Text of the determination
Determination | Case number: 519642 Page 1 of 18
Determination
Case number: 519642 8 May 2019
1 Determination overview
1.1 Complaint
The complainant held a Commercial Business Package insurance policy issued by
the financial firm (insurer) to cover a factory premises.
The complainant lodged a claim for two incidents that caused damage to the insured
property. Both related to perpetrators entering the property. These events included
theft of cabling, stripping of the main distribution board and loss of power to the alarm.
The insurer accepted the com plainant’s claim for the result ant property damage
following these events and to the extent it was covered by the policy. This is not in
dispute beyond the complainant seeking to review his decision to withdraw a claim for
$87,700 associated with the first incident.
The insurer also accepted the complainant’s claim for loss of rent . The insurer has
offered to pay $67,728. The complainant seeks loss of rent for 20 months equivalent
to $344,109.90, on the basis that:
the insurer caused delays in settling the claim for property damage
there were delays caused by the electrical supplier and retailer, which were beyond
the complainant’s control
if not for the claimed event, the complainant would have received a higher rental
income for the subject property
the insurer has not correctly calculated the loss of rent benefit under the policy.
1.2 Issues and key findings
Is the complainant entitled to claim for 20 months lost rent?
The complainant is entitled to claim for 20 months lost rent because the information
does not show this timeframe was unreasonable in the context of his circumstances.
Is the insurer liable to increase its offer for loss of rent?
The insurer is liable to increase its offer for loss of rent as the complainant has
established that the delays in restoring power were not his fault. This means the
insurer should settle the claim in the manner set out in section 2.2 of this
determination.
Determination | Case number: 519642 Page 2 of 18
Should the insurer pay anything more towards the first break-in?
The insurer should pay $43,850 because:
this is a 50% contribution towards an invoice associated with the first break -in
this cost was previously submitted to the insurer and considered by it
the insurer had included this amount in full when making an offer to settle the first
break-in in an email dated 27 March 2014
there is no basis to conclude this amount would not be covered under the policy
1.3 Determination
This determination is substantially in favour of the complainant.
The insurer is to settle the claim as outlined in section 2.2 and 2.3 below.
Determination | Case number: 519642 Page 3 of 18
2 Reasons for determination
2.1 Is the complainant entitled to claim for 20 months lost rent?
Circumstances of the claim
The complainant’s commercial property consists of factory premises comprised of a
sheet line shed and a main factory.
The complainant’s tenant (RB) held a lease for both premises. In February 2012, RB
vacated the main factory and moved most of the plant to a new location. RB paid a
reduced rent from that point onwards.
During this time, the complainant was seeking a tenant to lease both premises.
The insured property sustained a break-in between 6 and 9 April 2012, being the
Easter weekend (first break-in). Thieves threw a cable into the mains sub-box in the
sheet line shed, causing a fire and tripping and cutting off the power. The thieves had
then dismantled and stripped cabling over this weekend.
The complainant lodged a claim with the insurer for the first break-in. While he was
dealing with the damage from the first break-in, the premises were broken into a
second time, on 8 June 2012 (second break-in). The thieves broke into the main
factory, stripped out a significant amount of cabling and caused damage to the
property.
Due to the amount of cabling and damage caused, power was interrupted. Significant
works were required to restore power to the premises. This was not completed until
around the second week of December 2013. Further, the complainant says the works
did not reinstate all of the previous power that was available to the premises.
Therefore, the complainant is seeking lost rent of about $344,109.90. This is over a
20-month period.
Complainant says insurer delayed settling the property claim
The damage under the property section of the policy has been accepted and settled
by the insurer. However, the complainant says the insurer and its appointed loss
adjuster (PM) unnecessarily delayed settling the property claim. This affected the loss
of rent component because the property could not be let until the damage was
repaired.
