Determination 522478
Unreasonable delay in repairs after water leak claim and driveway damage by contractors
Summary
The insured's home leak repairs were delayed and driveway damage was caused by contractors. AFCA awarded $500 for non-financial loss and ordered a driveway repair cash settlement, but rejected further temporary accommodation and dining table claims.
The insurer was responsible for part of the repair delay, causing stress and inconvenience beyond what is normally expected.
Issues
- Delay primary · upheld“Due to an unreasonable amount of delay the applicant is entitled to $500 compensation for non-financial loss.”
- Claim amount dispute secondary · not upheld“The applicant has not provided any evidence of additional costs actually incurred that are covered under the Policy.”
- Repairs or contractors secondary · upheld“obtain a quote for the cost of repairs from a contractor ... and cash settle the applicant for this amount.”
Subjects and remedies
home or building damagepay compensationpay non financial loss
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 522478 Determination Page 1 of 4
Case number: 522478 30 August 2018
1 Overview
1.1 Dispute
This dispute is about the assessment and management of a claim made under a
home and contents insurance policy (Policy). The Policy was issued by the financial
services provider (FSP) and started on 8 August 2017.
On 18 August 2017, the applicant made a claim for a leak which had caused damage
to flooring. The claim was accepted and the repairs were authorised.
The applicant says the FSP:
unreasonably delayed the repairs and did not communicate properly
failed to provide suitable alternative accommodation for her and her pets, and
caused additional damage to property and contents.
1.2 Issues and key findings
Is the applicant entitled to additional temporary accommodation costs?
The FSP has met its obligations under the Policy and cash settled the applicant for
the reasonable costs of temporary accommodation for her and her pets. The
applicant has not established that she incurred any additional costs and is not
entitled to any further payment.
Is the applicant entitled to additional compensation or payment?
The FSP has provided a fair and reasonable remedy for the damaged table and
driveway. The applicant is not entitled to any additional compensation for these
items.
Due to an unreasonable amount of delay the applicant is entitled to $500
compensation for non-financial loss.
1.3 Determination
This determination is partially in favour of the applicant. Within 14 days of the
applicant’s acceptance of this determination the FSP :
must pay the applicant $500, and
obtain a quote for the cost of repairs from a contractor who is able to undertake
the work to repair the driveway and cash settle the applicant for this amount.
Case No: 522478 Determination Page 2 of 4
2 Reasons for determination
2.1 Is the applicant entitled to additional temporary accommodation
costs?
The Policy provides cover for temporary accommodation
Under the Policy the applicant is entitled to temporary accommodation if the property
cannot be lived in during the repairs. The product disclosure statement (PDS) says:
When an insured event damages your home to the extent you cannot live there, and we
agree, we will pay for your reasonable temporary accommodation costs for the time it will
take to repair or rebuild your home to a liveable condition. We will also pay for temporary
accommodation for your domestic pets in a commercial boarding establishment for the
same period that we pay for your temporary accommodation.
The cover is limited to 10% of the home sum insured. The applicant is seeking 10%
of the home sum insured. This is a limit to the cover, and does not mean that the
applicant is entitled to the maximum amount payable under the Policy.
Based on her level of cover, the applicant is entitled to:
up to 4 weeks in short term accommodation agreed to by us (e.g. standard rates for a hotel,
motel or serviced apartment), then if necessary up to another:
• 48 weeks in residential accommodation of a similar standard to your home…
The FSP provided applicant opportunity to find suitable accommodation
The applicant advised the FSP that she had pets that would also require
accommodation:
Customer adv she has 2 cats, 4 fish, and 2 72kg great danes, -Customer adv last time she
had to put her pets into temp accommodation they got sick -Customer adv this is very
stressful -Reviewed policy confirmed coverage for pets "in a commercial boarding
establishment for the same period that we pay for your temporary accommodation." as per
PDS -Customer adv if she could look for pet friendly accommodation herself - confirmed to
have insured send through quote for review -Requested customer to send through quote
for review for looking for her own pet friendly accommodation -Adv customer to call back as
soon as she has sent through the quote for review. (sic)
I am satisfied that the FSP acted reasonably and fairly in allowing the applicant to
find her own pet friendly accommodation. The applicant was given several
opportunities to provide quotes for the accommodation and failed to do so.
