Claim for storm damage to private jetty declined for faulty workmanship and structural fault
Text of the determination
Determination
Case No: 524062 Determination Page 1 of 6
Case number: 524062 19 October 2018
1 Overview
1.1 Dispute
This dispute arose after the applicant made a claim on his rural home policy on 5
January 2017, for damage to his private jetty following a storm on 27 December
2016.
The financial services provider (FSP) denied the claim, as it says the dominant cause
of the damage is the fact that the jetty was not built to specifications. The policy
excludes damage that has been caused by structural fault, faulty design or faulty
workmanship, as well as damage caused by erosion.
The applicant disputes the FSP’s decision, and says that he built the jetty to the
required specifications. He seeks for the FSP to accept his claim.
1.2 Issues and key findings
Has the applicant established a valid claim under the policy?
The policy provides cover for accidental damage, including to jetties. The applicant
has established that there was accidental damage to the jetty after a storm. The
applicant has therefore established a valid claim.
Can the FSP deny the claim?
On the balance of probabilities, and based on the evidence presented, the Panel is
satisfied that the applicant did not insert the jetty poles to the required depth of
1000mm. Both the FSP’s and the applicant’s own engineer considered this more
likely than not. The policy excludes cover in the case of a structural fault or faulty
workmanship.
However, given the severity of the weather at the time of the loss event, the Panel is
also not satisfied that the jetty would have withstood the storm, even if the poles had
been inserted to the correct depth.
The Panel considers it fair in the circumstances the FSP accepts 40% of the claim.
1.3 Determination
This determination is substantially in favour of the FSP.
The FSP must accept 40% of the claim. The FSP must also pay interest on this
amount, from the date of claim denial until the date of payment.
Case No: 524062 Determination Page 2 of 6
2 Reasons for determination
2.1 Has the applicant established a valid claim under the policy?
Policy provides cover for accidental damage
The applicant is required to establish that, on the balance of probabilities, he suffered
a loss caused by a risk insured against the policy. This is known as establishing a
valid claim.
The policy wording, together with the certificate of insurance, outline the conditions
under which cover is provided, and the exclusions that apply to that cover.
This is a rural farm policy that provides cover for accidental damage. The FSP
confirmed in a text message to the applicant that the policy covered his private jetty.
In the context of insurance claims, accidental damage means damage caused by
events which are neither expected nor intended.
There is no dispute between the parties that there was a storm in the area at the
relevant time. The FSP’s engineer (E) noted there was heavy rainfall and strong
winds in December 2016, and that the jetty was likely to have experienced ‘stronger
and similar prevailing winds’. The jetty was pulled out of the water and tipped upside
down during the storm, with only the end return remaining undamaged.
There is no dispute that the damage was neither expected nor intended. The
applicant has therefore established a valid claim for accidental damage under the
policy.
2.2 Can the FSP deny the claim?
FSP says damage due to jetty poles not being inserted deeply enough
As the applicant has established a valid claim, the onus now shifts to the FSP to
show that is entitled to deny the claim, either due to the operation of an exclusion or
otherwise. The FSP must prove the operation of the exclusion on the balance of
probabilities.
The FSP notes the policy excludes cover in the case of ‘s tructural fault, faulty
workmanship or faulty materials’.
E said that the jetty’s poles were not inserted into the ground to the required depth of
1,000mm during construction, but rather, were only inserted to depths ranging
between 690mm and 900mm, and that this caused the jetty to fail in the storm. It
based this on its measurements of the poles, and notes that its assessor’s (A’s)
findings corresponded with its results.
The applicant said that the poles were inserted to a depth of 1,000mm, however the
ground into which the poles were inserted has eroded over time (and that this is why
the depths appear lower now).
Case No: 524062 Determination Page 3 of 6
However, the applicant’s own engineer (T) also found that the poles were not
embedded deeply enough.
T noted that the staining on the posts indicated the posts varied in depth below
ground level from 700mm to 1,000mm.
T conducted a hand auger borehole measurement at the water’s edge of the former
jetty, which indicated a soil profile of 50mm of sand overlaying a stiff sandy silty clay.
