Determination 521837

Floor tile claim declined and mould remediation disputed after leak

FirmFinancial Firm (Unknown - Insurer)
Decided2018-11-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

After a water leak, the insurer denied the floor tile claim as pre-existing and dispute mould remediation, with the roof repairs still needed first. AFCA upheld the tile denial, ordered mould remediation within the insurer's scope of works and carpet replacement based on the sample, and awarded $500 non-financial loss.

The insurer's tiler established that the tile failure pre-existed the leak under the policy exclusions, while mould remediation is limited to the leak-related scope until the roof is repaired.

Issues

Subjects and remedies

home or building damagepay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination | Case number: 521837 Page 1 of 7 Case number: 521837 13 November 2018 1 Determination overview 1.1 Complaint The complainant holds a home and contents insurance policy with the financial firm (insurer). He lodged a claim against his policy after water leaked for two days from a flexible pipe under the bathroom basin. The insurer said the floor tiles were not damaged due to the water leakage, but had pre-existed that event. The insurer also assessed the resultant mould within the house and carried out some remediation, but said other mould areas had not resulted from the water leakage. The complainant contended the insurer deliberately delayed the claims process and he is also claiming the cost of alternative accommodation. The case manager provided the parties with a recommendation on the issues in complaint. The recommendation was partially in favour of the complainant. A copy of the recommendation is attached to this determination. The recommendation was issued by FOS. The Australian Financial Complaints Authority (AFCA) has replaced Financial Ombudsman Service (FOS). AFCA is responsible for managing FOS complaints lodged prior to 1 November 2018. While this determination is issued by AFCA we have applied the FOS Terms of Reference. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were correct (except for a minor amendment) and are adopted in this determination. Further submissions provided after the recommendation have been considered. Was the insurer entitled to deny the claim for damaged floor tiles? The insurer has established the application of a policy exclusion with respect to the damaged floor tiles and i s entitled to deny this part of the complainant’s claim. Is the insurer required to carry out additional mould remediation? The insurer is not required to carry out additional mould remediation. The complainant is required to complete roof repairs before the insurer can commence mould remediation. Determination | Case number: 521837 Page 2 of 7 Is the complainant entitled to compensation for non-financial loss? The complainant has established an entitlement to compensation for non-financial loss and the insurer is required to pay him $500. Is the insurer required to pay any additional amount? The insurer is required to base the carpet replacement on the sample the complainant supplied. The insurer is not required to pay for the complainant’s alternative accommodation beyond 30 August 2018. 1.3 Determination This determination is partially in favour of the complainant. I agree with the case manager’s reasons for the recommendation and the recommended outcome (with a minor amendment). The insurer is to carry out mould remediation in accordance with the scope of works identified in this determination. The insurer is also required to base the carpet replacement on the sample the complainant provided. The insurer is required to pay $500 compensation to the complainant. Determination | Case number: 521837 Page 3 of 7 2 Reasons for determination 2.1 Were the findings in the recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous AFCA decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied the documentation I have relied on has been provided to both parties. I am satisfied the case manager’s recommendation contains an accurate summary of the complaint, the issues to be determined, any applicable paragraphs of the Rules and any relevant law. 2.2 Was the insurer entitled to deny the claim for damaged floor tiles? Complainant has established a valid claim The complainant claimed against his policy for damage to floor tiles after water leaked throughout his house from a flexible pipe under the bathroom basin. The complainant said floor tiles in various rooms had become ‘drummy’ as a result of the water leakage. The complainant bears the onus of establishing a valid or prima facie claim for which the policy responds. The complainant has established a valid claim because his policy covers loss or damage due to liquid leaking, bursting, discharging or overflowing from certain items or devices. Since the insurer has denied this part of the claim, it bears the onus of establishing the application of at least one of the