Home / Financial Firm (Unknown - Credit) / Determination 520479

Determination 520479

Hardship arrangement not finalised; arrears not capitalised and enforcement fees applied

FirmFinancial Firm (Unknown - Credit)
Decided2018-09-04
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

The applicants had a hardship arrangement, and the FSP capitalised arrears on only one of their loans and then applied enforcement fees. AFCA found the FSP substantially met its obligations but should capitalise the arrears, reverse fees caused by that failure, and pay $1,000 non-financial loss.

A credit provider must genuinely consider hardship requests and honour agreed arrangements, so fees arising from its failure to capitalise must be reversed while fees from later missed payments remain payable.

Issues

Subjects and remedies

financial hardshiploan or hardship variationpay non financial lossrefund fees or charges

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 520479 Determination Page 1 of 6 Case number: 520479 14 August 2017 1 Overview 1.1 Dispute The dispute concerns a number of loans obtained by the applicants from the financial services provider (FSP), including:  two Home Loans and two Investment Loans jointly held by the applicants and  a Personal Loan in the sole name Mr applicant. The FSP provided the loans between July 2014 and August 2018. Details of the facilities are contained in section 3.2 of this Determination. The applicants claim that the FSP:  failed to honour a hardship arrangement entered in March 2017, despite their adherence to the arrangement and  applied unnecessary enforcement expenses to their loans without firstly notifying them of the arrears accrued during early 2018. 1.2 Issues and key findings Did the FSP meet its financial difficulty obligations? Based on the available information, the FSP has generally met is financial difficulty obligations as it has continued to work with the applicants since their initial hardship request in 2016. However, in order to fully comply with its obligations the FSP should have:  ensured that the arrangement entered in March 2017 brought finality to the matter by also dealing with how the arrears were to be repaid at the end of the six months in August 2017 and  capitalised the arrears on all accounts once the applicants had met all repayments under the arrangement offered by August 2017. Was the FSP entitled to apply legal fees on the applicants account? The FSP was entitled to apply fees charged due to engagement of its solicitors on 2 February 2017. The FSP was not entitled to apply the fees that are a direct result of it failing to capitalise the arrears in August 2017. The FSP should also pay $1,000 non-financial loss to the applicants. Case No: 520479 Determination Page 2 of 6 The FSP is entitled to apply the fees applied due to any subsequent missed repayments after August 2017 that have been fairly and properly incurred. What is an appropriate outcome? If the applicant accepts the Determination, the parties should take the steps set out below in section 1.3. 1.3 Determination This Determination is substantially in favour of the applicants. If the applicants accept this Determination within 30 days, then:  within seven days of acceptance, the FSP should credit the Home Loans and Investment Loan 2 with a total of $1,000 for non-financial loss compensation however it sees fit  within seven days the FSP should capitalise the arrears amount as at 25 August 2017, on the Home Loans and Investment Loan 2  within seven days of acceptance, the FSP should reverse any fees and interest applied on those fees that are a direct result of failing to capitalise the arrears in August 2017, on the Home Loans and Investment Loan 2  the applicants should continue to meet their repayment obligations on all facilities and  Mr applicant should work with the FSP to enter into an arrangement to see the Personal Loan repaid within a reasonable period, if it remains unpaid. If the applicants are in financial difficulty, then they should provide a completed Statement of Financial Position, including any supporting documentation and put forward a proposal within 14 days of accepting this determination for any outstanding arrears on any loan and the Personal Loan, if it remains unpaid. If this occurs, the FSP must consider the applicants ’ proposal and any reasonable alternatives that may assist the applicants, but is not obliged to accept any proposal if it does not consider it to be reasonable If within a further 14 days of the applicants providing the information, the parties cannot agree on an arrangement that will see the debt repaid within a reasonable period, or if they do not provide any proposal, the FSP will be entitled to commence recovery action, once our file is closed. If the applicants do not accept this Determination, the FSP is not required to take the steps set out above and it may continue with recovery action in accordance with the terms and conditions of the loans, once our file is closed. Case No: 520479 Determination Page 3 of 6 2 Reasons for determination 2.1 Did the FSP meet its financial difficulty obligations? The FSP substantially met its financial difficulty obligations A credit provider should be able to demonstrate that it has tried to work with a customer in financial difficulty and genuinely considered a request for assistance. The applicant should also be willing to work with the credit provider and propose a realistic repayment plan that will repay the loan within a reasonable time. I have reviewed the information provided by both parties and I am satisfied that the FSP has generally met its financial difficulty obligations to the applicants for the following reasons:  The FSP made reasonable attempts to contact the applicants and notify them of the arrears on their Loans from early 2016.  In response to the applicants’ initial hardship request in September 2016, the FSP requested information to determine whether it could offer assistance and decided to offer nil repayments for the month, followed by a review at the end of the month, as Mr applicant had indicated he had a third-party case which was due to settle.  The FSP sought an update and on 20 October 2016, which resulted in a six- month serviceability arrangement being offered. This was not maintained by the applicants.  The FSP only referred the applicants ’ account to its solicitors on 2 February 2017, after making reasonable attempts to contact the applicants after the October 2016 serviceability arrangement was broken in December 2016.  The FSP ensured it utlised a translator when speaking with Mrs applicant upon being on notice of the requirement in February 2017.  The FSP considered another hardship request on 28 February 2017, and requested an updated Statement of Financial Position to assess that request.  