The complainant says any payment for loss of rent should include the following delays
caused by the insurer:
it was unable to decide which cover under the policy was applicable to the subject
claim
Determination | Case number: 519642 Page 4 of 18
it would not assist in the claim when there was an ownership dispute about the
items taken
the insurer first made an offer towards the claim in an email dated 27 March 2014 –
this was almost two years after the first break-in
the delay in financial settlement placed the complainant in financial difficulty and
prolonged the repair process and having the property tenanted.
The insurer says the majority of delays were caused by an ownership dispute
between the complainant and RB about the parts that were taken and damaged.
The insurer also says that its settlement offer of $67,728 is fair and reflects the time it
would have reasonably taken to process the claim, carry out repairs and have new
tenants leasing the property.
Insurer delayed paying settlement monies
The history of the claim is known to the parties. While the parties may disagree on
some aspects of the claim, the panel does not propose to reproduce it in whole, save
where the following comments are relevant to the overall handling of the claim.
The available material shows there was some delay caused by the insurer and PM in
progressing the claims settlement. This is because the available material shows:
PM provided verbal approval (20 June 2012) for the complainant to clean the office
and fix plumbing but did not authorise repairs to the power cabling
the insurer initially considered the claim under Accidental Damage (Theft
component of Accidental Damage) and not malicious damage.
Between February 2013 and August 2013, the parties disagreed about whether the
main factory was considered occupied for the purposes of the policy (and therefore
whether the loss was excluded). PM confirmed the complainant could proceed with
repairs proposed by SE but raised concerns about ownership of a number of items
(whether owned by the complainant or RB).
The insurer initially agreed to limit its liability to damaged doors, cleaning offices and
repairs to copper fence and pipe. It said however, these costs were under the
$20,000 policy excess.
In August 2013, following advice from the complainant’s solicitor about a variation of
lease agreement in place with RB, the insurer accepted a theft claim within the terms
of the policy.
Between September 2013 and March 2014, the parties disagreed on the nature of
damage at the property, what excesses applied to which cover, and the scope and
quantum of repairs.
Determination | Case number: 519642 Page 5 of 18
On 8 May 2014, the insurer sent a cheque for $98,451.80 to the complainant. The
complainant returned the cheque as it was for the wrong amount, and requested a
cheque for the correct amount.
On 25 June 2014, the complainant banked a cheque received from the insurer for
$108,319.96. This was associated with the second break -in. This was the first amount
the insurer contributed to the complainant’s claim, being more than two years after the
second break-in.
Owing to an ongoing dispute about RB claiming ownership of the claimed items, the
first break-in was not settled until 17 June 2016. This is more tha n four years after the
event. The amount paid was $90,400.
Given the substantial amount payable under the policy and the delay in forwarding
this, the panel accepts this would have significantly impacted the complainant’s ability
to reinstate the extensive loss. This includes the fact it appears the amount of works
paid for were not a complete reinstatement due to limited funds.
Insurer’s failure to assist in the ownership dispute contributed to the delay
The insurer says the ownership dispute significantly contributed to the delay in settling
the claim.
However, there is no dispute the evidence shows the complainant was the legal
owner of the items claimed. Further, the information shows the insurer offered little to
no assistance to resolve this issue despite:
the complainant providing numerous documents to support his position
the insurer being on notice the complainant was intending to claim for the items
the information now showing the insurer had a liability to respond but failing to
identify this until after the complainant was left to resolve the issue with RB
In such a context, the panel considers the insurer’s decision in this regard has
substantially contributed to the issues surrounding the loss of rent claim. This is
because the insurer had an obligation to investigate and assess its liability after the
claim was lodged.
Despite this, and the fact the complainant did attempt to substantiate his position, the
insurer elected to leave it to the complainant to sort out the ownership issue with RB
and offered no assistance. The panel does not accept this was reasonable and would
have contributed to the delay in restoring power to the premises.
Insufficient evidence to support third break-in caused delay
The insurer believes there was a third break-in which required the substation to be
replaced. This led to further delays in the power being reconnected.