policy exclusions upon which it has relied. Insurer has established application of policy exclusion The insurer arranged SP, an experienced tiler to assess the damaged floor tiling. SP’s report (dated 23 February 2018) contained a comprehensive analysis of the damaged floor tiles and included a mud map, along with photographs. SP said the failure of the floor tiles (becoming ‘drummy’) had pre -existed the water leakage event. SP said the damage was due to the original installer not achieving the correct adhesive coverage / distribution. In addition, SP said the installer had failed to adhere to Australian standards by installing the correct type and amount of movement joints to ensure the longevity of the tiling system. The complainant provided two very brief reports , in addition to another slightly longer report from tilers. The two very brief reports lack sufficient detail and are too general in natur e to challenge SP’s findings. The longer report indicated the flooding contributed to the damage, however the report added nothing further of substance. Determination | Case number: 521837 Page 4 of 7 The insurer applied general policy exclusions such as the loss not being linked to any identifiable ev ent and ‘wear and tear’ through normal use. The insurer relied on SP’s findings when applying the exclusions. SP has the appropriate qualifications, knowledge and experience to assess the effective cause of damage to the floor tiling. SP’s findings indicate the damage did not result from the water leakage and had occurred over time. As such, the insurer has established the application of the policy exclusions and is not required to cover the complainant for the damaged floor tiles. 2.3 Is the insurer required to carry out additional mould remediation? Issue of mould remediation to be resolved The issue of mould remediation remai ns unresolved. The insurer rejected part of the recommendation that was substantially in the complainant’s favour a nd provided submissions in support. These submissions mainly related to the issue of mould remediation. The insurer has already carried out some mould remediation work to the house and indicated it was still committed to that task. The insurer said it wo uld be carrying out mould remediation to those areas affected by the water leakage. The insurer referred to its restoration contractor’s (W’s) scope of works (dated 12 September 2018) , which was based on AD’s ( a hygienist) analysis of the mould remediation works required at the house. W had carried out the drying process in late January 2018, which included removing the remaining damaged carpet and disposing it. Insurer obtained hygienist input AD carried out various tests on the extent of mould in the house on 7, 16 February 2018, 13 April 2018 and 4 July 2018. On the last visit to the property, AD said the issues with the roof affected the moisture levels within the house: Due to the length of time between the initial assessment and this assessment/testing (6 mths) it is more difficult to assess what would have been as a consequence of the initial event, we can however, certainly say that the kitchen had been effected in the initial event … AD said mould will send out spores which can spread further throughout the house through transference and air movement. AD also said the areas showing unacceptable results may have some areas that started through the roof issue (wall openings) and have now been affected further by the kitchen. Insurer obtained roofer input B, a roofer, attended the complainant’s property on 20 March 2018. There was an issue about water ingress above the main living room and hallway. B said the roof was in a ‘fair’ condition and mentioned broken roof tiles, which caused water ingress, Determination | Case number: 521837 Page 5 of 7 had been replaced at an earlier date. However, B found broken tiles amongst the remainder of the roof. B recommended the complainant replace these tiles immediately and reopen the weep holes. B reattended the property on 9 May 2018 and noted there were still two or three roof tiles that needed replacing. There was also a broken valley above the entrance. B also said the weep holes had not been reopened to the ridge capping above the roof. B said the tiles needed replacing and the weep holes reopened to ensure the roof was water tight. Complainant required to repair roof The complainant does not see the relevance of the roof issue and indicated he had carried out repairs to the roof. However, the information AD and B provided indicates there is still an issue with the roof. B said there were repairs to be carried out to make the roof water tight. AD said the roof issues had an impact on the extent of mould in the house, which could not be solely attributable to the water leakage event. The complainant provided a report from a mould cleaning company (undated). However, this report did not challenge the comments from AD and B. The report did not indicate the probable origin of the mould. The email between the mould