Summary
Stormwater claim where contractor W's wardrobe repairs were substandard and the FSP offered a $3,154.91 cash settlement based on W's quote. AFCA ordered a fresh quote from a willing repairer for cash settlement, plus $750 for non-financial loss.
An insurer cannot settle on a quote from a repairer unwilling to complete the works, and undue delay supports non-financial loss compensation under the Terms of Reference.
Issues
- Claim amount dispute primary · upheld“The FSP's offer does not fulfil its obligations to the applicant as this settlement is based on information from W, which is not prepared to complete the works.”
- Delay secondary · upheld“It has taken the FSP an unreasonably long period of time to process the claim.”
- Repairs or contractors secondary · upheld“the wardrobe repairs completed by W are clearly not to an acceptable standard and will require rectification works.”
Subjects and remedies
pay non financial lossreassess claim
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Determination
Case No: 517468 Determination Page 1 of 4
Case number: 517468 30 July 2018
1 Overview
1.1 Dispute
The applicant held a home building and contents insurance policy (the policy) with
the financial services provider (FSP). On 9 January 2018, the applicant lodged a
claim for stormwater damage to the insured property. The FSP accepted the claim
and authorised repair/replacement works under the claim to contractors ‘W’.
The applicant remains dissatisfied with the quality of repairs completed by W as well
as the FSP’s overall management of the claim. The applicant is seeking a higher
cash settlement and compensation for non-financial loss under the claim.
1.2 Issues and key findings
Does the FSP’s cash settlement offer fulfil its policy obligati ons?
The FSP, in seeking to finalise the applicant’s claim, has offered to issue a cash
settlement to the applicant in an amount of $3,184.91 (relating to the wardrobe in
question). The FSP’s offer does not fulfil it s obligations to the applicant as this
settlement is based on information from W, which is not prepared to complete the
works.
Accordingly, the FSP is to arrange a quote for the required repair and rectification
works from a consultant that is prepared to honour its quote. The wardrobe aspect of
the claim can be then be settled based on such a quote.
Is the applicant entitled to compensation from the FSP?
The available information establishes the FSP’s overall management of the claim
was less than ideal. Accordingly, in line with the FOS Terms of Reference, the FSP is
to arrange payment of $750 to the applicant by way of compensation for non-financial
loss.
1.3 Determination
This determination is substantially in favour of the applicant.
The FSP is to arrange for fresh quote for repairs and rectification works to be
obtained from a consultant that is actually prepared to complete the works , even if
approached by the applicant.
The FSP is to arrange payment of $750 to the applicant by way of compensation for
non-financial loss under the claim.
Case No: 517468 Determination Page 2 of 4
2 Reasons for determination
I note at the time of lodging this dispute the applicant had also raised concerns
regarding the FSP not provide him and his family with temporary accommodation
over the course of the claim. This aspect of the applicant’s dispute has been dealt
with in FOS’s preliminary view letter dated 25 June 2018.
I acknowledge and completely agree with the findings of the preliminary view in this
regard. The insured property did remain habitable for the purpose of the policy over
the course of the claim.
2.1 Does the FSP’s final cash settlement fulfil its obligations?
The quote relied on by the FSP to cash settle the claim is not acceptable
I have considered the available information and am satisfied on the balance of
probabilities it establishes the following:
the applicant found storm water ingress damage to the insured building on the
morning of 9 January 2018
the applicant contacted the FSP and lodged a claim for the damage
the FSP accepted the claim and appointed W to complete the repairs. The
repairs included replacement of some parts of damaged wardrobe, which is
subject of the dispute between the parties
the wardrobe repairs completed by W are clearly not to an acceptable standard
and will require rectification works which W has refused to undertake due to the
breakdown in relationship with the applicant
the FSP, on information provided by W, has sought to cash settle the applicant
for this aspect of the claim in the amount of $3,154.91, which the applicant
deems insufficient
the applicant has provided a quote from a different consultant in the amount of
$5,325.80 which the FSP has rejected as being unreasonable.