Determination | Case number: 519642 Page 6 of 18
The insurer relies on a note logged by the electricity supplier (JM) in August 2013
about this third break-in. The insurer says this was outside the period of cover. The
insurer has not provided confirmation that insurance cover was refused, and the
complainant was left effectively uninsured during this period.
Further, the panel is not satisfied that there is sufficient information to support a third
break-in. This is because:
JM has been slow to respond to the complainant and the insurer – it is possible its
note was logged late and was actually in relation to the earlier claim lodged by the
complainant
the complainant has provided information to show the security systems were
updated by that time and included a daily patrol - information from the security
provider confirmed there was no evidence of another break -in to the property
there is no police report or other information to support a third break-in
Whilst SE also confirmed there was a third break-in which resulted in the theft of
cabling and conducive elements located in the secondary side of the substation, it is
not clear if this was based on his observation or JM’s investigation.
In addition, the complainant has consistently said that around February 2013, JM had
advised the parts to repair the substation was obsolete and that it required
replacement. This is consistent with contemporaneous emails showing that JM was to
attend the site at th at time. This contradicts the insurer’s position that the substation
was replaced due to a third break-in.
Given all this, the panel accepts the information shows the electrical substation likely
required replacement due to the second break-in. This also contributed to the delay
and was outside the complainant’s control.
Information shows complainant attempted to reinstate power quickly
The insurer based its lost rent offer to the complainant on its understanding of how
long it should have reasonably taken the complainant to reinstate power and rent out
the premises.
This is based on PM’s report dated 4 October 2016. PM refers to advice received
from a consultant (PI) that said the repairs could have been completed in about three
months.
Nothing was provided by PM directly to confirm this timeframe. Neither is it clear if PM
considered the specific characteristics of the insured property.
The insurer further says the complainant caused delays by exploring other options,
such as taking considerable time in exploring whether to abandon the sheet line
substation and use the substation located on another road.
Determination | Case number: 519642 Page 7 of 18
The complainant says he explored what he thought would be a faster option to get
power reinstated by using a different substation. However, this was not possible.
This is supported by information which shows that even before liability for the first
break-in was confirmed, PM said he was aware the complainant was arranging
temporary power to be supplied to the main factory.
The panel notes RB was still claiming ownership of the sheet line items at this time.
The insurer had yet to confirm liability or the amount of settlement.
This inevitably impacted the complainant as the costs involved were significant and
he was effectively left uninsured during this process.
Although the insurer initially said the complainant caused delays by not replacing like
for like and was looking at an ‘upgrade’, it later retracted the upgrade statement
during the course of the dispute at AFCA. The complainant also provided evidence to
show that the reinstatement works were below the level previously available to the
premises due to the costs involved. Therefore, it is clear they were not an upgrade.
The available material also shows that the complainant was in discussion with real
estate agents and potential tenants at this time in relation to renting out the premises.
Given all this, the panel is satisfied the complainant explored options to reinstate the
power to the main factory as soon as possible so that he could let the property. The
information also shows the complainant explored options to mitigate his loss.
Available material shows electrical supplier and retailer contributed to delay
The available information shows the complainant experienced significant delays from
JM and the electricity retailer in reinstating e lectrical supply to the factory.
The complainant has provided a copy of a letter from a Member of Parliament (MP)
dated 20 March 2015. The MP’s letter confirms the complainant requested his
assistance due to delays experienced with JM, in reconnecting the electrical supply in
the factory following theft and disturbance. The letter also says that JM only restored
power after the MP intervened on the complainant’s behalf.
The information also shows the insurer had difficulty contacting JM and obtaining any
response. The complainant says the fact that the insurer also experienced delays
from JM in terms of a response supports his position.
For the reasons above, and having carefully reviewed the information provided by the
parties, the panel is satisfied there were delays caused by the electrical supplier and
retailer. This resulted in more time being spent restoring power to the main factory.
