Home / Financial Firm (Unknown - Insurer) / Determination 521109

Determination 521109

Shower leak claim declined as shower not a covered item; claimed link to earlier bath overflow claim not established

FirmFinancial Firm (Unknown - Insurer)
Decided2018-07-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant sought cover for a shower leak and for repairs to the waterproof membrane linked to an earlier bath overflow claim. AFCA found the shower is not a covered item and the applicant had not shown a causal link to the earlier claim, so the determination is in favour of the FSP.

A defined-events policy responds only to listed apparatus and events, and the applicant bears the onus of establishing a causal link to an earlier covered claim.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 521109 Determination Page 1 of 5 Case number: 521109 19 July 2018 1 Overview 1.1 Dispute The applicant holds a home building and contents policy underwritten by the financial services provider (FSP) covering her home address. On 8 May 2015, the applicant lodged a claim under the policy for liquid escaping from her shower (claim two). The applicant believes the shower is leaking due to the rupture of the waterproof membrane, which was caused by a previous escape of liquid claim from the bath in 2012 (claim one). The applicant seeks the cost to remedy the waterproof membrane and other yet to be determined repairs be covered by the FSP. The FSP says there is no evidence that there was damage sustained to the waterproof membrane or any part of the bathroom from claim one. It says the two claims are separate, standalone events and should be assessed individually. As the policy specifically excludes loss or damage from water escaping a shower, it is entitled to decline claim two. 1.2 Issues and key findings Was the FSP entitled to decline the claim? The FSP was entitled to decline claim two because:  the policy is a defined events policy;  the policy contains an exhaustive list of apparatus which it will cover an escape of liquid claim from;  a shower is not one of the listed apparatus;  therefore, the policy does not respond to the loss. The FSP is not liable to undertake any further repairs under claim one because:  there is insufficient evidence to show the bathroom, shower or waterproof membrane sustained any damage from claim one;  the FSP has previously repaired the resultant damage from claim one. 1.3 Determination This determination is in favour of the FSP. The FSP was entitled to decline the claim and is not required to take any further action. Case No: 521109 Determination Page 2 of 5 2 Reasons for determination 2.1 Is the FSP entitled to deny the applicant's claim? Onus on applicant to establish a prima facie claim It is accepted insurance law that the applicant carries the onus of proving , on balance, that an insurable event has occurred. This is known as a prima facie claim. Once the applicant has established a prima facie claim, the onus shifts to the FSP to establish, on balance, and entitlement to decline the claim on the basis of a policy exclusion or some other basis. The FSP's policy is a defined events policy. Therefore, the policy only responds to loss or damage caused by one of the listed events. One of the listed events is bursting, leaking, discharging or overflowing of liquid. As an aside, the applicant has purchased the optional cover of accidental damage. However, the policy is clear that this refers to accidental loss or damage from an accident as opposed to broadform accidental damage cover. Therefore, the claim will be assessed against the relevant insured event as set out in the relevant policy applicable at the time of each event. Policy covers escape of liquid only from the specified items There is no dispute the current policy covers loss caused by an escape of liquid. However, the policy provides an exhaustive list of items of which it will respond to claims from. A bath is one of the listed items. However, a leaking shower recess or cubicle is not one of the listed items. In fact , the policy specifically excludes loss or damage from a leaking shower floor or base, shower cubicle walls, shower glass screening or doors. Further, the cost to repair the item from which the liquid escaped is not covered under the terms of the policy. There is no dispute the shower is leaking. Leak detection tests showed the shower failed the static test to the shower base and the spray test to the screen. Therefore, the costs to repair the shower itself are not covered as it is the leaking item. And were it to be found that there was any resultant damage from the leaking shower (none is evident at the time of writing), this is also not covered as the policy does not respond to resultant damage from a leaking shower. On this basis, the FSP was entitled to decline claim two. 2.2 Is the FSP liable for further repairs under claim one? Claim one repairs undertaken in 2012 There is no dispute the FSP accepted claim back in 2012. This claim was due to a bath overflowing (a covered event under the policy in place at the time), causing damage to the nearby staircase and ceilings below. The FSP undertook the Case No: 521109 Determination Page 3 of 5 necessary repairs to the resultant damage in 2012. There was no damage to the bathroom recorded as a result of the event, and no repairs to the bath as it was not leaking or otherwise malfunctioning, it simply overflowed. Were it to be accepted that claim one did