On 17 March 2017, the FSP offered a si x-month serviceability test with the possibility of capitalization after considering the applicants Statement of Financial Position, which showed a substantial surplus of $2,506 and  the FSP appropriately confirmed the March 2017, serviceability arrangement in writing via email. The FSP did not fully meet its obligations as follows: although it had decided to capitalise arrears on the applicants ’ Home Loans and Investment Loans once they had proven serviceability by August 2017, it only capitalise the arrears on Loan 1. The FSP says this was due to human error. The FSP then refrained from capitalising arrears on the other loans solely because Mr applicant did not provide verbal consent for capitalisation. The FSP says it is standard practice for it to contact individuals to seek verbal consent at the end of a serviceability arrangement to confirm capitalisation. This is because capitalisation results in an increase in repayments and variation to the Loan. Case No: 520479 Determination Page 4 of 6 The FSP’s practice above is generally fair and reasonable. However, in the circumstances of this case, particularly the entry in the collection notes dated 28 August 2017, Mr applicant was of the view that capitalisation was implied in the agreement and he asked for the FSP to put its decision to capitalise in writing before he agreed. However, the FSP did not put the request in writing at that time, but delayed doing so until December 2017. Although Mr applicant could have just consented verbally at the time, given this is the outcome he is seeking now, the FSP could have also avoided this situation by bringing finality to the matter in March 2017. This could have been done by the FSP addressing how the arrears were to be repaid with certainty once repayments were met up to and including August 2017. For example, the FSP could have included a clause to specify the requirement for verbal consent when it confirmed the arrangement with the applicants by email on 21 March 2017. The FSP knew capitalisation was conditional upon consent being provided and not an immediate and automatic outcome of the serviceability arrangement being met. For the above reasons and the fact that the applicants met the March 2017 arrangement for six months, the FSP should capitalise the arrears as at 25 August 2017, which is when it decided capitalisation was appropriate. The FSP should also provide the applicants with $1,000 in non-financial loss compensation for the stress this has caused. 2.2 Was the FSP entitled to apply fees? The FSP was entitled to apply certain fees but not others From the available information, I am satisfied that the FSP was entitled to refer the applicants ’ accounts to its solicitors on 2 February 2017, and the fees applied as a result are justifiable. This is because:  the applicants had not maintained the October 2016 arrangement and  its attempts to contact the applicants since December 2016, when the arrangement was broken, were unsuccessful. The FSP should however reverse any fees, including legal fees and any interest applied on the fees, incurred as a direct result of its decision not to capita lise the arrears in August 2017, as these would not have been incurred if the arrears were capitalised. The FSP was entitled to apply all fees incurred due to subsequent missed payments and accrual of arrears post 25 August 2017, as no arrangement or hardship review was in place at the time. 2.3 What is an appropriate outcome? The FSP should capitalise the arrears as at August 2017 If the applicant accepts this determination within 30 days, the FSP should within seven days reduce the balance of the Home Loans and Investment Loan 2 (however it sees fit) by a total of $1,000 in non-financial loss compensation. Case No: 520479 Determination Page 5 of 6 The FSP should also within seven days of the acceptance capitalise the arrears as at 25 August 2017, on the Home Loans, and Investment Loan 2 and reverse any fees, including enforcement fees and any interest applied on them as a direct result of the arrears not being capitalised on the Home Loans and the Investment Loan 2, as at 25 August 2017. The applicants should continue to meet repayments on their Home Loans and Investment Loans, as their Statement of Financial Position provided on 30 April 2018, shows a surplus of $1,439 after repayments are met to each facility. If the applicants are in financial difficulty, they should provide within 14 days of accepting this Determination an updated Statement of Financial Position, including any supporting documentation and a proposal to clear any arrears that remain on the Home Loans and the Investment Loans after the FSP capitalise the arrears, reverse the fees and apply the non-financial loss compensation. This should also include a proposal for the Personal Loan, if Mr applicant did not already clear the remaining balance as he said he would in his email dated 18 June 2018. The FSP must consider the applicants ’ proposal and any reasonable alternatives that may assist the applicants, but is not obliged to accept any proposal if it does not consider it to be reasonable If within a further 14 days of the applicants providing the information, the parties cannot agree on a reasonable arrangement, or if the applicants do not provide a completed Statement of Financial Position and proposal within the required timeframe, he FSP will be entitled to commence recovery action, once our file is closed. If the applicant does not wish to accept this Determination, the FSP can recommence recovery action, once our file is closed. Case No: 520479 Determination Page 6 of 6 3 Supporting information 3.1 Decision process This dispute was the subject of a preliminary view that was substantially in favour of the applicants, which was not delivered to the applicants as attempts to contact them were unsuccessful. I have considered all the material submitted by the parties, both before and after the preliminary view was issued, in order to reach my decision. I am satisfied that the material I relied upon in reaching my findings has been exchanged between the parties. I have had regard to what is fair in all the circumstances, considering legal principles, applicable industry codes or guidance as to practice, good industry practice and previous relevant decisions of FOS. 3.2 Details of facilities Facility Balance Arrears Interest rate Monthly repayment Home Loan 1 $537,998.44 $4,131.76 4.10% (variable) $2,228.38 Home Loan 2 $428,170.80 $13,739.05 4.40% (fixed) $2,219.77 Investment Loan 1 $59,590.90 $5.04 4.90% (fixed) $334.16 Investment Loan 2 $272,917.00 $6,862.30 4.90% (fixed) $1,490.15 Personal Loan $1,000.00 $1,000.00 15.99% Due & payable The above figures for the Home and Investment Loans were provided on 24 April 2018, and the figure for the Personal Loan was provided on 26 June 2018. All figures provided are subject to change due to accrual of interest, fees and any missed payments.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.