The panel accepts this impacte d the complainant’s rental income and was outside his
control.
Determination | Case number: 519642 Page 8 of 18
Conclusions
Given the above, the panel is satisfied the evidence shows the 20 months being
claimed by the complainant is not unreasonable.
Instead, the available information shows that due to circumstances outside his
control, this timeframe was reasonable. These circumstances include:
the insurer’s failure to provide financial assistance despite the policy responding to
the property damage
issues with the electricity supplier and retailer
the complainant’s attempts to restore power under these challenging
circumstances
dealing with an ownership dispute with RB where RB’s position was not
substantiated
Therefore, the complainant is entitled to 20 months loss of rent.
2.2 What is the extent of the insurer’s liability for loss of rent?
No lease agreement in place with prospective tenant
The complainant says he was negotiati ng with a prospective tenant (NR) to lease the
premises when the loss occurred. The complainant has provided information to show
he had discussions with NR from January 2012 which indicate:
NR was considering paying at least $13,000 per month in rent
NR was ready to come to an agreement with the complainant (as per email dated
23 April 2012 where NR says it should come to an agreement within two weeks)
The complainant says the negotiations with NR ended after the second break-in,
when it was apparent that there was no definite timeframe for when the power would
be reinstated to the factory.
The panel acknowledges that the available information supports the complainant’s
submission that NR was a prospective tenant serious about leasing the property.
However, the parties agree that the complainant’s claim for loss of rent falls under the
‘Insurable gross profit basis’, particularly ‘Rent Receivable’. This says the amount
payable will be the difference between the ‘Standard Rent Receivable’ to the ‘Rent
Receivable during the Indemnity Period’. The ‘Indemnity Period’ begins from the
occurrence of damage and expires at the end of the period, being 24 months.
‘Standard Rent Receivable’ is defined to mean:
… the Rent Receivable during that period in the twelve months
immediately before the date of the Damage which corresponds within the
Indemnity Period*
Determination | Case number: 519642 Page 9 of 18
The ‘*’ contains the following note:
to which such adjustments will be made as may be necessary to provide for the
trend of Your Business and for variations in or other circumstances affecting Your
Business either before or after the Damage or which would have affected Your
Business had the Damage not occurred, so that the adjusted figures will represent
as nearly as may be reasonably practicable the results which, but for the
Damage, would have been obtained during the relative period after the Damage.
There was no lease agreement in place with NR, or any rent received by them prior to
the first break-in. Therefore, the panel is satisfied the insurer is not liable to include
potential rent from a prospective tenant when calculating the loss of rent payable.
Insurer has not correctly settled loss of rent claim
The insurer offered $67,728 for loss of rent. The basis for its calculations is set out in
section 3.4 below. This covered a 12-month period.
The panel accepts the complainant is entitled to a 20-month period for reasons
expressed above. Therefore, the period to be allowed by the insurer must be
extended by eight months.
The insurer’s calculations appear to be based on the rental received after the power
was restored. This is inconsistent with the policy.
The relevant benefit is the difference between the ‘Standard Rent Receivable’ and the
‘Rent Receivable’ during the ‘Indemnity Period’. The ‘Standard Rent Receivable’ is
based on the ‘Rent Receivable’ during the 12 months immediately before the
damage, not after.
The complainant’s calculations, set out in section 3.5, sets out the rent payable
(excluding outgoings and GST) in the 12 months preceding the first break-in. There is
no dispute those figures are correct. The annual figure is $157,390.
Over 20 months, this figure is $262,316.67.
Outgoings should be included
The complainant notes ‘Rental Receivable’ includes ‘contributions to outgoings’. In
support, he has provided the outgoings that were paid by the tenant between 2010-
2013.
The insurer has questioned whether all of the amounts were charged as outgoings.
For instance, there were a number of months that the security costs were not paid.