cleaning company and the complainant indicates an ame ndment was made to the report. However, it does not identify what the amendment was, when it was made or why it was made. That report is of no assistance to the complainant in this matter. The available information indicates it is necessary for the complainant to complete the roof repairs to ensure the mould remediation can commence and be effective. Extent of insurer’s responsibility for mould remediation However, the extent to which the insurer is required to perform the mould remediation is limited to W’s scop e of works. The remainder is due to the roof issue and is the complainant’s responsibility. Any mould remediation can only commence once the roof has been properly repaired to make it water tight by the complainant. 2.4 Is complainant entitled to compensation for non-financial loss? Complainant entitled to compensation The complainant raised various matters as to why he thought the insurer had handled his claim poorly. The recommendation fully outlined his reasons and outlined the approach to awarding compensation for non-financial loss. The recommendation accepted the claim was not straight forward. However, it identified aspects of the claims process that could have been better handled from a time span perspective. Determination | Case number: 521837 Page 6 of 7 The recommendation considered $500 as an appropriate amount of compensation. There were no submissions from either party with respect to this issue. As such, the insurer is required to pay the complainant $500 compensation for non-financial loss. 2.5 Is the insurer required to pay any additional amount? Insurer to replace carpet based on samples of old carpet The complainant said the insurer wanted to replace the damaged carpet based on the cheapest carpet replacement. The complainant provided a sample of the damaged carpet, upon which the insurer is required to base the replacement carpet. Temporary accommodation The complainant informed the insurer on 24 April 2018 he had completed the roof repairs, although a subsequent report from the insurer’s roof tiler suggested otherwise. The insurer was not required to pay the complainant any further accommodation costs beyond the date of the recommendation (30 August 2018). This was because the complainant had sufficient time to carry out the roof repairs. This would have allowed the mould remediation work to commence and the complainant would have been back in his house. There is nothing in the complainant’s submissions that warrant a change to this (the complainant had indicated he wants the insurer to pay for his six-month lease, but provided no reason why). Complainant provided further submissions Although the complainant accepted the recommendation, he provided additional submissions. He made various comments about what should be included in the scope of works: mould remediation (presumably for the entire house, as the insurer is still agreeable to remedying the water leakage related mould); painting all rooms; all skirtings; removing and re-installing insulation; yard and pool maintenance; provision of a skip to remove mould affected items. The insurer has provided compelling reasons for the extent to which it is responsible for mould remediation. Certain items in the complainant’s list are his responsibility. The reasons for this were outlined above. The complainant has provided no reasons why those items should be included in the scope of works. As such, the complainant’s further submissions do not warrant a change in the scope of works. Determination | Case number: 521837 Page 7 of 7 3 Supporting information 3.1 The determination is made under FOS Terms of Reference The Australian Financial Complaints Authority ( AFCA) has commenced managing disputes previously lodged with Financial Ombudsman Service (FOS). This determination is made under FOS Terms of Reference but has adopted the following terminology for consistency with AFCA. In this determination the AFCA terms have the same meaning as the FOS terms defined in paragraph 20.1 and Schedule 1, 2 & 3 of the FOS Terms of Reference. FOS definitions AFCA term applicant complainant financial services provider financial firm dispute complaint claim claim Recommendation Case No: 521837 Recommendation Page 1 of 11 Case number: 521837 30 August 2018 1 Overview 1.1 Dispute The applicant lodged a building and contents claim after a leak. The financial services provider (FSP) remediated water damage. It declined part of the claim because it says the floor tiles were not damaged by the leak, but fro m excluded events. The applicant disagrees with this decision and say the FSP refuses to remediate mould the leak caused. He wants the FSP to cover some of the cost to repair the tiles and carry out further mould remediation. He says the FSP handled the claim poorly. 