Home / Financial Firm (Unknown - Insurer) / Determination 522612

Determination 522612

$5,000 building excess applied to water damage claim

FirmFinancial Firm (Unknown - Insurer)
Decided2018-06-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant disputed the $5,000 building excess applied to her water damage claim and alleged claims delay. AFCA found the excess was payable under each year's certificate of insurance and that the FSP did not unreasonably delay the claim.

Each renewal notice and certificate of insurance showed the $5,000 building excess, and the onus was on the applicant to check them.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 522612 Determination Page 1 of 4 Case number: 522612 22 June 2018 1 Overview 1.1 Dispute The applicant (and her husband) has held building and contents insurance policies with the financial services provider (FSP) each year since 4 April 2011. The policy which renewed on 4 April 2017 provided for:  a $5,000 excess (comprising minimum excess $100 and voluntary excess $4,900) in the event of a building claim and  a $500 excess (comprising minimum excess $100 and voluntary excess $400) in the event of a contents claim. On 19 February 2018, the applicant lodged a claim for escape of liquid and water damage to their home. The FSP applied a $5,000 excess to the building claim. The applicant believes that only a $500 excess was payable. The applicant says because the FSP has been unable to produce documents to show that she agreed to an additional voluntary excess, it is not entitled to apply a $5,000 excess. The applicant ultimately paid the $5,000 excess on 9 April 2018, and the FSP approved repairs. The applicant says it was not until 28 May 2018 that the repairer received authority to proceed, and holds the FSP liable for delay in claims handling. The applicant says she has suffered anxiety as a result of the FSP’s conduct. 1.2 Issues and key findings Has the FSP correctly applied the $5,000 excess to the claim? The policy entitled the FSP to apply a $5,000 excess to the applicant’s building claim . Has the FSP delayed in its claims handling? The FSP has not unreasonably delayed the claim. No compensation for non-financial loss is warranted. 1.3 Determination This determination is in favour of the FSP. The FSP is not required to pay any compensation to the applicant. Case No: 522612 Determination Page 2 of 4 2 Reasons for determination 2.1 Has the FSP correctly applied the $5,000 excess to the claim? The onus rests with the applicant to review terms of policy at each renewal The applicant and her husband obtained a loan from a bank, whose representative also acted on behalf of the FSP to set up the policy to insure their home and contents from 4 April 2011. Payments for the policy were directly debited from the applicant’s account on a monthly basis. The applicant says that when the bank representative set up the policy in 2011, he erroneously nominated a $5,000 excess rather than $500. Alternatively, the applicant says the bank representative mistook a $5,000 excess with the need for $5,000 cover for portable items. The applicant also says that the FSP has been unable to produce any signed agreement from inception of the policy that she agreed to a higher excess voluntarily. The FSP is not required to disprove that the bank representative made a mistake or prove that the applicant agreed to higher excess. This is because each contract of insurance was for a period of 12 months, and there ha ve been six renewals since the alleged conduct at policy inception. Each renewal notice contains a sentence along these lines: Before renewing your policy, you must check whether the details included on this notice are correct and notify the insurer of any changes. The onus is on the applicant to review the policy documents to ensure the terms met her needs. The applicant concedes receiving the policy documents and renewal notices from the FSP. The applicant concedes that she did not notice the excess was $5,000 and that she and her husband made the mistake of not checking the renewal notices properly. I have reviewed each certificate of insurance for the years 2011 to 2017 inclusive. Each document for the relevant year shows a $5,000 excess is payable in respect of any claims made for a building claim. I am satisfied the FSP provided the applicant with the policy terms, which entitled the FSP to apply a $5,000 excess to the applicant’s building claim. 2.2 Has the FSP delayed in its claims handling? The FSP has not unreasonably delayed the claim The applicant lodged her claim on 19 February 2018. It was not until 9 April 2018 that the applicant paid the $5,000 excess. During the intervening period, the only discussion between the parties was about the excess payable. The FSP’s notes show that by 13 April 2018, “repairs have been started by the trades” however, a subsequent note of 26 April 2018 show that the repairs would start on 15 May 2018 and that the FSP had authorised temporary accommodation. Case No: 522612 Determination Page 3 of 4 During this time, the parties waited for the repairers to become available and decide on the scope of works. On 7 May 2018, the applicant submitted a variation to the scope of works to include repairs to the evaporative cooler. The FSP has since queried whether this was related to a leak from the bathroom vanity. The applicant has provided an email from the repairer which says that it only received authority to proceed on 28 May 2018. It is evident from the context of the email that the repairer had by that time submitted two variations, and the authority to proceed was clarified. On reviewing the FSP’s claim notes, I do not consider that the FSP has unreasonably delayed the claim. No compensation for non-financial loss is warranted The applicant says she has suffered greatly from anxiety because of the FSP’s conduct. While we have the power to award compensation for non-financial loss for stress, inconvenience, anxiety and disappointment, it is only in limited circumstances that compensation is considered for non-financial loss and awards are unlikely to be substantial. FOS expect applicants to be moderately robust in the way in which they deal with a problem and to bear the ordinary and normal degree of inconvenience associated with an insurance claim. We look at all the applicant’s circumstances when assessing the impact of the FSP’s conduct. The time taken and manner adopted in considering the applicant’s claim is not unusual and does not warrant compensation for non-financial loss. Case No: 522612 Determination Page 4 of 4 3 Supporting information 3.1 FOS approach This dispute has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only. The applicant remains concerned about ongoing matters such as service delays, quality and scope of works, and reimbursement of costs of temporary accommodation, dog kennelling and matching timber floors. As these matters are currently before the FSP, it is appropriate to allow the FSP an opportunity to respond to them in the usual course of their continuing claims management and they do not form part of this dispute.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.