The complainant’s position is supported by the ledger and invoices issued to RB. It is
also consistent with the lease issued to one of the tenants after the power was
restored. It is also consistent with the standardised commercial lease wording
provided by the state legal association. That standardised wording says the tenant is
Determination | Case number: 519642 Page 10 of 18
to contribute to outgoings. Outgoings include rates, land taxes, insurance policies and
other similar type costs.
There is also a letter from the real estate agent confirming all the leases the
complainant had, included this arrangement.
Therefore, the panel accepts the outgoings were payable by the tenant and should be
included in the insurer’s settlement.
How the claim should be settled
As stated previously, the amount payable under the relevant benefit is the difference
between the ‘Standard Rent Receivable’ and the ‘Rent Receivable’ over the relevant
period.
According to the complainant’s ledger, rent and outgoings were still being paid after
the event. For the period between April 2012 and April 2013, monthly rent of $1,820
was payable as well as insurance costs.
It is clear these need to be accounted for in any settlement.
Further, it is not clear to what extent outgoings were payable by the complainant
during the 20-month period that would have otherwise been charged to a tenant.
Accordingly, the panel accepts it is fair in all the circumstances that the loss of rent
claim should be settled in the following way:
the loss of rent duration is to be 20 months (between April 2012 and December
2013)
the rent to be applied (excluding outgoings) is $262,316.67
the insurer is to include any outgoings paid by the complainant during this 20-
month period that would have been payable by the tenant – this would include
insurance, land tax, rates, water, security
the insurer is entitled to deduct any rent received from the complainant during this
period
Therefore, if the complainant accepts this decision, he must clarify (with documents in
support):
what outgoings were paid for during this period that would have otherwise been
payable by the tenant
account for the total amount for rent he received between April 2012 and
December 2013.
Once this is done, the insurer will be in a position to calculate the total amount
payable. The insurer will also be required to pay interest on the payable amount
pursuant to section 57 of the Insurance Contracts Acts 1984 (the Act). Interest is
Determination | Case number: 519642 Page 11 of 18
payable from 31 December 2013, being the date the complainant had incurred the
lost rent, until payment is issued.
2.3 Should the insurer pay anything more towards the first break-in?
Insurer to settle complainant’s claim for damage caused by first break-in
The second break-in to the property occurred a short time after the first. The first
claim for damage had therefore yet to be settled, when the second break-in occurred.
The complainant says he withdrew an amount associated with the first break-in on the
advice of PM that doing so would expedite the settlement of the claims. The amount
withdrawn was based on SE’s quote dated 27 November 2012 totalling $87,700.
The available information shows this amount was considered by the insurer at one
point. PM’s email to the complainant dated 27 March 2014 had included this cost at a
50% reduction. The reduction was offered by the complainant. Following this, PM had
offered $131,272.73 towards the first claim. PM allowed this reduced amount in full.
This was not followed through with and the insurer ultimately settled the first claim for
$90,400 net of GST and excess. It is not clear from the insurer’s perspective why this
second quote was not included in the settlement.
There is no written advice confirming the complainant’s position that the insurer or its
representative asked the complainant to withdraw the first claim. However, the above
information shows this aspect of claim was included and then withdrawn from the
insurer’s settl ement for the first claim and the reasons for this are unclear.
While the complainant withdrew this aspect of the first claim, he now says that as it
took so long for the insurer to settle the second claim, he would now like this amount
to be paid.
During the dispute, the insurer submitted to AFCA that if the complainant wishes to
make a claim for the first break-in, its claims department can address this. However,
the insurer has not acknowledged the fact this invoice was submitted and considered
by it, when PM made the offer dated 27 March 2014.
The complainant, in recent correspondence to AFCA, says he will again accept
$43,850 in respect of this.
Given the above, particularly the fact the insurer’s earlier settlement offer allowed this
reduction in full, the panel considers it is fair in all the circumstances the insurer pays
$43,850 in settlement of that invoice.
