Home / Financial Firm (Unknown - Insurer) / Determination 524062

Determination 524062

Claim for storm damage to private jetty declined for faulty workmanship and structural fault

FirmFinancial Firm (Unknown - Insurer)
Decided2018-10-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's private jetty was damaged in a December 2016 storm and the FSP declined the claim for faulty workmanship. AFCA found the poles were not embedded to the required depth but that the storm may have damaged the jetty anyway, so it ordered the FSP to accept 40% of the claim with statutory interest.

The FSP showed the poles were too shallow, but the severity of the storm meant the jetty would not necessarily have withstood it even if built to specification, so the exclusion did not defeat the whole claim.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 524062 Determination Page 1 of 6 Case number: 524062 19 October 2018 1 Overview 1.1 Dispute This dispute arose after the applicant made a claim on his rural home policy on 5 January 2017, for damage to his private jetty following a storm on 27 December 2016. The financial services provider (FSP) denied the claim, as it says the dominant cause of the damage is the fact that the jetty was not built to specifications. The policy excludes damage that has been caused by structural fault, faulty design or faulty workmanship, as well as damage caused by erosion. The applicant disputes the FSP’s decision, and says that he built the jetty to the required specifications. He seeks for the FSP to accept his claim. 1.2 Issues and key findings Has the applicant established a valid claim under the policy? The policy provides cover for accidental damage, including to jetties. The applicant has established that there was accidental damage to the jetty after a storm. The applicant has therefore established a valid claim. Can the FSP deny the claim? On the balance of probabilities, and based on the evidence presented, the Panel is satisfied that the applicant did not insert the jetty poles to the required depth of 1000mm. Both the FSP’s and the applicant’s own engineer considered this more likely than not. The policy excludes cover in the case of a structural fault or faulty workmanship. However, given the severity of the weather at the time of the loss event, the Panel is also not satisfied that the jetty would have withstood the storm, even if the poles had been inserted to the correct depth. The Panel considers it fair in the circumstances the FSP accepts 40% of the claim. 1.3 Determination This determination is substantially in favour of the FSP. The FSP must accept 40% of the claim. The FSP must also pay interest on this amount, from the date of claim denial until the date of payment. Case No: 524062 Determination Page 2 of 6 2 Reasons for determination 2.1 Has the applicant established a valid claim under the policy? Policy provides cover for accidental damage The applicant is required to establish that, on the balance of probabilities, he suffered a loss caused by a risk insured against the policy. This is known as establishing a valid claim. The policy wording, together with the certificate of insurance, outline the conditions under which cover is provided, and the exclusions that apply to that cover. This is a rural farm policy that provides cover for accidental damage. The FSP confirmed in a text message to the applicant that the policy covered his private jetty. In the context of insurance claims, accidental damage means damage caused by events which are neither expected nor intended. There is no dispute between the parties that there was a storm in the area at the relevant time. The FSP’s engineer (E) noted there was heavy rainfall and strong winds in December 2016, and that the jetty was likely to have experienced ‘stronger and similar prevailing winds’. The jetty was pulled out of the water and tipped upside down during the storm, with only the end return remaining undamaged. There is no dispute that the damage was neither expected nor intended. The applicant has therefore established a valid claim for accidental damage under the policy. 2.2 Can the FSP deny the claim? FSP says damage due to jetty poles not being inserted deeply enough As the applicant has established a valid claim, the onus now shifts to the FSP to show that is entitled to deny the claim, either due to the operation of an exclusion or otherwise. The FSP must prove the operation of the exclusion on the balance of probabilities. The FSP notes the policy excludes cover in the case of ‘s tructural fault, faulty workmanship or faulty materials’. E said that the jetty’s poles were not inserted into the ground to the required depth of 1,000mm during construction, but rather, were only inserted to depths ranging between 690mm and 900mm, and that this caused the jetty to fail in the storm. It based this on its measurements of the poles, and notes that its assessor’s (A’s) findings corresponded with its results. The applicant said that the poles were inserted to a depth of 1,000mm, however the ground into which the poles were inserted has eroded over time (and that this is why the