1.2 Issues and key findings Is the FSP entitled to decline the tile claim? The FSP is entitled to decline the tile claim because its expert’s report convincingly explains why its initial installation method, and not the leak, caused the tiles to lift. Is the FSP required to carry out further mould remediation? The FSP is required to carry out further mould remediation for the entire property if the applicant provides sufficient confirmation of roof maintenance completion. If this does not occur, the FSP is to cash settle these costs. Is the applicant entitled to non-financial loss compensation? The FSP erred in its mould evaluations, which caused the applicant stress and inconvenience. It is to compensate the applicant $500 in non-financial loss. 1.3 Recommendation This recommendation is substantially in favour of the applicant. If both parties accept this recommendation, the parties are to carry out the steps outlined in Sections 2. Case No: 521837 Recommendation Page 2 of 11 2 Reasons for recommendation 2.1 Is the FSP entitled to decline the tile claim? Onus on FSP to establish policy exclusion defeats claim All insurance policies provide cover for loss or damage subject to various conditions and exclusions. These are outlined in the policy’s product disclosure statement (PDS). In this dispute the applicant has cover for damage caused by leaks, which the PDS defines as damage caused by liquid that are leaking, bursting, discharging or overflowing from certain items or devices. The parties agree the applicant established a prima facie (valid) leak claim. When an insured person establishes a valid claim, the onus shifts to the insurer to show whether the policy excludes the claimed damage. The insurer is required to establish this upon the balance of probabilities. Parties disagree on cause of damage The applicant claimed for water damage to building and contents on 24 January 2018 after a vanity unit hose burst, flooding his home. The FSP accepted the applicant’s claim and arranged contractors to assess the property’s water damage and begin restoration works. The FSP then partially declined the claim. On 7 March 2018 the FSP told the applicant it refused liability for the floor tiles. The FSP said its tiler’s (SP’s) report confirmed tile damage occurred due to insufficient installation methods, rather than the leak. The FSP based its partial decline on a policy exclusion for damage not linked to an insured event, contained in full in Section 3.1. The applicant denies the policy exclusion applies and says the tiles only started to lift after the leak flooded them. He maintains the leak damaged the tiles and wants the FSP to accept liability for all or some repairs, or arrange for an expert building report. The applicant provided reports by NS and GC, tilers who concluded moisture from the leak affected the tiles’ adhesive bond and caused the damage. As the experts dispute how tile damage occurred, the proximate cause of the damage needs to be considered. Policy coverage depends on proximate cause The proximate cause of damage is a question of fact depending on the circumstances in each dispute. It is not necessarily the first or last or the sole cause of the loss. Case No: 521837 Recommendation Page 3 of 11 Proximate cause is the effective, dominant or operative cause of the loss. If there are several causes operating at the same time, FOS will consider each one to determine which cause set the train of events in motion. Courts have said if one cause would have resulted in the harm in any case and the other would not have done so in the absence of the first, then the first is the proximate cause. Reports suggest tiles failure not related to claimed event I closely reviewed the reports and accept SP’s report establishes, on balance, the damaged tiles become drummy and de-bonded before the leak, due to their installation methods. SP’s comments are contained in Section 3.2. These highlight the tile s’ adhesive delaminated from the inside -out. SP views this as inconsistent with the usual effects of water ingress, which he says in almost all cases de-bonds the adhesive from the outside in. Based on this and other observations captured in his report, including the grouting style, lack of movement joints and location of cracks relative to damaged tiles, SP concluded the leak did not cause the damage. I find SP’s reasons persuasive because they are supported by explanations and photographs of the observations and/or tests on which SP based his conclusions. The report also shows consideration of the impact of the substantial, lengthy leak flooding the tiles, but other causes of tile damage SP observed sufficiently refute it was the proximate cause. Based on his attached curriculum vitae, I am also satisfied SP’s analysis is based on significant expertise in tiling, waterproofing and repair methods. While I am also satisfied NS is a licensed tiler, his report does not indicate whether he inspected the property. GC is also a tiler who attended the property, however neither his nor NS’s report explains how they reached the conclusion tile delamination occurred due to the leak. They do not mention or challenge several other