Flood damage to business contents claim declined

FirmFinancial Firm (Unknown - Insurer)
Decided2018-10-16
ProductGeneral Insurance · Motor
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A motor trade business claimed for contents damaged by water inundation during a 2017 weather event. The FSP denied the claim as flood damage, which is excluded because the optional flood cover was not selected, and AFCA found in favour of the FSP.

Once rainwater mixes with flood water it is all flood water, and the policy excludes flood without the optional flood cover.

Issues

Subjects and remedies

natural disastersmall businessno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 522552 Determination Page 1 of 8 Case number: 522552 16 October 2018 1 Overview 1.1 Dispute The applicant has a motor trades pack policy with the financial services provider (FSP). A claim was lodged under the policy after the insured premises was inundated with water following heavy rain from Cyclone Debbie. The FSP maintains the inundation was caused by flood which is excluded from cover under the terms of the insurance policy. 1.2 Issues and key findings Is the damage covered under the terms of the policy? Based on the available material, the FSP is entitled to deny the claim as the claimed loss is excluded from cover because:  the policy specifically excludes loss or damage caused by flood  on balance, the water that caused the loss was flood water Did the FSP mishandle the claim? There is insufficient basis to conclude the FSP is liable to pay compensation for the applicant’s claim or dispute experience. 1.3 Determination This determination is in favour of the FSP. The FSP is entitled to rely upon the terms and conditions of the policy to deny the applicant’s claim. Case No: 522552 Determination Page 2 of 8 2 Reasons for determination 2.1 Is the damage covered under the terms of the policy? The applicant does not have flood cover The applicant’s policy is a motor trade s pack policy which provides cover for loss or damage caused by defined events, including wind and/or water. However, the policy specifically excludes loss or damage caused by flood unless flood cover is selected as an option. Flood is defined in the product disclosure statement (PDS) as: “ “Flood” means the covering of normally dry land by water that has escaped or been released from the normal confines of any of the following: a. lake (whether or not it has been altered or modified); b. a river (whether or not it has been altered or modified); c. a creek (whether or not it has been altered or modified); d. another natural watercourse (whether or not it has been altered or modified); e. a reservoir; f. a canal; or g. a dam.” The policy schedule evidences that the applicant did not take up the optional benefit for flood. The applicant confirms he was aware he did not have flood cover. Circumstances of the loss The insured property is a vehicle smash repair business housing a workshop and an office. The exchanged material confirms there was a significant weather event across Australia and in particular in the area of the insured property during the latter part of March 2017. A substantial amount of rain fell during this time. The applicant says the insured property was inundated by stormwater at approximately 11pm on 30 March 2017, approximately three hours prior to M Creek breaking its banks. However, the applicant also says that M Creek did not break its banks until the early hours of 31 March 2017 at approximately 12.40am. The applicant says that stormwater entered the insured property through the gutters and downpipes which overflowed due to the volume of rain, as well as the stormwater inlet which was unable to cope with the run-off from W Place. The appl icant’s claimed loss is for contents only. In support of his position, the applicant has provided the following information:  a report from an engineer (SC) dated 9 October 2017  a signed witness statement indicating that he was at the insured property until 10.30/10.45 pm on 30 March 2017 and observed that water had receded back to the junction of W Street and B Road. At this time, he did not believe that the Case No: 522552 Determination Page 3 of 8 insured property was in any danger of water inundation and went home. He then received a telephone call from one of his workers around 11.30pm to say that water was inundating the shop. After driving back and parking nearby at the junction of W Street and P Highway, he stated that “water was visible to have come out of the storm drain to the south of the shop and was about 3-4 foot in height”  four signed witness statements from neighbouring properties  an email from an alternate insurer to a loss adjuster dated 7 February 2018. In order to assess whether stormwater runoff or flood waters inundated the insured property, SC set up a two-dimensional flood model to understand the flood behaviour at the site during the March 2017 storm event. Based on the results of the modelling, SC concluded that stormwater runoff inundated the insured property to a depth of approximately 86mm at about 12.40am on 31 March 2017, prior to backwater flooding from M Creek. SC stated that flood waters from M Creek subsequently reached the insured property at about 1am, which then exacerbated flooding at the property, increasing the flood depth to 126mm at that time, and eventually reaching a depth of 451 mm at about 1.20am. The applicant says that an alternate insurer is dealing with a claim for loss of profits for