The landlord's claim for peeling ceiling paint was declined as the damage was not caused by water ingress or another insured event. AFCA accepted the FSP's expert evidence that the cause was a paint defect.

The policy is a defined-events policy and the applicant failed to show the peeling arose from a listed event, so the FSP was entitled to decline.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 519944 Determination Page 1 of 4 Case number: 519944 10 August 2018 1 Overview 1.1 Dispute The applicant holds a landlord insurance policy underwritten by the financial services provider (FSP) covering a tenanted property. On 20 December 2017, a claim was lodged under the policy in respect of peeling paint to the ceilings. The applicant believed this was due to water ingress to the celling cavity. After considering the claim, the FSP declined it on the basis that the damage was not caused by water ingress or any other insured event. Rather, the damage had arisen due to either the method of the original paint application or new paint being applied over the original, and this is not a loss to which the policy would respond. 1.2 Issue and key findings Was the FSP entitled to decline the claim? The FSP was entitled to decline the claim because:  the policy is an insured events policy; and  there is insufficient evidence to suggest the damage arose as a result of an insured event. 1.3 Determination This determination is in favour of the FSP. The FSP was entitled to decline the claim and is not required to take any further action. Case No: 519944 Determination Page 2 of 4 2 Reasons for determination 2.1 Was the FSP entitled to decline the claim? Applicant has the onus to establish a prima facie claim It is established insurance law that the applicant carries the initial onus to show, on balance, the terms and conditions of the relevant insurance policy covers the loss. This is known as a prima facie claim. Once the applicant establishes a prima facie claim, the onus then shifts to the FSP to demonstrate, on balance, the loss is not covered, either by way of one of the policy exclusions or on some other basis. The FSP‟s policy is a defined events policy. The refore, the policy only responds where an incident caused by one or more of the listed events results in loss or damage, subject to any exclusions. One of the listed events is storm. FSP’s evidence The FSP appointed building fi rm “MB” to inspect the prope rty and report on the cause of the damage. Full details of MB‟s report are contained within section 3.2 of this determination. MB concluded there were no signs of water ingress to the ceiling, with the roof being in good condition, having recently been restored. MB considered the issue with the paintwork was due to a common defect known as „crazing‟ which causes paint to delaminate from the gyprock sheeting. This could be due to the original paint preparation or due to new paint being applied over the old. However, MB did not consider it related to the most recent painting undertaken. Photographs of the property included with MB‟s report do not show any signs of water ingress such as water staining or mould forming. I accept MB is appropriately qualified and experienced to comment in this matter. In the absence of contradictory information, the FSP is entitled to rely on MB‟s findings. Applicant’s evidence In support of his position that the damage arose as a result of an insured event, the applicant has presented evidence showing the roof was restored in January 2017, and the ceilings repainted in June 2017. The applicant has also presented an invoice from October for the replacement of three cracked roof tiles, which had been damaged post restoration. However, no comment as to the cause of the tile breakage has been supplied. Therefore, this does little to assist the applicant in establishing the broken tiles allowed water to enter the ceiling cavity, or that these tiles were broken as a result of an ins ured event. Case No: 519944 Determination Page 3 of 4 It is not known whether the location of the three cracked tiles corresponds with any of the damaged areas of the ceiling. However, as multiple areas of the ceilings are affected, on balance, it is unlikely that the two issues are related. A quotation from “CP” for the replacement of the bedroom ceiling was also supplied, which states the bedroom ceiling was water damaged. Apart from this brief one-line statement, there is nothing in the material to support such an assertion. CP does not comment on the remainder of the ceilings exhibiting peeling paint or speculate what could be the cause. Therefore, this report is of little value when considering this dispute. Further, CP‟s statement is at odds with both the photographic evidence showing no si gns of water ingress, and the tenant‟s denial that water has entered the residence. The applicant was invited to supply his own report from a suitably qualified person, such as a painter or builder as to the cause of the paint damage. However, he has not done so. Accordingly, there is insufficient evidence to support the applicant‟s assertions and the FSP‟s evidence is preferred. Damage not as a result of an insured event In order for the policy to respond, the damage must have arisen from event as defined by the policy. The evidence presented by the parties is not supportive of a finding that the damage arose as a result of a storm event, or any other event which would be covered under the policy. Rather, the damage appears to be the result of a defect with either the original paint or the reapplication of the paintwork in June. The onus to remedy this does not transfer to the FSP simply because it insures the home. Therefore, I do not accept the applicant has established a valid claim for the ceiling in the circumstances. On this basis, the FSP was entitled to decline it. Case No: 519944 Determination Page 4 of 4 3 Supporting information 3.1 FOS approach to this dispute A full exchange of the relevant information has taken place between the respective parties. Each party has had the opportunity of addressing any issues raised. All of the provided material has been reviewed and considered. The parties have raised numerous issues in their submissions to FOS. However, commentary in this determination is restricted only to those issues co nsidered relevant to the outcome. The applicant is represented in this dispute. For the sake of brevity, any references to „the applicant‟ will include material provided by his representative. 3.2 Relevant expert reports Record Key points FSP’s expert ( MB ) Builder‟s Report 2 March 2018  tenant advised over the last month, paint had started to peel off the ceilings in the bedroom and hallway  there was water ingress i n 2017, which had caused damage to the ceilings  the roof was repaired and the ceilings painted  there had been no recent water ingress through the roof  observation showed the paint is crazing  crazing is a common defect where paint delaminates from the gyprock sheeting  this is not from wat er ingress but is normally due to the age of the origin al paint or a new paint application being painted over the original  it was not though t this was caused by previous repairs  inspection of the roof showed it had been resurfac ed and there were no maintenance issues.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.