined). The
decision was eventually reversed by the FSP however there then arose concerns
regarding the assessment completed by H and repairs costs incurred by the
applicant. I note, by way of an agreement with the applicant reached with the
assistance of FOS in May 2018, the FSP agreed to replace H with different
consultants moving forward.
As part of this agreement, the FSP accepted to reimburse the applicant for his out of
pocket expenses incurred in authorising repairs to damage caused by the fire event.
The applicant contacted FOS several months later to request the dispute be re -
opened as the FSP had failed honour the agreement the parties had come to in May
2018.
The dispute was re-opened and I note the FSP, although continued to maintain it was
prepared to cover the applicant’s out of pocket expenses, was still maintain the
Case No: 525898 Determination Page 3 of 4
position that the applicant has not provided the requested supporting information.
The applicant did eventually provide this information via FOS and payment (as noted
above) has been prepared to the applicant. However, I note the FSP’s final internal
dispute resolution (IDR) communication to the applicant in May 2018, offers to
arrange a cash settlement and clearly refers to supporting information received
regarding the costs claimed.
Without compelling information to the contrary, I am satisfied this on balance
establishes the applicant had sent the FSP supporting information for the costs
claimed months prior as claimed. Further, the applicant has also provided a copy of
communication sent to the FSP on 12 June 2018, which included the supporting
information relating to the costs incurred and being claimed from the FSP.
Therefore, I am satisfied the FSP has dela yed the settlement of the applicant’s claim
beyond what would be considered reasonable. In line with the reasons discussed
above, I am satisfied the FSP’s overall management of the applicant’s claim has
been less than ideal. The claimed costs should have been settled much earlier by the
FSP.
In the interest of completeness, I acknowledge the applicant (as part of his expected
resolution) wants the FSP to respond to all questions he has put to it in his
communications. However, I am not in a position to enforce this upon the FSP, the
decision as to whether all the questions/concerns are actually addressed rests with
the FSP and not FOS.
The FSP is to arrange payment of the outstanding invoices referred to above, if it has
not already done so, within seven days of the applicant accepting this determination.
2.2 Is the applicant entitled to compensation under the claim?
The FSP is to pay the applicant $250 in compensation for non-financial loss
The TOR allow for an award of compensation for non-financial loss up to a maximum
award of $3,000. Such an award is subject to consideration as to whether there has
occurred an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the a pplicant’s expectation of enjoyment or
peace of mind.
In line with the matters discussed above, I am satisfied there has occurred an undue
delay in finalising the applicant’s claim for costs incurred in repairing damage
covered under the claim. This will reasonably have occurred in an unusual degree or
extent of interference with the applicant’s peace of mind.
Accordingly, I determine the FSP is to arrange payment of $250 to the applicant by
way of compensation for non-financial loss under the claim.
Case No: 525898 Determination Page 4 of 4
3 Supporting information
TOR 9.3
9.3 Other compensation
...
b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the
Financial Services Provider Compensate the Applicant for non-financial
loss but only where:
(i) An unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with the Applicant’s
expectation of enjoyment or peace of mind has occurred; or
(ii) In the case of a Dispute pertaining to an individual’s privacy rights
– injury has occurred to the Applicant’s feelings or humiliation has
been suffered by the Applicant.
The maximum amount of compensation for non-financial loss will be $3,000 per claim
made in the Dispute. …