Home / Financial Firm (Unknown - Insurer) / Determination 518987

Determination 518987

Settlement of water damage claim after defective and damaging repairs by insurer's repairer

FirmFinancial Firm (Unknown - Insurer)
Decided2018-11-01
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$63,749
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The insurer accepted a water damage claim, but its repairer did defective painting work, caused further damage and was alleged to have behaved aggressively. AFCA largely accepted the insurer's cash settlement, increased it by about $11,382 for further costs and temporary accommodation, ordered $3,000 for distress, and ordered statutory interest.

The insurer is responsible for its repairer's defective work and the damage it caused, so the claim must restore the complainant to her pre-repair position, subject to a reasonable assessment of the quotes.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 518987 Determination Page 1 of 11 Case number: 518987 11 October 2018 1 Overview 1.1 Dispute The applicant lodged a claim with the financial services provider (FSP) for water damage to her property. The FSP accepted the claim and organised its repairer to attend the property and carry out repairs. The applicant was unhappy with the repairs and sa ys:  the repairs were not completed to a satisfactory standard and in some instances not completed at all  the repairer was abusive and threatening towards her, making her feel unsafe in her own home, and  the repairer caused additional damage to some of her property and contents. The FSP has offered to cash settle the applicant $52,367.70 (inclusive of GST) plus $3,000 in non- financial loss compensation. The applicant says the FSP’s offer of settlement does not adequately cover the damage caused by its repairer or the stress she has gone through. 1.2 Issues and key findings Is the applicant entitled to further compensation for the damage? The FSP is to compensate the applicant by a further sum of $11,381.70, making a total of $63,749.40 (inclusive of GST). This is to account for the reasonable cost the applicant will incur for her temporary accommodation ($4,186), additional removalist costs ($1,400), a 10% margin ($4,761) for the transference of risk to the applicant for loss of the FSP’s warranty in respect to rectification works, and additional GST. Is the applicant entitled to further non-financial loss compensation? The applicant is entitled to a total of $3,000 for her stress and suffering and the way she was treated by the repairer. 1.3 Determination This determination is substantially in favour of the applicant. The FSP is to pay the applicant a total of $66,749.40 together with statutory interest from 3 May 2018 on $52,367.70 in accordance with section 57 of the Insurance Contracts Act 1984 (the Act). Case No: 518987 Determination Page 2 of 11 2 Reasons for determination 2.1 Is the applicant entitled to further compensation for the damage? Not in dispute repairs were not to standard and additional damage caused It is not in dispute the applicant had a valid claim for water damage in March 2017. The FSP authorised repairs to the applicant’s first floor rumpus room, spare room and office. When the applicant informed the FSP that repairs were not to standard, the FSP had the original building consultant assess the repairs. Further issues arose with that building consultant so the FSP subsequently appointed an independent building consultant (SG). SG prepared a comprehensive scope of works, an audit report and repair report of 3 May 2018. SG identified many areas of the applicant’s property that had been damaged by paint splatters as well as overpainting. SG stated the repairer’s work represented defective work in accordance with the relevant state’s Guideline to Stan dards and Tolerances. SG also confirmed some of the repairs originally required had not been carried out at all. SG’s scope of works stated the following was required as a result of defective repair work caused by the FSP’s repairer:  contents of the affected area will require removal and storage  entire rumpus room, spare room, office and stairwell will need to be repainted  carpets to the entire house require replacement in order to be consistent throughout  paving and tiles to the front entry require c leaning  front entry metal door will require cleaning or re-surfacing  light fitting and air-conditioning outlets will require cleaning  metal balustrade in the stairwell will require cleaning  cedar shutters and blinds will require cleaning and re-finishing  timber furniture will require cleaning and re-finishing  affected household ornaments will require cleaning. The FSP accepted SG’s report and rectification quotation. In addition, the FSP has accepted temporary accommodation will be required but has advised it will only be paid once the cost is incurred by the applicant. The applicant says the FSP’s offer of settlement does not cover the damage Due to SG’s report the FSP has offered the applicant $52,367.70 which is based on SG’s scope of works and itemised quote for the rectification work needed. This quotation totalled $52,367.70 made up of $39,426.00 for construction cost including demolition, a builder’s margin of $5,914.00 (15%), a contingency allowance of $2,267.00 (5%) and