convincing causes of damage SP raised and contain only conclusions For these reasons, I am more convinced by SP’s report. As I find SP’s conclusions comprehensively support by the contents of his report, the FSP is not required to obtain a further building report as requested by the app licant. Given the above, I accept SP’s view the leak was not the proximate cause of the claimed tile damage. FSP is entitled to rely on policy exclusion For all these reasons, I accept the FSP’s expert established the leak did not cause the damage. Accordingly, I satisfied that the FSP has established on the balance of probabilities it is entitled to rely upon the policy exclusion for damage not linked to the leak. Case No: 521837 Recommendation Page 4 of 11 The FSP is therefore entitled to decline liability for tile repairs. However, SP’s report did not deny the leak caused some paint covering the grout to flake off, as GC explained. If it has not already done so, the FSP is to include the cost of re-painting flaked or missing paint over the grouting in its cash settlement. This is to occur within 14 days of both parties’ acceptance of this recommendation. 2.2 Is the FSP required to carry out further mould remediation? Parties dispute FSP liable for further mould remediation The FSP confirmed the presence of mould in the wall cavity and roof in Februar y 2018, which the applicant claims was caused by the leak. The applicant says the FSP did not complete mould remediation works. He wants the FSP to provide:  carry out further mould remediation at the property, including within the walls, roof and flooring  provide a scope of works and timeline for work completion  reimburse accommodation expenses incurred while he awaited remediation. The FSP also says it is entitled to refuse remediation works to the roof and ceiling areas because it says the leak event did not cause mould to these areas. Regarding the walls, the FSP refuses to carry out further mould remediation or testing at present. It says the applicant needs to carry out maintenance works to the roof, or any mould treatment will be ineffective. The FSP says it asked the applicant to provide invoices confirming the repairs it requested are complete, but he has not yet done so. The FSP says once the applicant provides confirmation, it will engage a builder and then hygienist to attend to any remaining roof or (accepted) mould issues. FSP did not establish it remediated mould following leak I closely reviewed the FSP’s reports and claim records. After lodgement, the FSP’s disaster restoration contractor (WR) carried out mould remediation works for several days. Based on these, I am satisfied the substantial works took several days and included removing all carpets and skirting boards to dry, dehumidifying and sanitising the property’s floor and then carrying out moisture tests. On 31 January 2018 the FSP’s assessor (CL) inspected the property and decided no mould was present, based on WR’s verbal advice and his own visual observation the wall cavities lacked mould. However at the applicant’s request, CL arranged mould air testing, which occurred on 7 February 2018. CL reported on 20 February 2018 mould test results by AD, a hygienist, confirmed the presence of mould. AD completed mould swab testing on 16 February 2018. These results found unacceptable mould levels in the wall cavity and ceiling. Case No: 521837 Recommendation Page 5 of 11 AD’s report of 6 April 2018 referenced a discussion with a builder about their preferred approach to treating the property’s mould. The FSP did not provide this Service with a copy of the builder’s report. However overall I accept AD’s views establish the FSP is unable to warrant mould remediation works until the applicant completes (unrelated) roof maintenance works necessary to enable effective remediation. The FSP based its refusal to cover wall/ceiling mould on CL’s view, which is contained in Section 3.2. CL con cluded AD’s preferred approach to treating the mould (by first addressing maintenance issues to enable effective remediation), along with the property being dry at 20 February 2018 with a lack of visible or airborne mould at 7 February 2018, confirmed the leak did not cause the mould and stated ‘t here is no logical reason why we have increased mould levels ’ . I do not agree with CL’s conclusion or consider it supported by the mould test results or claim circumstances. This is because the applicant’s property experienced substantial water inundation for up to 48 hours followed by sustained attempts to dry the property. WR’s report confirmed visible mould occurred in the carpets by 29 January 2018. Air testing performed on 7 February 2018 confirmed mould, as di d swab testing performed on 16 February 2018. The other comments in AD’s report contained in Section 3.2 on balance do not establish maintenance issues (cracked tiles in the roof or insulation type) as the proximate cause of the ceiling, wall or other mould. Given this, the parties’ materials do not