depths appear lower now). Case No: 524062 Determination Page 3 of 6 However, the applicant’s own engineer (T) also found that the poles were not embedded deeply enough. T noted that the staining on the posts indicated the posts varied in depth below ground level from 700mm to 1,000mm. T conducted a hand auger borehole measurement at the water’s edge of the former jetty, which indicated a soil profile of 50mm of sand overlaying a stiff sandy silty clay. T found that even if the lake bed had a 50mm layer of sand, which was eroded over time, it is unlikely that the specified 1,000mm embedment was achieved. Applicant provided other information to show he complied with specifications Whilst the onus is on the FSP to establish the operation of the exclusion, the applicant also provided some other information in support of his position. The applicant provided a signed statement from M, who helped him construct the jetty. M said: I am writing to inform you that I can verify working with [applicant] to construct the jetty at his property at [address]. I can also verify that the posts of the jetty were rammed into the ground to the one metre measurement marked on the posts as per required specification. The FSP argued that M is a painting co ntractor and that the applicant has not provided evidence to establish M’s expertise in this field. The FSP contrasts this with its own reports, which it says have been provided by qualified experts. The Panel accepts the FSP’s argument as valid. However, it also notes that the statement has been provided by someone who was working with the applicant on the jetty at the time, and therefore witnessed first-hand the work that was completed. The applicant also provided a letter from his partner in support of his claim: Since the purchase of the property and transfer of the licence for the jetty in our names we have done everything required and adhered to all requirements from every department involved. At the time that the Jetty was being built [the applicant] was working at the [relevant local] council in Civil construction and is very diligent in all he does, wherever he works, so to imply that the post were not in the correct distance is simply not true. So instead of repairing we replaced the Jetty in acco rdance with the engineer’s drawings we wanted the jetty to be structurally stronger and safer than the previous one for generations to come. As with M’s evidence, though, no information has been provided to establish T’s expertise in this field. Further, the Panel notes that T has also not advised that she personally witnessed the applicant adhering to the building requirements. The applicant advised that the construction was approved by the local council. However, it was later confirmed that the Council approval was for undertaking construction, rather than it approving any completed construction. Also, a council member (the applicant’s friend), noted in a phone conversation with FOS that the council issues building approval, but does not inspect jetties after they have been built. The applicant’s friend noted that this is not a structure the council would inspect. Case No: 524062 Determination Page 4 of 6 Evidence shows jetty poles were likely not inserted to required depth Although M’s statement carries some weight as he was with the applicant a t the time of construction of the jetty, based on the bulk of information presented to FOS, and on the balance of probabilities, I consider it more likely than not that the poles were not embedded to the required depth of 1,000mm. Notably, even the Applica nt’s own engineer held this view. The FSP also raised that the applicant did not use the correct method to insert the poles, as it says the applicant excavated the soil and then backfilled the area, rather than ‘ramming’ the poles in. However, the applicant provided a statement to say that he drilled the poles in (i.e. ‘rammed’ them in) with a tractor, during a time of drought. M also confirmed in his statement that the poles were rammed in. On the balance of probabilities, I accept that the poles were rammed in. Jetty may have been damaged even if poles were inserted as per specifications Although the Panel considers that the poles were not built to the required depth, the severity of the storm also needs to be considered in assessing what is a fair outcome. Importantly, E’s first report noted that it was ‘possible that there were significantly higher/stronger winds at the location, including localised wind mini-tornadoes or microbursts around the jetty’. E also noted that the state weather bureau’s Monthl y Weather Review for December 2016 noted there was very heavy rainfall and damaging winds affecting large parts of the state in this month. E noted that the wind at the time of the jetty failure was coming from a north westerly direction, and reaching maximum speeds of 78km/hr, which is high. The applicant submitted anecdotal evidence that the jetty had previously survived many storms and had been underwater twice, with no structural damage at all. He stated that the ‘severe freak storm’ resulted in huge wa ves that pulled the jetty out of the