Applicant agreed to be cash settled for her temporary accommodation costs
The FSP then cash settled the applicant for her temporary accommodation costs:
When IO calls back, explain we are awaiting her quote for temporary accommodation we
can cash settle insured $839.00 for accommodation - Spoke to Insured and she is happy
with this will use the money to drive to a family members property 2.5 hours away and will
stay their until the repairs are completed (sic)
In all the circumstances the cash settlement of the temporary accommodation costs
was fair and reasonable, and was accepted by the applicant. The applicant has not
provided any evidence of additional costs actually incurred that are covered under
the Policy. The applicant is not entitled to any further payments for these costs.
Case No: 522478 Determination Page 3 of 4
2.2 Is the applicant entitled to additional compensation or payment?
The applicant accepted an offer in full and final satisfaction for the table
The applicant says her dining room table was damaged during the repairs. The FSP
does not accept that the damage was caused by their contractors, however offered a
cash settlement of $200 as a gesture of goodwill:
That being said, I am happy to honour my previous goodwill gesture of $200.00, as [the
contractor] has indicated that you have requested this. I would just like to reiterate that this
is offered without prejudice.
I would ask that you reply to this email with the BSB and account number for your
nominated bank account. Once I have this back, I will forward your details to our Accounts
Department for funds disbursement via direct deposit.
In response the applicant provided her bank account details. I am satisfied that the
applicant accepted the FSP’s offer in full and final satisfaction of her claim for the
damage to the table.
I acknowledge that the applicant says that the cost of restoring the table is $750
however no quotations have been provided to support her claim. In the absence of
any further information I am satisfied that the applicant accepted the offer and is
therefore not entitled to any further compensation for this item.
The FSP has agreed to repair the driveway or provide cash settlement
The applicant says her driveway was damaged by the contractors . The FSP has
agreed to repair the driveway. It says:
In relation to the driveway, the repairers have been attempting to resolve the matter, and
included in this has been reduction of private invoiced works for the cost of repairs.
However, we have asked they cease with this, and the F SP can confirm that it can
authorised for the repair of the driveway to be completed or can issue a cash settlement to
the Applicant for its cost to repair (once obtained). (sic)
The FSP notes the Applicant has verbally provided amounts for the repair of t he driveway,
however at this time for formal quotes have been forthcoming and the builders have called
the builder state to have quoted the Applicant and been advised of amounts differing to that
advised by the Applicant. Hence, should a cash settlement be considered the FSP would
seek to obtain its own formal quote. (sic)
I am satisfied that the FSP’s offer is fair and reasonable in the circumstances. It is fair
in all the circumstances the FSP pay to have the driveway repaired. Therefore, the
FSP must wit hin 14 days of the applicant’s acceptance of this determination, obtain a
quote for the cost of repairs from a contractor who is able to undertake the work and
cash settle the applicant for this amount.
FOS has a limited jurisdiction for non-financial loss
FOS will only award compensation for non-financial loss where there has been an
unusual amount of physical inconvenience, time taken to resolve a situation, or
interference with the applicant’s expectation of enjoyment or peace of mind.
In assessing whether to award compensation for non-financial loss, FOS expects
applicants to be moderately robust, bear the normal degree of inconvenience
experienced when a problem occurs, and take reasonable steps to minimise the
Case No: 522478 Determination Page 4 of 4
inconvenience suffered. Where an applicant has contributed to their loss arising from
the FSP’s conduct, their level of compensation may be reduced accordingly.
FOS can compensate an applicant for non- financial loss arising from the FSP’s poor
management of the claim. When doing so, FOS considers the severity and impact of
the FSP’s conduct on the particular applicant.
FOS takes a conservative approach to assessing compensation for non-financial
loss. The maximum amount FOS can award for non-financial loss is $3,000 per
claim.
The FSP failed to manage the claim efficiently and repairs were delayed
I have carefully reviewed the information provided by the parties and the following is
relevant:
the claim was lodged in August but repairs were not scheduled to start until
November
the applicant was on holidays until mid-September, however she contacted the
FSP on her return to advise that she was now ready to book the work in
in October the applicant contacted the FSP to advice that the work had not
started
the applicant was then only given four da ys notice that work would be starting
and that she was required to empty the kitchen and remove furniture
the applicant requested the work be postponed to give her more time to
organise removal of items and temporary accommodation
the repairs were re-booked for January/February
it appears there were unexplained delays during the repairs and the applicant
did not have the use of her kitchen at times
the applicant was paid $100 reimbursement for food costs and the management
of the repairs was transferred to another contractor, and
some repairs were delayed due to poor management of the work .
Based on the information provided I am satisfied that the FSP is responsible for
some of the delay. This unreasonable delay caused the applicant stress and
inconvenience in excess of what would normally be expected, and the applicant is
therefore entitled to $500 compensation for non-financial loss.