GST of $4,760.70. In simple t erms, the FSP has offered to remove and replace the applicant’s paint damaged carpets, clean all areas of paint spills including shutters, carry out a Case No: 518987 Determination Page 3 of 11 professional clean and repaint the job that was originally done. It also has offered temporary accommodation and removalist costs. It has also offered $3,000 in non- financial compensation. The applicant did not accept the offer of settlement from the FSP. The applicant wants additional rectification and replacement work to be done. Specifically, the applicant does not accept SG’s quoted cost for the painting, carpet and the restoration of the shutters. The applicant also says:  her antique light and other contents items were damaged  she needs to be cash settled for the temporary accommodation required when repairs are carried out, and  she will require $4,000 for removals and storage based on previous experience moving her contents. The applicant says the FSP needs to consider the loss its own repairer caused her, her stress and suffering as a result, and the difficulty she will have in organising repairs herself at a costlier price than what the FSP’s repairer has quoted. The Panel is aware that there can be differing opinions on what is required to rectify damage to property. The Panel is, however, satisfied th at the FSP’s offer based on SG’s report is generally fair and reasonable. Despite this, the Panel notes the applicant’s concerns about her organising the repairs. The Panel directs that an additional allowance of $4,761 be paid, being 10% of the original costs of $47,607, because this claim is being cash settled. This compensates her for the fact that she will be arranging the rectification work herself and she will not have the benefit of any FSP warranty on the repairs. The applicant has provided two quotes for re-painting within the same range There is a dispute about painting costs. The applicant has provided two of her own quotes for the rectification of the internal painting. One quote is for $11,000 and the other is for $10,500. SG’s quote for pai nting works was $5,503.13. However, $1,293.12 of the quoted painting cost involved the re-painting of damaged shutters. Therefore, SG’s total quote for the painting rectification works required to the water damaged interior was $4,210.01. When asked about the difference in quotes, SG reviewed the applicant’s quote for $11,000 and said it is “deemed slightly excessive”. SG also said the applicant’s quote allowed for a cornice replacement which SG’s scope did not, and the applicant’s quote did not itemise the protection of the works. SG says it quoted for this separately. The applicant’s second quote for $10,500 did not state that it included a cornice replacement. However, both the applicant’s quotes are within the same range. The FSP is not liable for any further painting work Neither of the applicant’s two quotes itemise protection of works and it is therefore reasonable to assume that the cost of such is accounted for in the total. SG’s itemised quote shows it allowed $1,931.50 for the protection and coveri ng of works during rectification. Therefore, SG’s total amount quoted for painting was $6,141.51. Case No: 518987 Determination Page 4 of 11 Despite the difference in the quotations, the Panel is satisfied that SG’s allowance for these painting costs was detailed and reasonable. The FSP is not liable for any further costs for painting. The FSP is liable for further removal and storage costs SG has allowed $1,300 for the removal and storage of the applicant’s items during rectification work of the first floor area of the applicant’s home. SG’s quote allowed for two labourers at $50 an hour over four hours and for two movements. SG allowed $500 for storage. The applicant has provided her own quote for the dismantling and reassembly of her bedroom suite as well as items in the lounge room, dining room and office. The a pplicant’s quote is for $2,700 with $1,350 payable upon completion of dismantle and the first move, and the remainder payable upon completion of the move back and reassemble. SG’s scope of works and quote does not indicate what is to be removed and dismantled or where it is to be stored. As outlined above, it is fair in all the circumstances that the applicant is compensated for the reasonable cost for her to organise the rectification work herself. This includes the cost of the preliminaries. While the applicant says the last time she had a removalist move her bedroom suite it cost her $4,000, there is no information to support this. The Panel is satisfied the FSP is liable for the difference in quotes for the removal and storage, being $1,400. The applicant wants all her shutters replaced to match throughout The replacement of the shutters in the applicant’s home is a major issue in contention. It is not in dispute the applicant’s shutters were damaged during the FSP’s initial repair w ork. SG has provided a photograph of one of the shutters with paint splatters on it as an example of the damage that has occurred to a number of other shutters. SG’s scope of works and quote allows $1,293.12 for re-painting of the damaged shutters and $910 for the removal and reinstallation of the shutters. The applicant says she does not accept the shutters can