Delay transferring savings account funds to new linked bank account
Summary
The applicant alleged the FSP delayed transferring savings funds to a new linked bank account after a phone request. AFCA found no undue delay, noting the applicant contributed, and that the FSP's identity verification and customer service matters were outside its power to review.
FOS cannot review the FSP's identity verification policy or general customer service, and the funds were transferred by end of March 2018 with no financial loss or unusual non-financial loss.
Issues
- Delay primary · not upheld
“The available information does not show the FSP unduly delayed in processing the transfer of Account funds to the C Account.”
- Poor communication secondary · upheld
“The FSP could have explained this more clearly when it spoke to the applicant on 11 March 2018.”
Subjects and remedies
no remedy
Text of the determination
Determination
Case No: 518874 Determination Page 1 of 5
Case number: 518874 31 July 2018
1 Overview
1.1 Dispute
The applicant held the following accounts with the financial services provider (FSP):
FSP account Linked to …
Savings account ***9080 (Account 1) S Bank account ***9781 (S Account)
Savings account ***2141 (Account 2) C Bank account ***6225 (C Account)
On 24 February 2018 the applicant called the FSP to transfer both Account funds to
the C Account. The FSP transferred $1.79 from Account 2 to the C Account the same
day. However, it first required the applicant to update the linked bank account for
Account 1 from the S Account to the C Account.
The applicant says the FSP delayed in processing his instructions to update the
linked bank account and transfer Account funds to the C Account.
1.2 Issues and key findings
Did the FSP delay transferring the Account funds to the C Account?
The available information does not show the FSP unduly delayed in processing the
transfer of Account funds to the C Account. More likely than not, the applicant also
contributed to the delay by stating he had not closed the S Account when he sought
to update the linked bank account details for Account 1 online.
What is the applican t’s loss?
The FSP is not required to compensate the applicant for loss because:
it sent the Account funds to the C Account by end of March 2018
he did not incur a degree of stress and inconvenience that warrants
compensation for non-financial loss.
1.3 Determination
This determination is in favour of the FSP. The FSP is not required to compensate
the applicant.
Case No: 518874 Determination Page 2 of 5
2 Reasons for determination
2.1 Did the FSP delay transferring the Account funds to the C Account ?
The FSP ’s policy sets out steps to update a new linked bank account
The FSP requires a linked account to make withdrawals from the Accounts. Page 40
of the Account terms and conditions provides that a new linked account may take up
to 10 business days to verify. The FSP says it applies this process for security
reasons and to confirm that its customer will receive the requested account funds.
The FSP ’s policy is:
Where the current linked bank account is open - send a random value transfer
for the customer to then confirm receipt
Where the current linked bank account is closed - debit a small amount for
rejection and confirmation of that account’s closed status .
After this, the new linked bank account should then be available for use and to make
withdrawals. However, if the status of the linked bank account is incorrectly selected
then it will have to restart the process. The Financial Ombudsman Service (FOS)
cannot compel the FSP to change its policy about how to update a linked bank
account in this dispute.
The applicant asked the FSP to transfer Account funds to the C Account
The applicant called the FSP on 24 February 2018 to transfer the Account funds to
the C Account. He had not used the Accounts for around five years. Given this, the
FSP had difficulty in identifying him at times as he incorrectly answered some of the
old security questions. The FSP’s verification procedure is further dealt with in
section 3.1 below.
I accept the applicant initially told the FSP on this call that he had closed the
S Account. However, he also then told the FSP he would complete updating the
linked bank account details online. The FSP confirmed this with the applicant and so
stopped processing his request over the phone.
The applicant sought to change the linked bank account for Account 1
The FSP says the applicant made an error online by not selecting the closed status
for the S Account. Given this, it sent a random value transfer to the S Account
instead of attempting a small debit for Bank S to then reject. This appears the most
likely scenario based on the FSP’s call recordings and system notes. This means I
do not accept the FSP is solely liable for the delay in transferring the funds from
Account 1 to the C Account.
