Leak and mould claim: cash settlement offer for remediation and repairs held unreasonable
Text of the determination
Determination | Case number: 524028 Page 1 of 14
Case number: 524028 30 October 2018
1 Determination overview
1.1 Complaint
The complainant lodged a home building insurance claim for a leak in February 2016,
which the financial firm (insurer) accepted. During repairs the insurer found a second
cause of mould and accepted a claim for damage caused by a leaking storm water
pipe in the subfloor.
The insurer offered to cash settle the complainant $31,432.85 for building repairs and
$10,771.53 for mould remediation.
The complainant is dissatisfied with this amount because he says it does not reflect
the extent of mould or building damage. He wants the insurer to carry out remediation
and repairs, or to increase the cash settlement amount based on quotes and reports
he provided. He also says the insurer handled the claims poorly and wants it to:
continue paying temporary accommodation until repairs finish
reimburse the costs of mould and the loss assessment reports.
1.2 Issues and key findings
Is the insurer entitled to cash settle the stormwater drain claim?
Is the insurer’s cash settlement offer reasonable?
The insurer’s offer is not reasonable because despite fully accepting the claim, its
offers (in error) reflect a limited scope of damage. The insurer is required to cash
settle the complainant’s quotes for mould remediation, building repairs, air systems
and professional/expert reports, together with an allowance for contingencies and
interest.
Did the insurer fully settle the other claims?
The insurer is entitled to cash settle the remaining laundry leak repairs based on its
builder’s quote. It is to pay the complainant a further 30 weeks accommodation.
Is the complainant entitled to non-financial loss compensation? The FSP is entitled to cash settle repair costs because its engineer confirmed repairs
will only be effective if subfloor maintenance work is also completed by the applicant.
Determination | Case number: 524028 Page 2 of 14
As the insurer refusal to provide a fair cash settlement offer, or extend the temporary
accommodation caused the complainant’s family significant stress, it is to pay $2,000
compensation in non-financial loss.
1.3 Determination
This determination is in favour of the complainant.
Within seven days of the complainant accepting this Determination, the insurer is
required to pay the amounts outlined in Section 2.2, 2.3 and 2.4.
Determination | Case number: 524028 Page 3 of 14
2 Reasons for determination
2.1 Is the insurer entitled to cash settle the stormwater drain claim?
The insurer accepted two water and mould damage claims
The complainant lodged a claim on 19 February 2016 for water damage from a leak in
the laundry, which the insurer accepted. During repairs in September 2016, the
insurer’s first building contractor (JP) found mo uld under the tiles. In October 2016,
the insurer’s hygienist reported a second cause of mould was likely and
recommended investigation. It is unclear why no investigation, apart from confirming
prior leak detection results, occurred at this time.
In February 2017, the insurer ’s contractor (FR) finished remediation of mould caused
by the laundry leak and provided a clearance certificate for JP to commence repairs.
On 15 March 2017, the complainant notified the insurer about more mould. The
insurer decided to investigate a possible second cause of mould and if this existed,
whether the complainant could then lodge a separate claim. On 22 May 2017, the
insurer engaged an engineer (EN), who attended the property three days later.
The insurer received EN’s repo rt on 29 June 2017. EN reported mould occurred due
to a leaking stormwater pipe in the subfloor and poor subfloor ventilation and the
insurer accepted the claim. Its technical specialist (PD) asked the complainant to
carry out subfloor-related maintenance works EN said were necessary to allow
effective mould remediation works and building repairs.
The complainant wants the insurer to repair building or increase settlement
offer
On 18 August 2017 the insurer said it would cash settle the claim due to:
the necessary maintenance works the complainant needed to do before effective
repairs and remediation could start
its contractors being unable to warrant repairs, given the presence of the subfloor’s
ventilation issues.
Based on its second building contractor’s (AJ’s) quotes, the insurer offered the
complainant $31,432.85 for building repairs and $10,771.53 for mould remediation.
The complainant says AJ’s scope of works does not reflect the true restoration costs.
He wants the insurer to repair the building or increase its settlement offer and says he
has been unable to complete the final subfloor maintenance works due to the
insurer’s inadequate settlement offer. He provided a written statement from his builder
(DR) stating the (complainant ’s own) subfloor vent ilation (maintenance) works could
be completed only after specific mould remediation works in the subfloor.
Determination | Case number: 524028 Page 4 of 14
Subfloor ventilation issues make cash settlement reasonable
The policy wording outlined in the product disclosure statement (PDS) provides the
insurer with the discretion to repair damage, or pay a cash settlement to the
complainant (contained in Section 3.2).