Determination | Case number: 519642 Page 12 of 18
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
3.2 Relevant policy provisions
Section Relevant wording
Busine ss interruption cover
section
Definitions
Page 17
“Annual Rent Receivable” means the Rent Receivable during the
twelve mont hs immediat ely before the dat e of the Damage.
“Rent Receivable” the amount of the rent received or receivable
(including base rental, Turnover rental and contributions to outgoings)
from the letting of property at the Business Premises.
“Revenue” means the Money paid or payable to You as a:
…
(c) Property owner – by t enants (being Rent Receivable).
“Standard Rent Receivable” means the Rent Receivable during that
period in the twelve months immediately before the date of the Damage
which corresponds with the Indemnity Period.
“Standard Revenue” means the Revenue earned within that period
during the twelve months immediat ely before the date of the Damage
which corresponds with the Indemnity Period.
Busine ss interruption cover
section
Cover
Page 20
5. Rent Receivable
This item is limited to loss of Rent Rec eivable and additional expenditure.
The amount payable will be:
(a) in respect of loss of Rent Receivable, the amount by which the
Rent Receivable during the Indemnity Period falls short of the
Standard Rent Receivable, in consequence of the Damage, and
(b) in respect of addi tional expenditure, the additional expenditure
necessarily and reasonably incurred for the sole purpose of
Determination | Case number: 519642 Page 13 of 18
Section Relevant wording
avoiding or diminishing the loss of Rent Receivable which, but for
that expenditure, would have taken plac e during the Indemnity
Period in consequenc e of the Damage, but not exceeding the
amount of the reduction in Rent Receivable thereby avoided,
less any sum saved during the Indemnity Period in respect of such of the
expenses and charges payable out of the Rent Receivable as may cease
or be reduced i n consequence of the Damage.
Provided that if the sum insured for this item is less than eighty percent
(80% ) of the Annual Rent Receivable (or its proportionately increased
multiple where the Indemnity Period exceeds twelve months), the amount
payable wil l be reduced so that We will be liable for no greater proportion
of the loss under this item than that which the sum insured bears to eighty
percent (80% ) of the Annual Rent Receivable (or its proportionately
increased multiple, if appropriate).
This provi sion will not apply if Your claim is for less than 10% of the sum
insured for this item.
3.3 Supporting information
Record Key information
Complainant’s expert (SE )
Electrical contractor’s letter
27 - 11 - 2013
First break - in:
Thieves broke into the smaller building that housed the main
switchboard and met ering facilities and deliberately and maliciously
short circuited the busbars so that the power supply to the building
would disconnect.
With power to the building isolated, the thieves stripped out the busb ars
within the switchboard cabinets, the mains cables exiting from
underground into the cabinets and the majority of the circuit and
machinery wiring that ran from the cabinets, together with sub mains
cables before they entered the ground to provide power into the other
larger building.
The thieves had also started stripping some heavy cabling associated
with the switchboards located in the larger building.
On this occasion, the electrical distribution company restored power to
the high voltage side of the trans former in the electrical sub - station
located within the grounds and isolated the low voltage terminals
following a standard safety procedure.
Second break - in
There was a further break - in to the larger building while the situation
was under Police in vestigation
There was further malicious damage that destroy ed the large
controlling switchboard and deliberate stripping out of large diameter
cables feeding the various switchboards in the building.
Determination | Case number: 519642 Page 14 of 18
Record Key information
Complainant’s expert (SE)
Correspondence to
complainant
0 5 - 0 3 - 2014
SE (KS) to complainant:
Originally quoted for work earlier in 2012
Received confirmation to proceed in November 2012
Commenced actual work on site in late January 2013
Whilst working on the project, we found the replacement of the sub -
station, connection of power, and electrical checks and approvals led to
a prolonged frustrating period with the electrical retailers who seemed
incapable of understanding what was glaringly obvious to everyone
else.