the insured property. The email from the alternate insurer to a loss adjuster states: “The hydrologist’s report that we obtained from [hydrologist] back on 27/11 did state the insured premises did suffer rainwater run off due to the very deluge of the 30 March. The flooding occurred from 31/3/2017. Are you able to calculate a possible loss of profits claim based on the .1m rainwater ingress to the insured shop[?]” The applicant says that despite several requests for a copy of this hydrology report, the alternate insurer has not provided it. The FSP has provided two assessment reports, together with a report from its hydrologist, WR, dated 12 May 2017 following a site inspection on 3 May 2017. The FSP also provided a supplementary report dated 1 June 2017 in response to a report provided by the applicant from NE. The app licant has confirmed he is no longer relying on the report from NE, and accordingly any references to this report have been disregarded. A further report from WR dated 18 April 2018 was provided in response to the report provided by the applicant from SC. WR concluded:  the floor levels of both the office and workshop are similar to the adjoining ground levels  the office and workshop were inundated to a maximum depth of about 1.2m above floor level  the rainfall in the vicinity of the applicant’s property w as most intense between midnight and 1.00am on 31 March 2017 Case No: 522552 Determination Page 4 of 8  the closest M Creek water level gauge to the insured property recorded a peak water level of 4.47 mGH at 2.30am on 31 March 2017, and the water level at the insured property would have peaked a short time later  initial and maximum inundation of the building at the insured property was caused by flood water from M Creek  stormwater runoff from the insured property is collected in an inlet pit at the corner of M Place and W Street and discharges to the open channel system along W Street. During flood events in M Creek, flood water could back up along the open channel system and flow back through the pipe system to inundate the subject property  the modelling undertaken by SC appears to be based on some questionable assumptions that would overestimate the initial stormwater depth, and the modelled peak depth of inundation by M Creek is significantly underestimated In addition, the FSP provided a signed statutory declaration from its loss adjuster (RR) who attended the insured property initially on 10 April 2017. RR stated:  at the time of attendance he noticed water marks on the walls approximately 900-1000mm from ground height  a number of photographs were taken at the time of attendance which identified a number of smaller items at ground level. It would be difficult to identify which items were in situ since the event and which items may have been placed/disbursed by the insured's staff to assist with drying out prior to the site meeting  damage below the height of 86mm (less than shoe height), to the insured's stock and contents would appear to be minimum with motors, circuit boards, electronic componentry and switching gear to larger plant and machinery items generally located well above the height of 86mm  based on his initial inspection of the property and other properties in the area assessed at that time, the vast majority of damage sustained was due to flood and water levels significantly above 86mm. The loss was caused by flood Having reviewed the exchanged material, the Panel is more persuaded by the conclusions of WR that the initial and maximum depth of inundation of the applicant’s property was caused by flood water from M Creek. In reaching this determination, the Panel considers that:  there is a significant difference between the peak flood depths reported by SC and WR, being 451mm as opposed to 1200mm. The reported maximum depth by WR is more consistent with the observed watermarks by RR at approximately 1000mm  the insured property could not have been inundated by stormwater approximately three hours prior to M Creek breaking its banks (at 12.40am on 31 March 2017) noting the applicant did not observe any water at 10.30pm on 30 March 2017 when he left the property  there is insufficient evidence that the gutters and downpipes overflowed to cause damage to the insured property before flood water arrived Case No: 522552 Determination Page 5 of 8  the applicant’s observation of water visibly coming out of the storm drain to the south of the insured property shortly after 11.30pm on 30 March 2017 is consistent with WR’s findings that the initial inundation of the property would have been caused by backflow from the W Street open channel through the pipe drainage system under W Street. In the circumstances, the Panel is satisfied on balance that the inundation of the applicant’s property was caused by flood and not stormwater runoff. T he FSP is entitled to rely upon its policy exclusion to deny the applicant’s claim. 