The Service expects an insurer to exercise this discretion fairly in all the
circumstances.
Given the repairs and remediation required, the panel considers it is fair for the
insurer to cash settle the cost of repairs. EN stated repairs would be ineffective until
either timber joists no longer blocked the subfloor ventilation, or powered ventilation
was added. No expert material challenges this view. The complainant’s builder and
the insurer ’s own records confirm removing wall wrap, improving drainage and
stormwater pipe repairs occurred in August 2017. The parties agree the complainant
had not completed the final subfloor ventilation works by the time the insurer offered
cash settlement.
In the above circumstances, even if the complainant is justified in deferring the final
steps required, cash settlement is fair because the expert material confirms the
insurer’s builders cannot warrant repa irs, due to the building’s subfloor design.
Accordingly, the insurer is entitled to cash settle the claim rather than carry out
repairs.
However, the complainant also raised the difficulty of either:
engaging builders to undertake these works before mould remediation (given the
subfloor is mouldy)
completing mould remediation before effective ventilation is arranged (potentially
enabling mould regrowth).
The complainant has not provided written confirmation of the extra costs to allow
builders to perform the necessarily ventilation work when mould is present. Despite
this, it is likely such works will incur additional costs such as, for example, builders’
protective wear.
The insurer accepted the claim for damage from the leaking pipe. This damage
includes mould contamination in the subfloor. A reasonable cash settlement must
therefore include those costs additional to (but not including) the complainant ’s own
maintenance work, required to allow builders to carry out (the maintenance) work in a
mould contaminated environment.
Determination | Case number: 524028 Page 5 of 14
2.2 Is the insurer’s cash settlement offer reasonable?
Parties dispute insurer offered fair cash settlement for mould remediation
In August 2017 the insurer arranged for scope of works assessments and quotes
from:
its building contractor (AJ), for water damage to the dining/kitchen area
a hygienist, for mould remediation.
The complainant disputed the insurer ’s cash settlement offer of 4 September 2017.
He engaged a hygienist (VA) and provided a mould remediation quote by DR for
$40,854, based on VA’s report of 7 October 2017.
The complainant initially provided a builder’s (IP’s) quote for $41,931 (dated 6
February 2018). He also provided a heating and cool ing technician’s (AA’s) report and
quote for $16,980, stating the property’s air systems needed replacement due to
mould contamination.
After lodging this complaint with the Service, the complainant provided updated mould
remediation quotes by DR (for $75,317) and updated building quotes by RB (for
$63,199.40 and $10,644.97).
The insurer agrees to pay RB’s quote for $63,199.40, but argues the complainant ’s
other quotes are not reasonable because it says
RB’s quote addresses damage beyond AJ’s scope of works
the quotes respond to damage from long-term moisture build-up and design of the
vents, falling outside the scope of cover provided by the policy
AA’s report does not sufficiently link air systems’ damage to the accepted
(stormwater leak) event, or define the extent of damage or necessary repairs
DR’s second quote is significantly higher than DR’s first
further, DR’s first quote is dated 2 November 2016, prior to the subfloor claim and
is therefore outdated.
The insurer’s mould remediation quote is too limited in scope
The panel has closely reviewed the reports, scope of works and quotes the parties
provided.
AJ’s mould remediation scope of works is based on a property assessment
undertaken on 21 July 2017. Material the insurer provided to the Service during the
later course of this complaint confirms both AJ’s quotes are based on instructions by
a second technical specialist (BJ). BJ requested AJ provide a limited scope of works
and quote based on insured damage only. It is unclear why BJ requested limited
estimates after PD accepted the stormwater claim in full, based on EN’s report.
Determination | Case number: 524028 Page 6 of 14
It is also unclear whether AJ’s mould remediation scope is based on a hygienist’s
opinion. The insurer provided the Service with a hygienist’s report FR provided in
October 2016. It also provided subsequent scope of works estimates for mould
remediation by JP, for ongoing repairs and remediation of the laundry leak water and
mould damage. Undated variations for mould remediation (including building) works
JP carried out reached $54,951.82.
Mould continued occurring throughout the home after FR’s February 2017 clearance
certificate, due to the second source (stormwater drain) the insurer ’s engineer
confirmed on 29 June 20 17. The panel is therefore unable to accept JP’s mould
remediation was successful.