Works were finally signed off and the premises e nergised in the second
week of Dec 13 with SEC awaiting instructions to power up the main
factory. The former sheet line building is powered up.
Property manager (RR)
Leasing & Managing
authority
01 - 07 - 2016
Lessee’s outgoings are listed:
> Council rates
> Building insurance
> Water rates
> Glass insurance
> Land tax (if permitted by law)
> Public liability insurance
> Building operating expenses
Complainant’s expert (SE)
Electrician (KS) letter
16 - 08 - 2016
Attended site following first break - in in April 2012 and rec tification quote
provided in May 2012.
Second break - in to the main factory in June 2012 and prepared a
quotation.
There were delays due to complications of ownership and ins ured
interest of plastics processing machinery in the same building that was
first damaged.
KS prepared a quote for repair of circuit and control wiring for the
machinery but understands the decision was then made to write off the
equipment.
Early 2013 - the insured requested works proceed wit h re - establishing
the main electrical supply to the factory.
18 March 2013 - KS supplied electrical works request form for
connection and replacement of consumers mains and associated works
to the existing sub - station.
The power company (JM) investigated and found the substation
needed to be replaced as the existing type was redundant.
There was significant contact with JM and the power company (EA)
during this period as the situation was now treated as a new electricity
connection.
There were additional delays with the electricity retailer (EA).
4 October 2013 – the delivery and installation of the new substation
was complet ed.
It appears there were further delays with EA as KS has a copy of
further electrical works request dated 30 October 2013. KS presumes
that this form was to start the process for the actual metering
Determination | Case number: 519642 Page 15 of 18
Record Key information
installation to occur.
Complainant’s expert (JM)
Electricity Supplier
18 - 08 - 2016
JM provided background information to the complainant in relation to
the lifecycle/timeframes in replacing the substation:
The initial vandalism of the switchboard was logged in the JM dat abase
in April 2012.
The JM substation was not damaged in the incident.
There was a second break - in in June 2012 before the reinstatement of
the supply.
This time there was damage to the JM owned kiosk substation.
Pr ior to completion, there was a third break - in logged in the JM
database in August 2013, where there was extensive damage to the
JM owned kiosk substation.
JM made the decision to replace it with a larger unit based on the
increased net work load.
JM replace d the unit in October 2013.
Generally, this kind of maintenance or replacement can be conducted
on the same day as the fault, if supply is interrupted and required to be
reinstated. Key driver is network integrity.
Re: timeframes for a new connection reque st – handled by customer
projects team led by JH. Jobs are negotiated with customer and
provided as a service, so the drivers are different – anecdotally JH has
advis ed timeframes for a substation are generally 2 - 3 months. Can vary
on case by case basis d epending on negotiation & acceptance of an
offer, network outage limitations and the JM staff field capacity.
Complainant’s expert (RR)
Property manager (RR)
Correspondence
0 6 - 0 7 - 20 18
Confirms RR acting for complainant’s property since May 2015
Lease agr eements for the relevant properties required that the tenants
are responsible for the following outgoings as a minimum:
> Council rates
> Land tax (single holding basis)
> FES – fire equipment
> Insuranc e
> Alarms
> Alarm monit oring
> Patrols
> Phone line alarm
> Electricity
> Water rates and usage
Insurer’s expert (CL, PM)
Assessment report
04 - 10 - 2016
Material Damage :
First break - in on 16 April 2012 :
The insured’s claim for damage sustained as a result of the first break -
in has been settled at $110,400 (ex GST).
It is apparent the ins ured elected not to reinstate like for like.
We have received an invoic e to substantiate they have incurred costs
totalling $125,370 to reconnect power to the site.
Settlement of this aspect of the claim was delayed due to a dispute
o ver ownership of the subject matter between the landlord and the
Determination | Case number: 519642 Page 16 of 18
Record Key information
tenant.
Second break - in on 8 June 2012
The insured’s claim for damage sustained as a result of the second
break - in was settled at $108,319.96 (ex GST).
