Determination 517468

claim_amount_dispute

FirmFinancial Firm (Unknown - Insurer)
Decided2018-08-17
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$750
Amount claimed$5,326
SourceAFCA PDF

Summary

Stormwater claim where contractor W's wardrobe repairs were substandard and the FSP offered a $3,154.91 cash settlement based on W's quote. AFCA ordered a fresh quote from a willing repairer for cash settlement, plus $750 for non-financial loss.

An insurer cannot settle on a quote from a repairer unwilling to complete the works, and undue delay supports non-financial loss compensation under the Terms of Reference.

Issues

Subjects and remedies

pay non financial lossreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 517468 Determination Page 1 of 4 Case number: 517468 30 July 2018 1 Overview 1.1 Dispute The applicant held a home building and contents insurance policy (the policy) with the financial services provider (FSP). On 9 January 2018, the applicant lodged a claim for stormwater damage to the insured property. The FSP accepted the claim and authorised repair/replacement works under the claim to contractors ‘W’. The applicant remains dissatisfied with the quality of repairs completed by W as well as the FSP’s overall management of the claim. The applicant is seeking a higher cash settlement and compensation for non-financial loss under the claim. 1.2 Issues and key findings Does the FSP’s cash settlement offer fulfil its policy obligati ons? The FSP, in seeking to finalise the applicant’s claim, has offered to issue a cash settlement to the applicant in an amount of $3,184.91 (relating to the wardrobe in question). The FSP’s offer does not fulfil it s obligations to the applicant as this settlement is based on information from W, which is not prepared to complete the works. Accordingly, the FSP is to arrange a quote for the required repair and rectification works from a consultant that is prepared to honour its quote. The wardrobe aspect of the claim can be then be settled based on such a quote. Is the applicant entitled to compensation from the FSP? The available information establishes the FSP’s overall management of the claim was less than ideal. Accordingly, in line with the FOS Terms of Reference, the FSP is to arrange payment of $750 to the applicant by way of compensation for non-financial loss. 1.3 Determination This determination is substantially in favour of the applicant. The FSP is to arrange for fresh quote for repairs and rectification works to be obtained from a consultant that is actually prepared to complete the works , even if approached by the applicant. The FSP is to arrange payment of $750 to the applicant by way of compensation for non-financial loss under the claim. Case No: 517468 Determination Page 2 of 4 2 Reasons for determination I note at the time of lodging this dispute the applicant had also raised concerns regarding the FSP not provide him and his family with temporary accommodation over the course of the claim. This aspect of the applicant’s dispute has been dealt with in FOS’s preliminary view letter dated 25 June 2018. I acknowledge and completely agree with the findings of the preliminary view in this regard. The insured property did remain habitable for the purpose of the policy over the course of the claim. 2.1 Does the FSP’s final cash settlement fulfil its obligations? The quote relied on by the FSP to cash settle the claim is not acceptable I have considered the available information and am satisfied on the balance of probabilities it establishes the following:  the applicant found storm water ingress damage to the insured building on the morning of 9 January 2018  the applicant contacted the FSP and lodged a claim for the damage  the FSP accepted the claim and appointed W to complete the repairs. The repairs included replacement of some parts of damaged wardrobe, which is subject of the dispute between the parties  the wardrobe repairs completed by W are clearly not to an acceptable standard and will require rectification works which W has refused to undertake due to the breakdown in relationship with the applicant  the FSP, on information provided by W, has sought to cash settle the applicant for this aspect of the claim in the amount of $3,154.91, which the applicant deems insufficient  the applicant has provided a quote from a different consultant in the amount of $5,325.80 which the FSP has rejected as being unreasonable. The information does not establish complete wardrobe replacement is needed The available information establishes on balance the repairs completed by W to the wardrobe subject of this dispute were not done to an acceptable level. Further, in the course of carrying out the repairs, W has caused further damage to walls, ceiling and skirtings in an around the wardrobe. It is clear the applicant is very dissatisfied with the quality of repairs as we ll as the unreasonable amount of time it is has taken the FSP to manage the claim. Having considered the available information, I am satisfied the applicant has shown the works completed by W are not to an acceptable standard. In saying that, I also accept the FSP’s position that the repairs had yet to be completed and there is no information establishing the wardrobe now requires complete replacement. In my opinion, I am satisfied the available information does show the wardrobe repairs are in need of rectification and finalisation. Also, that there now exists additional damage caused to the property in and around the wardrobe caused by W. Case No: 517468 Determination Page 3 of 4 I acknowledge the applicant is of the view a complete replacement of the wardrobe is warranted. However, as noted above, I do not believe the available information supports this is the case. Rather, the wardrobe can be repaired/rectified to the standard the FSP is obliged to provide under the claim. I note the FSP, in an effort to resolve the dispute, without accepting complete replacement of the wardrobe was needed offered to pay the applicant $3,154.91 which it says represents the cost to remove and replace the wardrobe. This settlement offer is based on information from W, which is not prepared to do the works. FOS, has on many occasions in the past, made it clear that an insurer is not entitled to rely on quotes to determine its liability to a claimant where the consultant providing the quote is not prepared to complete the quoted works. This is the case in this instance and therefore, I am not satisfied the FSP has established an entitlement to settle the claim on this basis. I determine the FSP, within 14 days of the applicant accepting this determination, is to obtain a quote for the repair and rectification of the wardrobe to the required standard. The quote is to also include the cost to repair all the additional damage caused by W in its attempt to repair the wardrobe. The above quote is to be sourced from repairer that is prepared to complete the works for the quoted amount regardless of whether authorised by the FSP under the claim or approached by the applicant outside of the claim. The FSP is to then cash settle the applicant on the basis of this quote under the claim. 2.2 Is the applicant entitled to compensation under the claim? The FSP’s overall management of the claim was less than ideal The FSP acknowledges that there were concerns regarding the level of service provided to the applicant under the claim for which it has apologised. However, the FSP is not of the view these concerns with its level of service are such that require payment of compensation to the applicant under the claim. The TOR allow for an award of compensation for non-financial loss up to a maximum award of $3,000. Such an award is subject to co nsideration as to whether there has occurred an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the a pplicant’s expectation of enjoyment or peace of mind. The available information establishes the applicant’s claim has taken an undue extent of time to resolve and finalise. I accept the delay in finalising the claim has been contributed to by both parties however the majority of the responsibility rests with the FSP and its appointed consultants. I note the FSP has also waived the applicant’s excess payment under the claim. Having considered all the information, I am satisfied it is clear that there has been a failure by the FSP to provide an acceptable level of service under the claim. It has taken the FSP an unreasonably long period of time to process the claim and which Case No: 517468 Determination Page 4 of 4 for the most part is due to delays in the assessment and repairs process. I am satisfied this not only amounts to undue delay in finalising the claim but will reasonably have also caused undue stress and interference with the applicant’s peace of mind. In line with section 9.3 b) (i) of the FOS ToR, I determine the FSP is to arrange payment of $750 to the applicant by way of non-financial compensation under the claim. 3 Supporting information TOR 9.3 9.3 Other compensation ... b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the Financial Services Provider Compensate the Applicant for non-financial loss but only where: (i) An unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; or (ii) In the case of a Dispute pertaining to an individual’s privacy right s – injury has occurred to the Applicant’s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.