Given the ongoing cause of mould, it is unclear what AJ’s mould estimate is based on
(apart from BJ’s instruction to quote for limited damage), or why it is significantly l ower
than prior mould remediation works actually carried out and likely unsuccessful.
In the above circumstances, the panel is persuaded that AJ’s quotes are based on
instructions by BJ, which conflict with the insurer ’s claim acceptance.
The complainant p rovided a hygienist’s (VA’s) report of 6 October 2017. It confirms
substantial mould contamination throughout air and surfaces in the overall property.
VA concluded water damage to the property’s timber flooring increased indoor
humidity, causing mould growth and contamination on surfaces not touching water. The
report included test results confirming:
significantly higher airborne mould counts in the dining room, laundry, bedrooms 1,
3 and 5 and subfloor when compared with an outdoor sample
visible mould on contents items.
The panel accepts the complainant arranged for VA’s report reasonably quickly after
the insurer’s cash settlement offer. The complainant provided the insurer with DR’s
mould remediation quote for $40,854, which states it is based on VA’s report. The
panel accepts DR’s quote is dated 2 November 2017 (not 2016 as listed or relied
upon by the insurer in declining the claim for mould remediation works), given VA’s
report is from October 2017.
In contrast, AJ’s scope of works states it addresses mould ‘in the subfloor [which]
looks like it goes up into the wall cavity in the dining room’. The panel therefore is not
satisfied AJ’s mould remediation quote is sufficient to address the contamination
confirmed by VA’s report.
The result is that the panel is not persuaded the insurer ’s cash settlement offer for
mould remediation is reasonable.
Determination | Case number: 524028 Page 7 of 14
DR’s 2018 mould remediation quote fair in all the circumstances
DR’s (first) quote states it ‘only applies to the kitchen lounge end of the house and
exclude s the newly renovated area’. The panel accepts the newly renovated area
references the laundry/garage area the insurer’s previous building contractor (JP)
partially repaired, before the insurer discovered the subfloor leak.
Although it is not itemised, on balance, the panel considers DR’s July 2018 quote
likely most closely reflects costs to remediate the property’s current mould, because:
levels may have increased while the complainant needed to dispute the
unreasonable cash settlement offer
DR’s earlier (itemised) quote therefore may not capture all current damage
DR’s earlier quote did not include the garage/laundry areas, where mould has likely
recurred after the insurer said it was cleared (February 2017).
On balance, the panel is persuaded the complainant took steps to mitigate the extent
of damage. The complainant’s partner told the insurer on 8 December 2017, three of
four subfloor (tree stump, drainage and pipe repair) ventilation works were complete.
The insurer questions whether this occurred, but its claim records repeatedly
reference drainage and pipe repairs its contractors and representatives recorded the
complainant completed.
The complainant ’s builder (IP) confirmed he removed wall wrap (sisolation) in Aug ust
2017, during an inspection to advise on the necessary subfloor works. The
complainant also argues, when seeking a quote for subfloor mechanical ventilation,
contractors advised it:
would be helpful for the installers to install when the flooring has been
removed. Also suggested that by installing mechanical ventilation before
mould remediation issue had been resolved could cause more mould
damage to the rest of the house.
The complainant’s restorer (DR) provided persuasive comments supporting mould
remediation occur before installing the final ventilation (maintenance) works.
Given the above information and the extensive evidence of previous unsuccessful
remediation attempts in the claim, the panel accepts it was likely complications would
arise if the complainant attempted to commence repairs to the subfloor before
addressing the mould, or vice versa. This is due to the nature of mould damage and
the insurer ’s substantially insufficient cash settlement offer.
In these circumstances, the panel is persuaded it was reasonable for the complainant
to dispute the offer and await a suitable settlement before completing the final
subfloor maintenance steps.
Determination | Case number: 524028 Page 8 of 14
As a result, the panel does not accept the insurer’s assertion the complainant caused
further mould or building damage by delaying repairs or settlement.
The insurer had sufficient time to arrange an accurate mould remediation quote and
did not do so. The insurer is therefore required to cash settle the mould remediation
works based on DR’s 2018 quote.
The insurer is liable for heating and cooling quote
The panel does not accept the insurer ’s arguments it is entitled to decline the claim
for AA’s quote. This is because VA’s report confirms extensive mould contamination
and:
AA reported the mould contaminatio n infiltrated the property’s heating and cooling
systems
AA stated the contamination renders them unsafe and they require replacement
the insurer provided no expert material refuting these views
the insurer had sufficient time to arrange its own heating/cooling quote and did not
do so.
