Home / Financial Firm (Unknown - Insurer) / Determination 522619

Determination 522619

Lifetime repair guarantee claim declined for ceiling paint failure

FirmFinancial Firm (Unknown - Insurer)
Decided2018-08-03
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant sought rectification of peeling ceilings under the insurer's lifetime repair guarantee after an earlier repair and two water-ingress claims. AFCA found the guarantee was not triggered because the damage came from ongoing roof water ingress, not defective workmanship or materials.

The lifetime repair guarantee covers only defective workmanship or materials, and the ceiling damage was from roof maintenance issues and duplicated damage already settled under an earlier claim.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 522619 Determination Page 1 of 6 Case number: 522619 3 August 2018 1 Overview 1.1 Dispute The applicant holds a home building and contents policy underwritten by the financial services provider (FSP) covering his home address. On 21 November 2016, the applicant contacted the FSP to advise there was paint flaking and peeling on the ceilings throughout the house. The applicant believed this was due to the quality of workmanship undertaken from a previous claim in 2013 (claim one) , and sought that this be rectified under the FSP‟s lifetime repair guarantee (LRG). The FSP inspected the property, however noted the applicant had previously lodged a second claim for water ingress in 2014 (claim two), which was cash settled. The FSP noted the applicant had not undertaken the repairs from claim two, and considered the water issues present were the same for which it had previously settled under that claim. On this basis, the FSP declined to cover any rectification works pursuant to the LRG under the current claim (claim three), as it did not consider the issues present currently were related to claim one. 1.2 Issue and key findings Is the FSP liable to undertake repairs under its LRG? The FSP is not liable to undertake any rectification repairs under its LRG because:  the material shows the failure of the paintwork is not due to the quality and/or materials used by the FSP in the repair of the home under claim one; and  in the circumstances, the LRG benefit is not triggered. 1.3 Determination This determination is in favour of the FSP. The FSP is not liable to undertake any repairs pursuant to its LRG and is not required to take any further action. Case No: 522619 Determination Page 2 of 6 2 Reasons for determination 2.1 Is the FSP liable for rectification works? Onus rests with the applicant to establish entitlement to the LRG benefit There is no dispute between the parties that the applicant suffered a loss from a risk insured against or that the FSP accepted claims one and two. However, a dispute has arisen between the parties as to the extent of the FSP's liability under the policy. In particular, the applicant says the repairs undertaken for claim one are faulty and should be rectified pursuant to the FSP‟s LRG. As the party seeking the benefit of cover under the LRG, the onus rests with the applicant to show he is entitled to it. Chronology of events The following events are not disputed between the parties: Date of loss Claim Affected areas 27 February 2013  One  ceilings in hallway, entrance, kitchen, dini ng room, family room, lounge room, laundry and bedroom one suffered water damage  works completed by builders “PI” on behalf of the FSP  ridge capping tiles re - bedded as were dislodged in the storm  these were repaired by PI as part of the claim. 3 September 2014  Two  ceilings in lounge room, kitchen, dining room and hallway were damaged due to water ingress  damage quoted by building firm “LS”  claim cash settled based on LS‟s quotation as maintenance issues to roof required remedying to prevent further water i ngress  LS unable to warranty works until roof fixed. 21 November 2016  Three  ceilings in kitchen, lounge room, dining room, bedroom three, entrance, family room and laundry are flaking and peeling  FSP declines rectification under LRG on the basis the dama ge is the same as the unrepaired damage from claim two. Expert evidence The FSP has appointed a number of experts over these three claims. Full details of the various expert reports are contained within section 3.2 of this determination. The various reports are clear in stating that there is no issue with the works undertaken by PI in 2013 for claim one. Those works were completed to a tradesman like standard and had not failed during the ordinary course of events. The LRG is quite narrow in terms of its application. It applies only to the quality of workmanship and materials used by the FSP in the repair of the home. It is not a blanket cover for all perils which may befall repaired areas of the home in future. Simply because the same areas again are damaged is not, of itself, sufficient to Case No: 522619 Determination Page 3 of 6 trigger the benefit. Rather, the applicant must show the quality of the material or workmanship of the repairs were defective. Applicant’s evidence The applicant was invited to provide his own report from a suitably qualified person in support of his position that the issues with the ceiling related to claim one. The applicant presented a report from painter “KH”. KH considered the cause of the failure of the paint was due to the plaster not being dry when painted. This has caused the paint to bubble and flake, and is therefore defective works. However, it is not clear from the report as to whether KH was aware of the existence of claim two, and the issues identified with the roof at that time. It is also not clear if KH is aware the roof has ongoing water ingress issues. Certainly, the report is silent on that particular point. Therefore, on balance, as it appears likely KH was not aware of claim two, his report is less persua sive than it otherwise might have been. On this basis, the FSP‟s evidence is preferred. Claim two was cash settled Claim two was cash settled due to maintenance issues with the roof which were allowing repeated instances of water ingress. Until the roof was remedied, the water ingress would continue to occur. As the FSP was unable to warranty the work because of this, it chose to cash settle the claim. The FSP‟s claim notes show that during a discussion between it and the applicant on 29 September 2014, the FSP advised the applicant of the maintenance issues with his roof. The applicant confirmed he was aware of the issues and that this was his responsibility to remedy. The FSP also confirmed during claim two that the workmanship for claim one was not in question, rather, the issues related to a new event of water ingress. Applicant did not undertake any works to roof The applicant