ground and onto its side, and that the constant surge of waves then broke the jetty up into sections. The Panel is not completely satisfied, based on the evidence presented by both parties, that the jetty would have withstood the storm event if it had been built to specifications, especially given E’s advice that it was possible that there were localised wind mini-tornadoes or microbursts around the jetty, and there was very heavy rainfall and damaging winds in that month. The Panel therefore considers it fair that the FSP accepts 40% of the claim. The FSP must also pay statutory interest on this amount, pursuant to section 57 of the Insurance Contracts Act 1984 (Cth). Interest is payable from the date of claim denial until the date of payment. Case No: 524062 Determination Page 5 of 6 3 Supporting information 3.1 Key references Policy and other related documents Document Provision Product Disclosure Statement 01 - 01 - 2015 Page 18 The events You are insured against 1 Accidental damage but not for: loss or damage directly or indirectly caused by or arising out of: … – a structural fault, faulty workmanship or faulty materials Page 50 What You are insured against This policy insures You against Accidental damage, burglary and theft occurring during the Period of In surance. Page 50 What is not insured This policy does not insure You against: 1 damage directly caused by: … earth movement no matter how caused, including erosion, vibration, subsidence, seepage, saturation, creeping, landslip, mudslide, collapse, shrinkage, settling, expansion or heaving, unless the damage occurs within 72 hours of, and is directly caused by: … c) Storm water or Flood, and Your Certific ate of Insurance for this policy states under the heading ‘Flood cover’: ‘Your policy includes co ver for damage caused by Flood’. 2 damage directly or indirectly caused by or arising out of:  a structural fault, faulty design or faulty workmanship performed by You Text message from FSP to Applicant 5 January 2017 ‘Hi [Applicant]. Your home cover inclu des private jetties so I will get a claim open for the damage the storm did to it. Cheers [FSP’s representative].’ Expert reports and other related documents Record Key points FSP engineer’s (E’s) 1 st report 22 June 2017  [The State weather bureau’s] Monthly Weather Review for December 2016 states that there was very heavy rainfall and damaging winds affecting large parts of the State.  It was possible that there were significantly higher/stronger winds at the location, including localised wind mini - t or nadoes or microbursts around the jetty.  The posts were buried less than 900mm into the soil and the posts were not Case No: 524062 Determination Page 6 of 6 rammed into the soil, but rather dug and backfilled. Letter from Applicant 18 August 2017  The poles for the jetty were drilled and rammed into the ground using a tractor to a depth of 1 metre, as per the engineer’s instructions.  The poles were 1 metre deep. Due to erosion on the dry land at the time, and then the wash from the lake around the poles over the years, the exact depth is hard to determine.  The jetty has survived many storms and been underwater twice, with no structural damage at all.  The severe freak storm had huge waves which pulled the jetty out of the ground and onto its side. The constant surge of the waves broke the jetty in to sections.  Perhaps there would have been less damage if the poles were deeper into the ground, but the jetty was built to specifications. E’s 2 nd report 2 February 2018  The posts’ embedment depths range from 690mm to 900mm. The assessor’s results for th is matched E’s results.  It does not believe that there would be over 200mm of soil settlement around the posts due to water currents and erosion, unless the post holes were excavated and backfilled wit hout compaction, whic h does not coincide with the insur ed’s report or the requirements set out in the drawings.  In the alternative, erosion and settlement (i.e. a gradual process reducing the jetty’s structural capacity) caused the jetty to fail [not the storm]. FSP assessor’s (A’s) report 6 February 2018  Considered E’s findings.  Erosion would be a gradual deterioration of the jetty structure’s integrity, which is excluded under the PDS.  If the jetty posts were not installed to the required depth, then policy exclusion of faulty workmanship should apply.  Ap plicant’s claim should be denied. Applicant’s engineer’s (T’s) report 10 July 2018  Poles were generally embedded less than the specified 1000mm depth into the soil for a notable period of time prior to the storm event, leading to the failure of the jetty  The jetty poles were likely embedded less than the specified 1000mm at the time of failure.  It is possible that the 1000mm embedment depth at the time of construction was achieved with erosion at the top of the soil profiling occurring after the lake was f illed. However, noted that even if the lake bed had a 50mm lawyer of sand, similar to the hand auger taken adjacent to the lake, it is unlikely the specified 1000mm embedment was achieved.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.