Accordingly, the insurer is required to cash settle the complainant the cost of AA’s
quote.
RB’s butler’s pantry quote is based on a loss adjustor’s review of damage
As the insurer accepts RB’s quote for $63,199.40, it is req uired to pay this amount (if
it has not already done so).
Regarding the butler’s pantry quote, the panel accepts the complainant has
established a claim for this damage which the insurer’s submissions do not sufficiently
challenge. This is because, although AJ provided a scope of works for the kitchen
from August 2017:
AJ’s repair quote, which the insurer relies on, does not itemise the works
it is therefore unclear what this quote is based on
the panel accepts the butler’s pantry repairs are located near the kitchen, a site of
significant water damage to timber flooring and benches
regardless, RB’s scope of works and quote was arranged by an independent loss
adjustor and therefore sufficie ntly challenges AJ’s.
Further, documents the insurer provided late in the course of this complaint confirm
AJ considered the ‘walk in pantry’ sustained tile and (timber) subfloor damage.
Accordingly, the insurer is required to pay RB’s repair quote for $10 ,644.97.
Determination | Case number: 524028 Page 9 of 14
The insurer is required to pay an amount allowing for interest and
contingencies
Unforeseen costs when the complainant carries out repairs may arise, meaning the
quotations may not cover all possibilities. The panel is satisfied a fair cash settlement
amount should therefore allow for a contingency fee on the complainant ’s quotes.
Given the panel is also satisfied the insurer should not have refused the quotes by
RB, DR and AA, the amount is to allow for interest on these quotes.
For the above allowances, the panel considers it fair in these circumstances for the
insurer to increase its cash settlement by $20,000.
The complainant also incurred professional fees in correctly disputing the insurer’s
scope of works and repair quotes.
If the complainant has already paid the fees incurred by AK, the insurer is to
reimburse this amount. If not, the insurer is required to pay AK directly.
In addition, the insurer is also required to:
reimburse the complainant the cost of VA’s report in l ine with its agreement to do
so on 15 August 2018
cash settle the complainant an equivalent amount for the post-remediation
clearance testing VA stated is necessary after the complainant finishes repairs.
2.3 Did the insurer fully settle the other claims?
The insurer is to cash settle remaining laundry/garage works for $1,239.65
When bringing this complaint before the Service, the complainant also argued JP did
not complete repairs for the laundry/garage damage the insurer accepted (before the
stormwater pipe leak was discovered). The complainant says JP did not finish
plastering walls and left live wires hanging from the wall.
The insurer says JP removed the garage wall sheeting as part of the mould
remediation and the garage roof issues pre -dated the first claim, which the insurer’s
claim records confirm. The panel accepts when the stormwater pipe leak was
discovered and the insurer accepted this claim on 29 June 2017, there was no
purpose in JP completing garage wall repairs from that point onwards.
The insurer now agrees to cash settle the complainant $1,239.65, for the remaining
plastering and painting, based on JP’s quote of 13 April 2018. The complainant
provided a quote and scope of works by RB for $4,946.15, which included these
repairs.
However, the panel accepts the insurer’s assertion it is not required to cash settle the
cost of carpets (as contained in RB’s quotes) because:
Determination | Case number: 524028 Page 10 of 14
claim records confirm it cash settled the complainant the contents sum insured in
December 2017
per the wording in Section 3.1, carpet are contents items under the insurer’s policy.
RB’s quote is not itemised by price. Accordingly, the insurer is entitled to cash settle
JP’s remaining repairs for $1,239.65.
The insurer is required to cash settle further accommodation
The insurer’s policy includes an accommodation benefit costs for up to 12 months
from when an accepted event occurred.
The complainant wants a further 14 weeks accommodation costs based on DR’s and
RB’s remediation and repair period estimates, plus the 24 week s drying-out period the
insurer previously agreed to, based on its engineer’s view.
The insurer says no further accommodation is payable because it already cash
settled or covered in total 50 weeks of the accommodation benefit (after 3 July 2017)
and the complainant delayed repairs.
The insurer is required to cash settle the complainant’s costs for further
accommodation because the panel is satisfied the accommodation benefit has been
used after 4 September 2017 substantially due to errors in the insurer’s assessments
or decisions. This is because:
the insurer’s remediation and repair offers were based on BJ’s unsupported
decision to limit the scope of damage they addressed
further, the insurer’s remediation and repair quote costings were not fair and
reasonable
the insurer erred in refusing AA’s air system costs
the complainant was required to dispute these decisions, starting from 4
September 2017
the complainant provided sufficiently challenging information in a reasonable time.