establish the FSP is entitled to limit its liability for mould at the property. The FSP is therefore liable for further mould remediation. Applicant did not confirm roof maintenance completed The applicant says the roof is repaired and regardless is of no relevance to mould issues within the walls. He disagrees with AD’s view maintenance works to the ceiling is required by the applicant before the FSP can warrant repairs. He says:  these repairs included only two tiles with minor cracks  they are not related to walls or flooring  he believes his roof is watertight. I give greater weight to AD’s views on the steps required to enable appropriate mould remediation works. I am not convinced the appli cant’s photographs and his belief about the adequacy of repairs establish mould remediation works will now be effective. The applicant wants the FSP to remediate the property rather than cash settle repairs. However since April 2018, he has had sufficient time to arrange for these repairs and provide confirmation to the FSP. Case No: 521837 Recommendation Page 6 of 11 FSP is required to remediate the mould or cash settle these costs I note it is possible for mould damage to increase if both parties do not take the steps outlined to allow for mould remediation works. Given this, if both parties accept this recommendation, I consider it fair in all the circumstances for the:  applicant, within 21 days, to provide the FSP with a builder’s invoice confirming the requested roof maintenance works are complete  within 7 days of receipt, the FSP is to commence mould remediation works. If the applicant elects not to do so, then the FSP is to cash settle the claim within 14 days of the 21 days expiring. The cash settlement is to be based on a quote and scope of works for mould remediation of the entire property, allowing for final mould clearance (including swab and air) testing. In confirming roof maintenance is complete, the applicant is not required to install new insulation, given I accepted the FSP is liab le for the property’s mould. This includes mould the FSP noted likely exists within the insulation material itself. Regardless I am satisfied new insulation should be installed after, and not before, mould treatment. Other claims The FSP reimbursed the app licant’s accommodation costs until 25 April 2018. Claim records confirm the applicant told the FSP on 24 April 2018 he finished the requested roof repairs. However he has not yet provided sufficient confirmation the requested repairs occurred, so remediation has not yet commenced. Given this, the FSP is not liable for accommodation from the date of this recommendation until the date the applicant provides the FSP with such confirmation. The applicant also says the FSP requested the cheapest carpet replacement, which he says is unreasonable as he provided matching carpet samples. The policy states the FSP will pay the cost to repair the applicant’s home using the same materials if they are readily available in Australia. Accordingly if it has not already done so, the FSP is to base the carpet settlement on the (old) carpet samples the applicant said he provided its agents. 2.3 Is the applicant entitled to non-financial loss compensation? Applicant argues the FSP handled the claim poorly The applicant says the claim experience was stressful and confusing. He says:  the FSP’s assessor incorrectly advised of no mould on initial assessment and based on this his family returned to an unsafe home environment Case No: 521837 Recommendation Page 7 of 11  AC did not investigate mould until prompted by the applicant  the tests confirmed the property contained mould and was therefore unsafe  the FSP and its contractors failed to respond in an adequate manner, generally  he needed to repeatedly seek information before to receive any claim updates The applicant also says the requirement to seek reimbursement from the FSP for accommodation payments causes him financial stress, due to exiting financial commitments for the insured property’s mortgage and other bills. He argues the FSP’s lack of repair timeframe prevents him from mitigating accommodation costs by arranging, for example, a short-term rental. Applicant is entitled to $500 non-financial loss compensation FOS’s Terms of Reference allow the payment of compensation (capped at $3,000) for non-financial loss. FOS may decide an FSP should compensate an applicant for such loss only where there has been an unusual amount of physical inconvenience, time taken to resolve a situation, or interference with the applicant’s expectation of enjoyment or peace of mind. FOS takes a conservative approach to compensation for non-financial loss. The parties’ materials confirm the FSP arranged for disaster restoration specialists to attend to the property’s flooding almost immediately and it appears the FSP continues to reimburse the applicant’s accommodation. The FSP did not cause the leak or mould, the complex situation involving the roof is beyond the FSP’s control and it agreed