Payment in settlement of this aspect o f claim was released based on
the quotations on file, after the Tenant confirmed in writing that the
subject matter of the claim was owned the Landlord.
Loss of rent:
In the months leading up to the first break - in, the tenant (RB) was in the
process of co nsolidating their business and had vacated the Main
Factory, reducing their rent to $3,000 for the Sheet Line Factory only.
Complainant advised that immediately before the first break - in, they
were in negotiation with a prospective new tenant interested in letting
the whole site (Main Factory & Sheet Line Factory ) for approximately
$13,000, which was later to be raised to $15,750, but no agreement
was ever signed.
Insurer’s electrical consultant said a like for like repair should take no
longer than three m onths.
Documents show that after the power was reconnected in late 2013 (20
months after the first break - in), the Sheet Line Factory was rented to a
new tenant (MT) for $3,150 per month.
Documents show two further tenants subsequently moved into the main
f actory after the 24 - month indemnity period had ex pired.
The following key events significantly protracted the period of
interruption:
> decision not to reinstate like for like
> delays in authorising contractor
> third break - in
Based on the identified timeline, CL rec ommends the insurer’s liability
for loss of rent is based on an interruption period of six months (25
weeks) which it believes related directly from the two break - ins which
were covered by the policy and allows for:
> Three months (13 weeks) to ascert ain the scope of works
> Obtain quotations for the first two break - ins
> Undertak e the works on a like for like basis (base d on a three month
or 12 - week program per advice from PB).
FSP may wish to consider a further two months (9 weeks) for delays
experienced by the contractor to obtain parts over the festive period.
Quantum:
Rent the complainant would have received ‘but for’ the event
Shortly before the first break - in, the tenant (RB) was in the process of
consolidating its business and had vacated the Main F actory reducing
their rent to $3,000 for the Sheet Line Factory only.
Complainant advised that shortly before the loss he was in negotiations
with a prospective new tenant interested in leasing the whole site for
approximately $13,000 per month, later to b e increased to $15,750, but
Determination | Case number: 519642 Page 17 of 18
Record Key information
no agreement was ever signed.
Documents show power was reconnected to the site in late
November/early December 2013.
The complainant was therefore able to re - let the Sheet Line factory
immediat ely for $3,125 per month.
The Main Factory took a further six months (26 weeks) to rent the rear
section and a further two years for a tenant for the front section.
Documents show:
Tenant Building/area Amount
per month
Date
MT Sheet line factory $3,125 Dec 2013
AW Rear of main
factory
$5.038.00 Jun 2014
MF Front of main
factory
$6,250 Aug 2016
Recommendation :
Based on the information provided, assuming the Sheet Line substation
could be repaired by JM, CL calculates the insurer’s liability could
range from $18, 750 to $35,076. Should the complainant prove the
substation was irreparable as a result of the second break - in, the FSP’s
liability could increase to $67,728.
3.4 Insurer’s proposed loss of rent settlement
Stage Period Insurer’s liability
per month
Comment
Scope of works, obtain
quotes & engage
contractor
3 months $9,375 Based on $3,125 per month
Delay in commencing
works over festive
period
2 months $6,250 Based on $3,125 per month
Undertak e works 3 months $3,125 + $16,326 First six months at $3,125.
Thereafter rent for entire site at
$8,163 (based on sheet line and
rear of main factory being leased
per current rent )
Determination | Case number: 519642 Page 18 of 18
Stage Period Insurer’s liability
per month
Comment
Sub - total $35,076
Replace substation 4 months $32,652 Based on $8,163 per month for
sheet line factory and rear of
main factory being leased as per
current rent.
Total $67,728
3.5 Complainant’s 12 month calculated loss of rent
Rental period Monthly rent Total
March 2011 – August 2011 $15,000 $75,000
September 2012 – January 2012 $15,750 $78,750
February 2012 – March 2012 $1,820 $3,640
Total $157,390