The information does not establish complete wardrobe replacement is needed
The available information establishes on balance the repairs completed by W to the
wardrobe subject of this dispute were not done to an acceptable level. Further, in the
course of carrying out the repairs, W has caused further damage to walls, ceiling and
skirtings in an around the wardrobe.
It is clear the applicant is very dissatisfied with the quality of repairs as we ll as the
unreasonable amount of time it is has taken the FSP to manage the claim.
Having considered the available information, I am satisfied the applicant has shown
the works completed by W are not to an acceptable standard. In saying that, I also
accept the FSP’s position that the repairs had yet to be completed and there is no
information establishing the wardrobe now requires complete replacement.
In my opinion, I am satisfied the available information does show the wardrobe
repairs are in need of rectification and finalisation. Also, that there now exists
additional damage caused to the property in and around the wardrobe caused by W.
Case No: 517468 Determination Page 3 of 4
I acknowledge the applicant is of the view a complete replacement of the wardrobe is
warranted. However, as noted above, I do not believe the available information
supports this is the case. Rather, the wardrobe can be repaired/rectified to the
standard the FSP is obliged to provide under the claim.
I note the FSP, in an effort to resolve the dispute, without accepting complete
replacement of the wardrobe was needed offered to pay the applicant $3,154.91
which it says represents the cost to remove and replace the wardrobe. This
settlement offer is based on information from W, which is not prepared to do the
works.
FOS, has on many occasions in the past, made it clear that an insurer is not entitled
to rely on quotes to determine its liability to a claimant where the consultant providing
the quote is not prepared to complete the quoted works. This is the case in this
instance and therefore, I am not satisfied the FSP has established an entitlement to
settle the claim on this basis.
I determine the FSP, within 14 days of the applicant accepting this determination, is
to obtain a quote for the repair and rectification of the wardrobe to the required
standard. The quote is to also include the cost to repair all the additional damage
caused by W in its attempt to repair the wardrobe.
The above quote is to be sourced from repairer that is prepared to complete the
works for the quoted amount regardless of whether authorised by the FSP under the
claim or approached by the applicant outside of the claim. The FSP is to then cash
settle the applicant on the basis of this quote under the claim.
2.2 Is the applicant entitled to compensation under the claim?
The FSP’s overall management of the claim was less than ideal
The FSP acknowledges that there were concerns regarding the level of service
provided to the applicant under the claim for which it has apologised. However, the
FSP is not of the view these concerns with its level of service are such that require
payment of compensation to the applicant under the claim.
The TOR allow for an award of compensation for non-financial loss up to a maximum
award of $3,000. Such an award is subject to co nsideration as to whether there has
occurred an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the a pplicant’s expectation of enjoyment or
peace of mind.
The available information establishes the applicant’s claim has taken an undue
extent of time to resolve and finalise. I accept the delay in finalising the claim has
been contributed to by both parties however the majority of the responsibility rests
with the FSP and its appointed consultants. I note the FSP has also waived the
applicant’s excess payment under the claim.
Having considered all the information, I am satisfied it is clear that there has been a
failure by the FSP to provide an acceptable level of service under the claim. It has
taken the FSP an unreasonably long period of time to process the claim and which
Case No: 517468 Determination Page 4 of 4
for the most part is due to delays in the assessment and repairs process. I am
satisfied this not only amounts to undue delay in finalising the claim but will
reasonably have also caused undue stress and interference with the applicant’s
peace of mind.
In line with section 9.3 b) (i) of the FOS ToR, I determine the FSP is to arrange
payment of $750 to the applicant by way of non-financial compensation under the
claim.
3 Supporting information
TOR 9.3
9.3 Other compensation
...
b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the
Financial Services Provider Compensate the Applicant for non-financial
loss but only where:
(i) An unusual degree or extent of physical inconvenience, time
taken to resolve the situation or interference with the Applicant’s
expectation of enjoyment or peace of mind has occurred; or
(ii) In the case of a Dispute pertaining to an individual’s privacy right s
– injury has occurred to the Applicant’s feelings or humiliation has
been suffered by the Applicant.
The maximum amount of compensation for non-financial loss will be $3,000 per claim