T found that even if the lake bed had a 50mm layer of sand, which was eroded over
time, it is unlikely that the specified 1,000mm embedment was achieved.
Applicant provided other information to show he complied with specifications
Whilst the onus is on the FSP to establish the operation of the exclusion, the
applicant also provided some other information in support of his position.
The applicant provided a signed statement from M, who helped him construct the
jetty. M said:
I am writing to inform you that I can verify working with [applicant] to construct the jetty at
his property at [address]. I can also verify that the posts of the jetty were rammed into the
ground to the one metre measurement marked on the posts as per required specification.
The FSP argued that M is a painting co ntractor and that the applicant has not
provided evidence to establish M’s expertise in this field. The FSP contrasts this with
its own reports, which it says have been provided by qualified experts.
The Panel accepts the FSP’s argument as valid. However, it also notes that the
statement has been provided by someone who was working with the applicant on the
jetty at the time, and therefore witnessed first-hand the work that was completed.
The applicant also provided a letter from his partner in support of his claim:
Since the purchase of the property and transfer of the licence for the jetty in our names we
have done everything required and adhered to all requirements from every department
involved.
At the time that the Jetty was being built [the applicant] was working at the [relevant local]
council in Civil construction and is very diligent in all he does, wherever he works, so to
imply that the post were not in the correct distance is simply not true. So instead of
repairing we replaced the Jetty in acco rdance with the engineer’s drawings we wanted the
jetty to be structurally stronger and safer than the previous one for generations to come.
As with M’s evidence, though, no information has been provided to establish T’s
expertise in this field. Further, the Panel notes that T has also not advised that she
personally witnessed the applicant adhering to the building requirements.
The applicant advised that the construction was approved by the local council.
However, it was later confirmed that the Council approval was for undertaking
construction, rather than it approving any completed construction.
Also, a council member (the applicant’s friend), noted in a phone conversation with
FOS that the council issues building approval, but does not inspect jetties after they
have been built. The applicant’s friend noted that this is not a structure the council
would inspect.
Case No: 524062 Determination Page 4 of 6
Evidence shows jetty poles were likely not inserted to required depth
Although M’s statement carries some weight as he was with the applicant a t the time
of construction of the jetty, based on the bulk of information presented to FOS, and
on the balance of probabilities, I consider it more likely than not that the poles were
not embedded to the required depth of 1,000mm. Notably, even the Applica nt’s own
engineer held this view.
The FSP also raised that the applicant did not use the correct method to insert the
poles, as it says the applicant excavated the soil and then backfilled the area, rather
than ‘ramming’ the poles in.
However, the applicant provided a statement to say that he drilled the poles in (i.e.
‘rammed’ them in) with a tractor, during a time of drought. M also confirmed in his
statement that the poles were rammed in. On the balance of probabilities, I accept
that the poles were rammed in.
Jetty may have been damaged even if poles were inserted as per specifications
Although the Panel considers that the poles were not built to the required depth, the
severity of the storm also needs to be considered in assessing what is a fair
outcome.
Importantly, E’s first report noted that it was ‘possible that there were significantly
higher/stronger winds at the location, including localised wind mini-tornadoes or
microbursts around the jetty’.
E also noted that the state weather bureau’s Monthl y Weather Review for December
2016 noted there was very heavy rainfall and damaging winds affecting large parts of
the state in this month. E noted that the wind at the time of the jetty failure was
coming from a north westerly direction, and reaching maximum speeds of 78km/hr,
which is high.
The applicant submitted anecdotal evidence that the jetty had previously survived
many storms and had been underwater twice, with no structural damage at all. He
stated that the ‘severe freak storm’ resulted in huge wa ves that pulled the jetty out of
the ground and onto its side, and that the constant surge of waves then broke the
jetty up into sections.
The Panel is not completely satisfied, based on the evidence presented by both
parties, that the jetty would have withstood the storm event if it had been built to
specifications, especially given E’s advice that it was possible that there were
localised wind mini-tornadoes or microbursts around the jetty, and there was very
heavy rainfall and damaging winds in that month.
The Panel therefore considers it fair that the FSP accepts 40% of the claim.