acknowledges he did not undertake any repairs to the roof to prevent further water entry. The applicant also concedes he did not repair the ceilings after claim two, as he was not aware what the settlement funds were provided for. He did not realise he was supposed to repair the ceilings and used these to replace guttering and paint the soffit eaves. The „mud map‟ prepared by builder “DW” shows the water staining to be below the areas of the skylight and valleys, suggesting this is related to the historical issues identified at the home. Although DW says the damage is „new‟ it is unclear if DW was aware at the time of their inspection that the applicant had not repaired the damage from claim two. Case No: 522619 Determination Page 4 of 6 Whilst I am not entirely persuaded by the applicant‟s statements, as the FSP‟s claim notes of 29 September 2014 confirmed the FSP informed the applicant it was covering the ceilings, patio ceiling and skylights, the fact remains that much of the damage claimed for under claim three is a duplication of claim two. As the FSP has already settled claim two in full, the applicant is not entitled to additional funds for repairs. He has been indemnified already for this loss. Insofar as PI states the ceilings are no longer repairable, I do not accept this puts an onus on the FSP to cover the difference. Had the applicant repaired the ceilings in 2014 or thereabouts, they would likely not require replacement now. Claim three duplicates claim two to a large extent To a large degree, the items now claimed under claim three are those works originally assessed and accepted under claim two. Accordingly, I am satisfied the damage to the kitchen, lounge room and dining room have already been settled under claim two. The damage to bedroom three is not an area repaired by the FSP under claim one, nor was it included in the scope of works (SOW) for claim two. Accordingly, this is a new area of water damage. If the applicant chooses to do so, he may lodge a new claim for this damage. The remaining areas, being the entrance, family room and laundry are all areas repaired by PI under claim one. However, the various experts are clear in stating the issue does not lie with the works undertaken by PI, but rather in that there have been further instances of water ingress. In these circumstances, the LRG is not triggered and the FSP is not obliged to undertake any works pursuant to it. Case No: 522619 Determination Page 5 of 6 3 Supporting information 3.1 FOS approach to this dispute A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to FOS. However, commentary in this determination is restricted only to those issues considered relevant to the outcome. 3.2 Relevant expert reports Record Key points FSP’s expert (PI ) Builder‟s Report 9 March 2013  after a recent storm event, wat er staining was evident to the ceiling in the entrance/hallway and kitchen/dining room  roof tile s had been lifted in the heavy winds, causing the ridge tiles to rattle and break away the cement f ixing  this allowed wat er to ent er into the home. FSP’s expert (LS ) Builder‟s Report 11 September 2014  there was a previous water entry event, which was repaired by the FSP  however, the cei ling s to the lounge, kitchen, dining and hallway now ha ve water stains again  the rear patio area has water staining to the soffits and eaves  roof inspection showed the skylights ha ve section s which have been damaged and have some holes present  the valley tiles are laid too close together, whic h leads to water d amming up and overflowing the valley trays  it is recommended the customer addresses these maintenance issues to prevent further ingress  the resultant damage is not from a one - off event but due to long term maintenance issues  this is not the result of any work carried out by the previous panel builder  cash settlement is recommended due to the maint enance required. FSP’s expert (PI ) Builder‟s Report 17 December 2016  roof pointing works were carried out to a satisfactory standard, as was the internal painti ng  the internal ceilings are stained and peeling due to ongoing water ingress  as there was originally storm related damages to the property, this masked the maintenance related issues , which were not identified at the time  maintenance issues have now been identified  water is entering the cavity via the valleys or tracking or from some tiles high up which are lapped incorrectly  these drainages issues likely only become apparent in periods of heavy rainfall Case No: 522619 Determination Page 6 of 6  the ceilings are no longer repairable but must be re placed  it is recommended the insured engage a roof plumber to rectify all roof related issues. FSP’s expert (DW ) Builder‟s Report 19 January 2017  there is new (current) water staining and paint flaking off the ceilings  this is due to the general condition of the roof, which is allowing wind driven rain to enter under storm conditions  the ridge tiling had been done to a tradesman like finish  the ceilings in the kitchen, hallway, entry, and family room have been painted to a tradesman like finish  al l other work was to a satisfactory level  however, the original installation of the tiles to the roof is less than tradesman like  the cutting and finishing of the valley gutter is appalling, and the cutting and fitting of the tiles around the skylights is a lso poor  the tile clips fitted has created a 3mm gap between the tiles and this allows wind driven rain to enter these spaces  it pools on the ceiling and causes staining below  the insured was unaware of these issues. FSP’s expert (AS) Assessor‟s report 18 October 2017  two previous claims had been lodged for water ingress  claim one was repaired by PI, claim two was cash settled as the work was unable to be warrantied  the insured advised he was unaware the cash settlement money was for the repairs to the ceiling  he spent it on replacing the gutters and painting the eaves  these were not in the SOW  none of the work in the SOW has been carried out, and the last repairs were those done by PI in 2013  as there are no new damages, and all issues are from claim tw o, there is no further mon i es owing to the insured under this claim  he has already been settled for the loss. Applicant’s expert (KH) Painter‟s report 27 August 2017  after inspecting the ceilings, the cause of the flaking an d peeling would definitely be f r o m painting the ceilings while still damp from water damage  the ceilings have not been al lowed to dry nor has it been mad e certain the leaks were fixed  it appears like two quick coats of wa ter based ceiling paint have been applied to a still wet surface  this makes the defective and in need of rectification.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.