be repaired to how they were prior to the damage caused by the painter. The applicant says the cedar type of her original shutters is no longer available in Australia, and even if the shutters are re-painted they will not match throughout the house. The FSP’s liability for the shutters is not limited by the terms of the policy The damage to the shutters was not caused by the insured event that gave rise to the water damage claim. There was no known water damage to the shutters at all. The damage was caused solely by the FSP’s repairer during the course of repairs. This means, in this instance, any terms of the policy which limit liability do not apply. It is not a question of repairing only the damaged items due to obligations under the Case No: 518987 Determination Page 5 of 11 policy. It is a matter of returning the applicant to the position she was in prior to the repairer’s error. The applicant has provided a quote for replacement and restoration of shutters The applicant has provided a quote of $66,000 for the replacement of all shutters. The quote says: “Note: This is Australian Cedar. The colour does not match existing colour in the house.” The applicant has also provided a copy of a n appraisal on her property from a real estate agent which states: “It was unfortunate to discover within your home that the plantation shutters, wall paint and carpet are damaged. Buyers seeking to purchase within the […] estate are particular, detail orientated and accustomed to blue chip homes. We feel they would be concerned and unhappy with the current state of your plantation shutters, damaged carpet and amateur paint work. These areas of concern will affect your overall sale price. We would strongly recommend you repair the areas of concern mentioned above to keep the image and quality of the house.” Despite the recommendation to repair the damage, it is on this basis the applicant says the FSP should cover the cost of replacing all shutters so they match throughout. However, the applicant has also provided a quote for the restoration of all shutters, should they not be replaced, to ensure the paint splatters are fixed and the shutters still match throughout. The applicant’s quote f or restoration of all shutters was for $38,500, which appears to be an excessive figure. While the actual loss in the value of the home is only speculative until the applicant sells the home, it is fair in all the circumstances that the FSP returns the applicant to the position she was in prior to its repairer’s error. The quality or value of the item damaged should not influence the FSP’s liability. The FSP is not liable for the restoration of all the cedar shutters While it is accepted the same finish is no longer available in Australia, there is no information to show the available restoration method, as quoted by SG, would result in an inferior shutter to what is currently in the home. The Panel finds the FSP is not further liable to pay more than its previously accepted rectification cost of the shutters. The FSP is not liable for the bathroom shutters The applicant also says SG did not take into account her bathroom shutters, which were different to the cedar shutters quoted for replacement and restoration. The applicant says these shutters were also damaged by the same repairer. The applicant’s quote for bathroom shutters comes to $3,300. There is, however, no report to support a payment for damage to the bathroom shutters. Case No: 518987 Determination Page 6 of 11 The FSP was asked to respond on whether it was aware of damage to the bathroom shutters. The FSP referred this request to SG, who advised the only damage noticed, and which the applicant pointed out in the bathroom, was paint splatters on the tiled floor. In this instance, the Panel is not satisfied the FSP is liable for the rectification work on the bathroom shutters. The FSP is not required to increase its settlement for replacement of the carpet The FSP has accepted the replacement cost of the carpet throughout the house. SG’s s cope of works and quote allows $1,099.92 for the labour and removal of all existing carpet and $17,025.50 for carpet laying, a total of $18,125.42. SG has confirmed that the cost of the carpet was based on an 80/20% wool/nylon blend with underlay in line with standard rates. The applicant says her carpet cost approximately $35,000 when she purchased it but has provided a quote for $26,400 for replacement. The applicant’s quote includes removal, disposal and installation, as has the FSP. However, it also allows for furniture removal, which the FSP has accounted for separately. If the cost of the removalist and storage, already provided for above being $2,700, is added to the FSP’s quote for carpet replacement, it comes to $20,825.42. Therefore, the overall difference in quotes is $5,574.58. This approximates 25% of the FSP’s overall quote for carpet replacement. However, the Panel is satisfied that SG’s quotation is not an unreasonable allowance, particularly when taking into account the quotation contingency allowance and the additional 10% the Panel has allowed for the contingencies the applicant may face in organising the rectification work herself. The FSP is liable for temporary accommodation costs The FSP has also accepted two weeks of temporary accommodation costs. When