At 4 September 2017, the date when the insurer provided a substantially
unreasonable settlement offer the complainant needed to (accurately) dispute, 43
weeks of the policy’s twelve -month accommodation benefit remained.
Whilst the complainant has not yet installed the powered vents in the subfloor or
changed the joists behind the vents, the panel does not consider this caused
unreasonable delays because:
the complainant provided plausible explanations why
he otherwise completed necessary maintenance
Determination | Case number: 524028 Page 11 of 14
as stated, the panel considers the insurer ’s decisions and assessments caused the
delays.
Further, claim records confirm the insurer’s own building repair estimates were for a
similar period (13 weeks). They also note a drying out period of 24 weeks, which the
complainant’s expert does not include. However, given the passage of time, the full
period may no longer be required.
Considering all matters, the panel is of the view that it is fair that the insurer pay for a
further 30 weeks of temporary accommodation.
As the complainant has contents in storage, the insurer is to cash settle the
continuing costs of storage for the same period.
2.4 Did the insurer handle the claim reasonably?
We take conservative approach to non-financial loss compensation
Under the FOS Terms of Reference, we allow the payment of compensation (capped
at $3,000) for non-financial loss. We may decide an insurer should compensate a
complainant for such loss only where there has been an unusual amount of physical
inconvenience, time taken to resolve a situation, or interference with the
complainant’s expectation of enjoyment or peace of mind.
We take a conservative approach to compensation for non-financial loss.
The insurer ’s errors caused stress and inconvenience to complainant’s family
The complainant says the complainant’s family have been out of their home since
October 2016, causing stress for his partner and seven children.
Claim records confirm JP, the complainant and the insurer’s assessor all contributed
to various delays before 29 June 2017. However, the insurer provided temporary
accommodation under the policy’s benefit from October 2016, under the laundry
claim, until 3 July 2017. It then covered accommodation costs until 24 November
2017 and cash settled the complainant the equivalent of 24 weeks accommodation.
On balance, the panel accepts the complainant’s assertion accommodation
uncertainty then:
arose as the settlement amount approached exhaustion
caused his large family stress.
Claim records also confirm the complainant works away from home. His partner, who
looks after seven children while he works away, also needed to follow up
accommodation and other claim actions trying to understand or resolve the claim.
Determination | Case number: 524028 Page 12 of 14
In the above circumstances, the panel is persuaded the complainant experienced an
unusual degree of stress and inconvenience because the insurer after 4 September
2017 refused to:
extend accommodation
provide a cash settlement sufficient to remediate and repair the property.
Accordingly, the insurer is required to compensate the complainant $2,000
compensation in non-financial loss.
Determination | Case number: 524028 Page 13 of 14
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Policy
How we settle your buildings claim
We will choose to settle your claim for loss or damage to your home or
'other cover' in one of the following ways:
1. Arrange for repairers, builders or suppliers to repair or rebuild your
home. If you agree, we can arrange for our preferred repairers, suppliers
or builders to repair or rebuild your home.
2. Pay you the reasonable cost to repair or rebuild your home. We can
choose to: pay you, pay your nominated repairer, supplier or builder, or
provide you with store credits from one of our nominated suppliers.
The types of contents we insure
… (if you are an owner who lives in your home, your carpets are included
as part of your General Contents).
Other cover
We may also provide 'other cover' for your home or contents during the
policy period.
Determination | Case number: 524028 Page 14 of 14
When you can claim for other cover – In most cases, you can make a
claim for other cover when a listed event causes loss or damage to your
home or contents and we agree to pay for that loss or damage.
Other cover and your sum insured – … for these items, we’ll pay on top
of your sum insured: Temporary accommodation for home owners.
Temporary accommodation for home owners
If a listed event causes loss or damage to your home and we agree you
c an’t live in it and you need to move out so it can be repaired or rebuilt.
Covered under Buildings Insurance – costs for temporary
accommodation that we agree are reasonable and appropriate for you,
your family and your pets that you normally keep at your site any additional
living expenses that we agree are appropriate costs to remove and store
your contents and then return them to your home. We pay these costs for
the reasonable time we agree it should take to repair or rebuild your home
for up to 12 months from when the listed event took place. We pay this on
top of the Buildings sum insured.
Conditions – … we won’t cover costs caused by unreasonable delays in
repairing or rebuilding your home.