The FSP must also pay statutory interest on this amount, pursuant to section 57 of
the Insurance Contracts Act 1984 (Cth). Interest is payable from the date of claim
denial until the date of payment.
Case No: 524062 Determination Page 5 of 6
3 Supporting information
3.1 Key references
Policy and other related documents
Document Provision
Product Disclosure
Statement
01 - 01 - 2015
Page 18
The events You are insured against
1 Accidental damage
but not for:
loss or damage directly or indirectly caused by or arising out of:
…
– a structural fault, faulty workmanship or faulty materials
Page 50 What You are insured against
This policy insures You against Accidental damage, burglary and theft
occurring during the Period of In surance.
Page 50 What is not insured
This policy does not insure You against:
1 damage directly caused by:
…
earth movement no matter how caused, including erosion, vibration,
subsidence, seepage, saturation, creeping, landslip, mudslide, collapse,
shrinkage, settling, expansion or heaving, unless the damage occurs within 72
hours of, and is directly caused by:
…
c) Storm water or Flood, and Your Certific ate of Insurance for this policy states
under the heading ‘Flood cover’: ‘Your policy includes co ver for damage
caused by Flood’.
2 damage directly or indirectly caused by or arising out of:
a structural fault, faulty design or faulty workmanship performed by You
Text message from
FSP to Applicant
5 January 2017
‘Hi [Applicant]. Your home cover inclu des private jetties so I will get a claim
open for the damage the storm did to it. Cheers [FSP’s representative].’
Expert reports and other related documents
Record Key points
FSP engineer’s
(E’s) 1 st report
22 June 2017
[The State weather bureau’s] Monthly Weather Review for December 2016
states that there was very heavy rainfall and damaging winds affecting large
parts of the State.
It was possible that there were significantly higher/stronger winds at the
location, including localised wind mini - t or nadoes or microbursts around the
jetty.
The posts were buried less than 900mm into the soil and the posts were not
Case No: 524062 Determination Page 6 of 6
rammed into the soil, but rather dug and backfilled.
Letter from
Applicant
18 August 2017
The poles for the jetty were drilled and rammed into the ground using a
tractor to a depth of 1 metre, as per the engineer’s instructions.
The poles were 1 metre deep. Due to erosion on the dry land at the time,
and then the wash from the lake around the poles over the years, the exact
depth is hard to determine.
The jetty has survived many storms and been underwater twice, with no
structural damage at all.
The severe freak storm had huge waves which pulled the jetty out of the
ground and onto its side. The constant surge of the waves broke the jetty
in to sections.
Perhaps there would have been less damage if the poles were deeper into
the ground, but the jetty was built to specifications.
E’s 2 nd report
2 February 2018
The posts’ embedment depths range from 690mm to 900mm. The
assessor’s results for th is matched E’s results.
It does not believe that there would be over 200mm of soil settlement around
the posts due to water currents and erosion, unless the post holes were
excavated and backfilled wit hout compaction, whic h does not coincide with
the insur ed’s report or the requirements set out in the drawings.
In the alternative, erosion and settlement (i.e. a gradual process reducing the
jetty’s structural capacity) caused the jetty to fail [not the storm].
FSP assessor’s
(A’s) report
6 February 2018
Considered E’s findings.
Erosion would be a gradual deterioration of the jetty structure’s integrity,
which is excluded under the PDS.
If the jetty posts were not installed to the required depth, then policy
exclusion of faulty workmanship should apply.
Ap plicant’s claim should be denied.
Applicant’s
engineer’s (T’s)
report
10 July 2018
Poles were generally embedded less than the specified 1000mm depth into
the soil for a notable period of time prior to the storm event, leading to the
failure of the jetty
The jetty poles were likely embedded less than the specified 1000mm at the
time of failure.
It is possible that the 1000mm embedment depth at the time of construction
was achieved with erosion at the top of the soil profiling occurring after the
lake was f illed. However, noted that even if the lake bed had a 50mm lawyer
of sand, similar to the hand auger taken adjacent to the lake, it is unlikely the
specified 1000mm embedment was achieved.