asked to provide a value of temporary accommodation costs that will be accepted, the FSP says it relies on the product disclosure statement (PDS) which says temporary accommodation costs will only be paid if actually incurred. However, as mentioned above, the terms of the policy do not apply to the damage caused by the repairer. If the FSP wishes to cash settle the applicant for the rectification work, it is to cash settle the temporary accommodation costs as well. The applicant has provided a quote for temporary accommodation at a place close to her home. The average room rate at the nominated accommodation is $299 a night. This is for an apartment with one queen sized bed. The applicant has a son who would be required to stay there too and therefore the Panel does not think this quote is unreasonable. The FSP is liable for 14 nights accommodation at $299 a night. The FSP is to cash settle the applicant $4,186 for temporary accommodation. Case No: 518987 Determination Page 7 of 11 The applicant says additional damage was caused to her contents The applicant says further damage was caused to many of her contents items, some being antiques. The applicant wants compensation for these items. SG has confirmed in its report that a number of contents items have been marked with paint. This is also supported by photographs. SG has identified at least four wooden items with paint damage, in addition to household ornaments. The applicant says her antique light was also damaged. SG has accounted for these in its scope of works and quote for professional cleaning. SG has not, however, accounted for these items to be re-painted or re- finished despite its repair audit report stating “ The timber furniture will require cleaning and re-finishing ”. SG’s quote allows $1,293.12 for the re -finishing of the cedar shutters only. The applicant has not provided a quote for the cost of re- finishing her damaged furniture. The FSP is not liable to pay any further costs for rectification works The FSP has accepted rectification works amounting to $52,367.70. As outlined above, the FSP is liable for a further temporary accommodation and removalist costs. The FSP’s quotation included an allowance for a builder’s margin and contingencies. The Panel has found that an additional allowance of $4,761, being 10% of the original costs of $47,607, be made for the fact that this claim is being cash settled as the applicant will be arranging the rectification work herself. The Panel is satisfied that the FSP is not liable for any further rectification costs. T he applicant originally requested the FSP provide her the amount accepted in SG’s rectification report so she could start to organise repairs herself, despite disputing the balance of what she felt she was entitled to. The FSP refused this request unless t he applicant signed a deed of release in full and final settlement of the dispute. Considering, however, the applicant was entitled to the $52,367.70 regardless of what was the outcome of the dispute, the FSP should apply statutory interest to this amount in accordance with section 57 of Act. Interest is to be applied from 3 May 2018, the date of SG’s repair and audit report, to the date of payment. 2.2 Is the applicant entitled to further non-financial loss compensation? The FSP has offered $3,000 in non-financial loss compensation The FSP accepted the applicant’s claims experience has not been a positive one and has offered a $1,500 ex gratia payment for the poor workmanship carried out to her property. The FSP has also offered a further ex gratia payment of $1,500 for the applicant’s stress and inconvenience. The applicant, however, says this is far from meeting her level of stress and suffering she experienced. The applicant is extremely upset about the way the FSP’s repairer treated her; she says she has even purchased a security camera as a result. Case No: 518987 Determination Page 8 of 11 The applicant is entitled to compensation for non-financial loss Under 9.3 of our Terms of Reference (TOR), FOS may award compensation for non- financial loss in certain limited circumstances. That includes for situations where there has been an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the applicant’s expectation of enjoyment or peace of mind. However, the maximum amount of compensation FOS can award for non-financial loss is $3,000 per claim. The claim is measured by each event that gave rise to non- financial loss. In this instance, the applicant was reasonably entitled to expect that work undertaken by the FSP’s repairer, in meeting its obligat ions under the policy, would be carried out in a professional and reliable manner. The applicant was also entitled to feel safe with the repairer entering her home. The Panel considers the applicant’s emotional distress about the way she was allegedly treated by the repairer and the defective repair work to be cause for a claim for non-financial loss compensation. The FSP is to compensate $3,000 for the applicant’s distress The FSP’s first building consultant provided a re -attendance report of 9 November 2017 and stated: “I can advise that the insured’s discomfort, distress, tears and fear of the painting contractor that was visible to me during my re- attendance was completely genuine.” While the Panel accepts the FSP