There was also some confusion because the FSP had transferred $1.79 to the
C Account. The applicant thought this was a random value transfer and part of the
FSP’s policy to verify the C Account, when the FSP did so because it had closed
Account 2. The FSP could have explained this more clearly when it spoke to the
applicant on 11 March 2018. However, consistent with the FSP’s policy, it had to
restart the linked bank account process at this time given the closed status of the
Case No: 518874 Determination Page 3 of 5
S Account. The FSP eventually manually transferred from Account 1 to the
C Account:
$256.30 on 19 March 2018
$0.15 on 27 March 2018 (as an interest credit).
2.2 What is the applicant’s loss?
The applicant has not incurred financial loss in any event
The FSP transferred both the Account funds to the C Account by end of March 2018.
This means the applicant has not incurred any financial loss for which the FSP must
compensate him.
The applicant is not entitled to compensation for non-financial loss
FOS takes a conservative approach to compensation for non-financial loss and our
approach is set out in section 3.2 below. Overall, I do not consider the applicant
suffered a degree of stress and inconvenience that warrants compensation. This is
because the FSP did not solely cause the delay in changing the linked bank account
for Account 1 and transferring its funds to the C Account. The Account funds
available were relatively small, and the applicant did not state he relied on accessing
them for any urgent purpose. FOS also expects that an applicant be moderately
robust and bear the normal degree of inconvenience when a problem occurs, such
as in this dispute where:
the FSP had difficulty in identifying the applicant and there was some confusion
about the purpo se of the FSP’s $1.79 credit to Account 2
the applicant more likely than not listed the S Account as active, when it had
closed.
The FSP apologised to the applicant for customer service issues during the dispute. I
do not consider any extra award of compensation to him appropriate in the
circumstances.
Case No: 518874 Determination Page 4 of 5
3 Supporting information
3.1 Claims that FOS cannot consider
FOS cannot review the FSP’s policy about identity verification
The applicant complained about the FSP’s verification procedures and certain
security questions asked of him by its representatives. FOS accepts that the FSP is
entitled to verify a customer’s identity before discussing account information with
them. FOS cannot review or compel the FSP to change the type of questions it asks
its customers, as this is the FSP’s own policy.
Customer service issues
FOS does not have the power to consider disputes concerning the general level of
customer service provided by a financial services provider. Disputes relating to
customer service are more appropriately dealt with by the financial services provider
itself. This is because the level of customer service is influenced by the financial
services provider’s policy on a number of issues, such as staff levels and training.
3.2 FOS approach
How we assess disputes
FOS is not a court of law. We do not have the power to take or test evidence on oath,
or to require third parties to give evidence. When we assess disputes, we consider
available documents, the recollections of the parties and all relevant circumstances.
We give more weight to contemporaneous documentary information. If there is no
relevant documentation, we will decide what is most likely to have occurred based on
the information provided to us. If there are conflicting recollections and these are
evenly weighted, we may find that a claim cannot be established.
Compensation for non-financial loss
Non-financial loss includes claims for stress or inconvenience caused by an error of
the financial services provider. The maximum amount we can award for non-financial
loss is $3,000 for each claim.
We will only award compensation for non-financial loss if there has been an unusual
degree or extent of inconvenience. We will not award compensation for loss that an
applicant may incur as a result of pursuing a dispute or rectifying a financial services
provider’s error.
When assessing whether the circumstances are of an unusual nature we will review:
the degree or extent of physical inconvenience suffered
the general time taken to resolve the dispute
the extent to which the financial services provide r’s actions interfered with the
applicant’s expectation of enjoyment or peace of mind.
Case No: 518874 Determination Page 5 of 5
We will assess any claims for non-financial loss in accordance with the FOS Terms
of Reference. If we do award compensation, it is unlikely to be substantial.