to further mould inspection (after roof maintenance) from 24 April 2018. However, the applicant needed to raise concerns about mould before the FSP agreed to initial testing. CL’s initial view on the absence of mould and his later conclusion on AD’s view of the cause of mould is unsupported by the claim materials. Although the AD further tested for mould on 16 February 2018, the FSP did not tell the applicant about necessary roof maintenance until 24 April 2018. I accept these decisions caused the applicant physical inconvenience and stress. In all these circumstances the FSP is to pay the applicant $500 i n non-financial loss compensation. This is to occur within 14 days of the date both parties accept this recommendation. Case No: 521837 Recommendation Page 8 of 11 3 Supporting information 3.1 Policy Your cover Insured events We cover loss or damage to your home or contents that is caused by certain events. We call them insured events. For us to cover you for loss or damage caused by an insured event, the event must happen … during the period of insurance. Leak Liquids that are leaking, bursting, discharging or overflowing from certain items or devices. General exclusions What we don’t cover We don’t cover you under your policy for loss or damage to your home or contents or for legal liability which is caused by or arises in connection with any of the following items, events or circumstances: Loss not linked to event Loss to your home or contents which can’t be linked to any identifiable event … Settling your claim Options to settle your claim We may choose, at our option, one or more of the following ways to settle your claim: 1. Pay the cost to have your home rebuilt or repaired as new – that is, pay to rebuild or repair it using the same materials if they are readily available in Australia or equivalent materials in terms of quality, purpose and specifications. Temporary accommodation We pay your reasonable temporary accommodation costs after an insured event happens. If we agree to pay your claim for an insured event and you need to move out of your home because the event makes your home unfit to live in, then we pay (or reimburse you for) your: Case No: 521837 Recommendation Page 9 of 11 - ongoing accommodation costs while your home is being rebuilt or repaired for up to 12 months from when the insured event happened until your home is fit to live in. 3.2 Reports Record Key points FSP’s expert ( SP ) Licensed tiler Report 23 - 02 - 2018  Below are my findings through a visual ins pection and resonance testing of the floor tiling system  The tiles have been installed directly onto the concrete sub - strate with an approximate grout joint size of 10 - 15mm to the main floor areas and with a 3mm grout joint size in the remaining wet areas using an unknown type of adhesive (As no tile removal was conducted) and grouted using proprietary blended floor grout. In m y professional opinion this main floor has not been installed by a professional tiler, but instead has been a D.I.Y install.  I had been informed there had been a water ingress suffered from a burst flexible water feed hos e located in the vanity cupboard wi thin the bathroom. This water ingress has been reported to have potentially flowed for a period of 48 hours and covered up to 90% plus of the dwellings foot print within the internal areas.  As stated earlier all of the drummy/de - bonded tiles have occurred w ithin the main floor area as listed: Entry 1 Tile; Office/Dining 34 Tiles ; Kitchen 12 Tiles .  With close analysis of the drummy/de - bonded tiles through both a close - up visual inspection and the resonating sounds that are emitting from particular tiles, in m y expert opinion all of the currently drummy/de - bonded tiles where pre - existing to the water ingress event.  As an example, the tiles in particular within the kitchen area are mainly emitting the drummy sound from the centre of the tile and are consistently solid/sound to the majority of the tile. This is inconsistent with what is considered usual for tiles that have been directly affected by a water ingress event, water ingress events cause the tiles in 99% of cases to de - bond from the perimeter inwards not from the centre out wards.  Some of these tiles are emitting a very ‘High Pitched’ sound that indicates to me from our past vast experience of repairing tiles that the original installer has failed to achieve the correct adhesive coverage/bond with the til es.  