cause damage to the bathroom, waterproof membrane and/or shower, then this would be sufficient to bring the repairs to the shower and/or waterproof membrane in under the claim. A leaking shower would be covered where this was resultant damage, as opposed to the source of the water escaping or leaking. As the party seeking the benefit of extended cover under claim one, the onus rests with the applicant to show a clear causal link between the two. FSP expert evidence The FSP appointed engineering firm “JH” to inspect the bathroom and comment on if claims one and two could reasonably be considered to be related. JH‟s reports are quite unequivocal in stating the two events are not linked. JH says that if claim one had caused damage to the substrate such that it was able to crack or penetrate the waterproof membrane, then it would be expected that the timber substrate was swollen. However, visual inspection showed it was not. Whilst the timber floor was water stained from the bath overflow event, this does not constitute „damage‟ as it is merely cosmetic and does not interfere with the function or structural integrity of the floor. JH noted there were no other signs of movement in the building such as cracked tiles or cracks at the junction. JH also says that a waterproof membrane should be of flexible material so as not to rupture during building movement. Any event causing rupturing of the waterproof membrane would need to be significant. JH noted the entire bathroom appeared to have been waterproofed at the time it was last renovated, which is good practice. As the water escaping from the shower was tracking through the grouting, this indicated the waterproof membrane was intact and stopping water permeating through the floor. This was also confirmed by the subfloor inspection which showed no water staining from this event. Cause of the shower leak is the lack of a water stop JH concluded the cause of the leaking shower was due to the lack of, or an inadequate, water stop. JH noted the bathroom appeared to date from the late 1990‟s to early 2000‟s, based on its décor. The shower recess is classed as an enclosed shower recess as it is fully framed. The Building Code of Australia (the Code) requires that an enclosed shower recess with no hob or set down (as is the case with the applicant‟s shower) be fitted with a water stop to protect the area from water damage. The Code provided this requirement from the 1996 revision onwards. Accordingly, JH concluded the shower did not comply with the Code at the time it was installed. The onus to remedy this does not transfer to the FSP simply because it insures the home. Case No: 521109 Determination Page 4 of 5 JH also noted there was evidence of prior silicone application to the area, indicating previous attempts to arrest water escaping from the shower. This is evident in the photographs provided. JH outlined that the problem could be easily and cost- effectively remedied by the installation of a water stop in the shower. Re-application of silicone alone will not arrest the problem. Applicant’s expert evidence The applicant was invited to provide her own report from a suitably qualified person in support of her position that claim one had ruptured and compromised the waterproof membrane, thus causing the shower to leak. In support of her position, the applicant provided reports from builder “GM”. GM‟s initial report states that visual inspection of the bathroom subfloor revealed the ti mber substrate had swelled and severed the waterproof membrane, allowing water to penetrate the laundry ceiling below. However, there is no current damage to the laundry ceiling, and photographs of the subfloor do not depict swollen timbers. The waterproof membrane is not visible from the subfloor, so it is unclear how GM formed the viewed this had ruptured. GM‟s later report agrees there is a leak from the shower. He maintains this is due to the ruptured membrane, although he later concedes it is not possible to determine for certain whether the membrane has ruptured without invasive testing, such as pulling up the tiled floor to investigate. I am of the view that GM‟s conclusions are speculative at best, and he has presented no more than a potential theory of how the shower came to be leaking. Therefore, the FSP‟s evidence is to be preferred. Further, GM has not commented on the lack of water stop, leaving JH‟s conclusions unchallenged. On this basis, the applicant has not demonstrated a link between claims one and two, so as to bring her claim for repairs to the shower within the ambit of claim one. Therefore, the FSP is not required to indemnify her further under claim one and is considered to have discharged its liability for this claim with the repairs previously undertaken. Applicant may present further evidence However, in the event the applicant chooses to proceed with GM‟s recommendation of stripping out the entire bathroom as opposed to JH‟s recommendation to merely install a water stop, and it is discovered the membrane is ruptured or other damage is present to the bathroom from claim one, then the FSP is to re-assess its liability at that time. Case No: 521109 Determination Page 5 of 5 3 Supporting information 3.1 FOS approach to this dispute A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to FOS. However, commentary in this determination is restricted only to those issues considered relevant to the outcome.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.