cannot always guarantee the conduct of the contactors it uses for repairs, upon engagement of that particular repairer the FSP does take on responsibility for the repairer’s actions. As can be grasped from SG’s repair audit report and discussion above, the FSP’s repairer caused a large amount of additional damage other than the original water damage claimed for. There was damage in areas that were not even affected by the original water damage claim. The Panel considers it fair in the circumstances that the FSP pay the applicant compensation for her visible stress and discomfort following the repairers conduct. This means the FSP should pay the applicant $3,000 in total for her distress and discomfort caused by the repairer and the faulty repair work. Case No: 518987 Determination Page 9 of 11 3 Supporting information 3.1 FOS approach to this dispute There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise in this dispute. This decision has been made by a Panel consisting of an ombudsman, an insurance industry representative appointed by the Financial Ombudsman Service Board, and a consumer representative appointed by the Financial Ombudsman Service Board. This determination follows consideration of all of the information exchanged and is based on what is fair in all the circumstances, having regard to the relevant legal principles, terms of the policy, good industry practice including codes of practice and prior determinations where applicable. The parties have raised numerous issues in their submissions to FOS. For the purpose of this determination, commentary is restricted to only those issues considered relevant to the outcome. 3.2 Reports Report Extract SG Repair Audit Report 3 May 2018 It is my opinion that the paint splatters have resulted from inadequate protection of the existing fixtures and fittings throughout the affected areas and represents defective works in accordance with the NSW Guide to Standards and Tolerances – 2017, section 13.2 … The inspection also revealed that the paint applied to the ceiling areas of the affected rooms displayed evidenc e of starved painted surfaces. It is my opinion that the starved painted surfac es is consistent with only a single coat of paint being applied to the affected ceiling areas and represents defective works in accordance with the NSW Guide to Standards and Tolerances – 2017, section 13.2 … As a result of the contractor’s defective works, it is my opinion that:  The contents of the affected area will require removal and storage.  The entire rumpus room, spare room, offic e and stairwell will need to be repainted.  The carpets to the entire hous e will require replac ement in order to be consistent throughout.  The paving and tiles to the front ent ry will require cleaning. Case No: 518987 Determination Page 10 of 11  The front entry metal door will require cleaning or re - surfacing.  The light fitting and air - conditioning outlets will require cl eaning.  The metal balustrade in the stairwell will require cleaning.  The cedar shutters and blinds will require cleaning and re - finishing.  The timber furnit ure will require cleaning and re - finishing  The affected household ornaments will require cleaning. … SUMMARY The inspection confirmed that the cont ractor engaged to undertake remedial works to the residence has failed to complete the works to the residenc e, fixtures and fittings with due care and skill. As a result, further extensive remediation works wi ll be required to restore the residence to an acceptable industry standard. CC Re - attendance Report 9 November 2017 We found the ceiling to be showing evidence of uneven and patchy paint work. It appears the roller has not been correctly and evenly applies…resulting in a patchy and poor finish… We also found that the cutting in around the ceiling above the stairs was also poorly completed… Cutting marks along the cornice to the front elevation wall were left along the wall. … I can confirm that the p ainting of the walls to the spare room has not been completed. … SUMMARY … The Insured advised that during the course of repairs and mostly after the completion of repairs the painting contractor would communicate with her in an aggressive manner and she would be intimidated by the painting contractor to a point that she was afraid to allow the painter into her home. The Insured advised that when she attempted to raise concerns with the painter over the quality of the painting works and incomplet e repairs to the spare room the paint er became aggressive and made threatening remarks towards her. I obviously cannot comment on the insured's allegations as I am unable to substantiat e same, however I can advis e that the lnsured's discomfort, distress, tears and f ear of the painting contractor that was visible to me during my re - attendance was completely genuine. It would be my suggestion that should painting rectification works as stated above be accepted that an alternative painting Case No: 518987 Determination Page 11 of 11 contractor be engaged. 3.3 Additional information relied upon  The parties’ submissions.  SG’s scope of works and itemized quotation for rectification work.  The applicant’s quotes for painting, shutters, carpet, temporary accommodation and removals.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.