I have als o witnessed within the office/dining area that where the owner has identified (and marked majority) drummy tiles that there has been movement that has occurred previously to the water ingress event occurring. This movement has been evidenced by 2 x crack lines to the grout joints … This crack - line in some places has actual sections of grout missing from within the grout joint itself, to which is a direct indication to me that this has occurred at least 12 months or more prior. The majority of tiles that are currently drummy within the lounge/bar area are loc ated directly against the Case No: 521837 Recommendation Page 10 of 11 area of the crack - line …  The tiles that are loc ated against the sliding door track have been subjected to thermal expansion occurring to the dark coloured door trac k being heated by the direct sunlight that hits it at some point in the day. As there are no movement joints located within the entire floor tiling system, that is no perimeter or intermediated movement joints installed at all, then the thermal expansion a nd movement that will occur within any floor tiling system has no ability to be absorbed and as in this case and many others res ults in the tiles becoming drummy/de - bonded over time.  In conclusion the failure that has occurred within this dwelling to the f loor tiling system has been a pre - existing condition that has been caused by the original installer not achieving the correct adhesive coverage/distribution … [and installing] the correct type and amount of movement joints to ensure the longengevity of the tiling system. Applicant’s expert (NS ) Licensed tiler Report 04 - 04 - 2018  The e xisting floor tiles … have taken significant damage due to flooding/wat er damage.  Moisture has affected the bond of old adhesive to the point of delamination.  The tiles should be removed and replaced as soon as possible. Applicant’s expert (GC ) Tiler Report Undated  I recently visited … to inspect the flooded tiled area due to a burst pipe in the bathroom.  I have been a tiler for 10 years now … with my experience I have come a cross cases like this one where water damage has caused tiles to become 'drummy ', discolour cosmetically and grout to lift.  As the tiles in this property were laid thirty (30) plus years ago, it is hard to determine what adhesive was used to lay the tiles etc., and in my opinion the flooding that occurred was a contributing factor to the tiles becoming 'drummy'.  The tile grout has clearly discoloured, and lifted in areas, and in my opinion the water that flooded this area would have contributed to the discolouration and lifting grout as it covered the tiled area for a substantial period of time. FSP’s expert (AD ) Hygienist Rep ort 06 - 04 - 2018  Recommendations: t he continued entrance of moisture in the roof cavity via broken roof tiles and the removal of the cellulos e insulation needs to be addressed and rectified as a start point in the remediation of the dwelling, then the ceilin g/roof cavity can then be inspected for any mould or moisture issues.  This is the best at this stage and cheapest way forward in the remediation of the dwelling.  Initially post remediation environmental testing was conducted on 07 Feb 18 for the degree of viable (live) mould within the dwelling … all samples at the time were of an acceptable level, noting that the outside air sample was quit e high … it appeared tha t all the majority of remediation action had been completed except the removal of the damaged kitchen cabinetry. I noticed no visible mould and the dwelling had no obvious smells associated with mould issues. On the 16 Feb further internal wall testing was Case No: 521837 Recommendation Page 11 of 11 requested … to determine the levels of viable mould Colony Forming Units (CFU’s) within the wall cavities … as the owner had further concerns of mould within the dwelling due to his child.  Six of the seven mould samples were classed as not acceptable at t he time of testing, all six samples were taken from wall cavities.  Other comments: all internal walls/studs etc had a moisture reading of 11 to 13% which is considered dry ; Water damage is noted within the kitchen dining room area whether the damage is old or new it points to concurrent issues within the roof cavity; Water will wick up a wall to approximately 60cm, all internal walls opened up had no sign of wicking or water damage whatsoever; The expens e of removing internal walls may indeed out way the co st of fixing the roof and investigating the roof cavity as if the moisture issues are not addressed first mould issues will continue to appear within the dwelling . FSP’s expert (CL ) Loss assessor Assessment update 20 - 02 - 2018  The areas tested and which are not accept able are – Inside wall near the main bedroom; Inside wall near the front door; Inside wall near the dining room; Kitchen kick panel; C eiling in the dining room where there is unrelated water damage .  [AD] have stated they are of the opinion the r eason for the high readings is due to ongoing water issues within the roof space . Therefore, if the property is dry as per the report dated 20th February 2018 and the readings not ed on the 12th February stating all areas were noted as either Acceptable or Good, why have the walls tested as Not Acceptable now when the property has been dried and also the Insured has fixed the leak. There is no logical reason why we have increase mould levels.  However the internals of the walls were NOT swab tested on the 12t h February only air sampling was tested .