2.2 Did the FSP mishandle the claim? Evidence does not show FSP mishandled the claim The applicant says the FSP has failed to act in a timely manner in an attempt to have the matter resolved. The claim was lodged with the FSP on 4 April 2017. Between this and 27 July 2017 the FSP assessed the claim and provided a decision to deny liability. The applicant requested the claim be reviewed by the FSP through its internal dispute resolution (IDR) procedures on 8 February 2018. The FSP provided its IDR response in a letter dated 30 April 2018. The Panel does not consider these timeframes to be unreasonable, particularly given it would be within the timeframes set out in the General Insurance Code of Practice. Further, the FSP’s position on this dispute has been substantively established. Given all this, the Panel does not accept there is sufficient basis to conclude the FSP is liable to pay compensation for the applicant’s claim or dispute experience. Case No: 522552 Determination Page 6 of 8 3 Supporting information 3.1 FOS approach to this dispute There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise in this dispute. This decision has been made by a Panel consisting of an ombudsman, an insurance industry representative appointed by the Financial Ombudsman Service Board, and a consumer representative appointed by the Financial Ombudsman Service Board. This determination follows consideration of all of the information exchanged and is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. The parties have raised numerous issues in their submissions to FOS. For the purpose of this determination, commentary is restricted to only those issues considered relevant to the outcome. 3.2 Applicant represented by a broker During the course of this dispute, the applicant has been represented by a broker. For the purposes of this determination, submissions made by the applicant’s broker have been treated as if they had been made by the applicant. 3.3 Rainwater that mixes with flood water is flood The Courts have established that once rainwater mixes with flood water, it is all considered flood water. Where rainwater mixes with flood water and causes damage, a flood exclusion will usually apply to defeat the claim. Accordingly, when deciding disputes, consideration has been given to whether there was any rainwater runoff damage before the flood water arrived at the insured property. 3.4 Relevant expert reports Record Key point s FSP’s expert ( WR ) Hydrology Re port 12 May 2017  The subject property is located on the western side of M Place north of its intersection with W Street. The building is constructed of concrete blocks with a concret e floor. A vehicle smash repair business, with a building housing a workshop and an office, is located on the subject property.  The office and workshop were inundated to a maximum depth of about 1.2 m above floor level. The floor levels of bot h the office and the workshop are similar to the adjoining ground levels. Case No: 522552 Determination Page 7 of 8  Peak rainfall occurred in the hour to 0100 hours on Friday 31 March.  The water level recorded at the B gauge peaked at 4.47 mGH at 0230 hours on Friday 31 March 2017. The water level at the subject property would have peaked a short time later.  Site observations and discussions wit h other witnesses in the area indicate that inundation in B was widespread with many other properties in M Place and surrounding streets inundated above floor level.  Rising flood levels in M Creek would have overflowed into W Street and the local catchmen t to the sout h of W Street via the flow path, as well as backing up along the open channel along W Street near the subject property. This floodwater would have combined with flow in the local catchment. The initial inundation of the property would have bee n caused by backflow from the W Street open channel through the pipe drainage system under W Street. Later during the event, floodwater overtopped W Street, M Place and the railway line west of the property.  Based on published flood modelling results, wat er from the M Creek would inundate the subject property during a major flood event. This is consistent with what occurred during the March 2017 flood event.  Initial and maximum inundation of the building at the subject property was caused by floodwater fr om M Creek. Applicant’s expert (SC ) Report 9 October 2017  In order to assess whether stormwater runoff or M Creek flooding inundat ed the property, and to what extent, a two - dimensional (2D) flood model was set up to better understand the flood behaviour at the site during the March 2017 storm event.  Based on the results of the modelling, it is concluded that flooding at the property was initially due to stormwater runoff. This resulted in a flood depth of up to about 86 mm at the property at about 12. 40 a m on the 31 March 2017 prior to backwater flooding from M Creek impacting on the property.  Floodwat ers from M Creek subsequently reac hed the property at about 1 am, which then exacerbated flooding at the property, increasing the flood depth to 126 mm at th at time, and eventually reaching a depth of 451 mm at about 1.20 am. FSP’s expert (WR) Further Hydrology Report 18 April 2018  The SC report is consistent with the WR report in finding that the peak depth of inundation of the subject property was caused by floodwat er overflowing from M Creek.  The modelling undertaken by SC indicates shallow (86 mm above floor level) inundation by stormwater prior to inundation by floodwater. However, based on the information that is provided, the modelling undertaken by SC appears to be based on some questionable assumptions that would overestimate the initial stormwater depth. In addition, the mo delled peak depth of inundation by M Creek is significantly Case No: 522552 Determination Page 8 of 8 underestimated.  For these reasons, I remain of the opinion that the initial and maximum depth of inundation of the subject property above floor level was caused by floodwater overflowing from M C reek.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.