Home / Financial Firm (Unknown - Insurer) / Determination 516292

Determination 516292

Storm damage claim to smash repair business premises partly denied; partial settlement ordered

FirmFinancial Firm (Unknown - Insurer)
Decided2018-08-21
ProductGeneral Insurance · Motor
OutcomeFor the complainant in part
Amount awarded$12,000
Non-financial loss—
Amount claimed$70,000
SourceAFCA PDF

Summary

A motor smash repair business claimed over $70,000 for storm and water damage to its premises, and the FSP denied the claim for pre-existing roof defects and claim delays. AFCA found some storm damage was covered and ordered a $12,000 full and final settlement with no interest.

The seepage exclusion did not apply to water entering through the roof, but the applicant's delay and failure to make the property watertight prejudiced the FSP's assessment, so AFCA limited the settlement to the storm-related damage established.

Issues

Subjects and remedies

home or building damagesmall businesspay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 516292 Determination Page 1 of 8 Case number: 516292 3 August 2018 1 Overview 1.1 Dispute The applicant holds a motor trade insurance policy which provides cover for its motor vehicle smash repair business. In June 2015, the applicant lodged a claim under the policy for storm damage to the business premises and equipment. The FSP denied the claim on the basis that the damage was caused by pre-existing issues with the roof which allowed water to enter the property. The FSP also says it has been prejudiced by the applicant’s delay in providing information and failure to protect the property from further damage. The applicant disputes the FSP’s decision and seeks cover for the cost of repairing the damage (estimated at over $70,000). 1.2 Issues and key findings Is the FSP liable for the damage? The available information establishes that not all of the damage claimed by the applicant was caused by the storm in June 2015. Further, the FSP’s ability to assess the claim has been materially prejudiced by the applicant’s delay and failure to undertake repairs. Nevertheless, I am satisfied that, on the balance of probabilities, the applicant’s property suffered some damage during the storm, in circumstances which are not clearly excluded under the policy. In these circumstances, a partial settlement of the claim is appropriate. 1.3 Determination This determination is partly in favour of the applicant. The FSP is to pay the applicant the amount of $12,000 in full and final settlement of the claim. The FSP is not required to pay interest on this amount. Case No: 516292 Determination Page 2 of 8 2 Reasons for determination 2.1 Is the FSP liable for the damage? Policy provides cover for storm damage subject to exclusions The applicant is required to show that, on the balance of probabilities, it has suffered a loss caused by a risk insured against under the policy. This is known as a prima facie claim. If the applicant is able to establish a prima facie claim, then the onus shifts to the FSP to show that, on the balance of probabilities, it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. The a pplicant’ s policy provides cover for damage caused by the events listed in the policy, including the insured event of storm. However, the insured event of storm excludes cover for damage caused by water seeping or percolating through a wall, roof or floors. The policy also contains a general condition which requires the applicant to take reasonable care to maintain the premises (and other business property) in sound condition. The policy provides that the FSP may refuse to pay a claim or reduce the amount paid if the applicant breaches this condition. FSP’s assessment of claim was delayed The FSP did not assess the damage to the property until approximately ten months after the storm occurred, as it was waiting for the applicant to provide further information. The applicant lodged a claim for storm damage on 25 June 2015. During the claim lodgement process, the applicant advised that water had leaked through the roof, causing damage to the ‘lighting and bathroom’. The FSP made several attempts to contact the applicant o ver the following weeks to make arrangements for a builder to be appointed to assess the damage to the property. However, the applicant failed to respond. On 7 August 2015, the applicant called the FSP and advised that she would prefer to appoint her own builder. The FSP explained that the applicant’s builder would need to provide a report on the damage and a quotation for the necessary repairs. The FSP attempted to contact the applicant by telephone and mail over the following months regarding the provisi on of her builder’s report. However, when the applicant failed to provide the report by mid-November 2015, the FSP closed the claim. In March 2016, the applicant provided a quotation from her builder (NC) for $62,540 for the repair of ‘water flood damage’ to the business premises. NC’s quotation included repairs to the roof and the replacement of ceilings in the bathroom, office and workshop. Case No: 516292 Determination Page 3 of 8 However, NC’s quotation did not provide any further information about the nature of the damage and the mechanism by which it had occurred, or include any photographs. The applicant has subsequently submitted additional quotes for the repair of water damage to the auto spray booth and the replacement of a water damaged camera system. She says the computers in the office also suffered water damage. Following receipt of NC’s report, the FSP appointed an assessor (CC) to attend the property and inspect the damage. The FSP subsequently appointed an engineer (TE) to determine the cause of the damage. Property has suffered damage due to rainwater entry The FSP’s engineer (TE) inspected the property in July 2016 and confirmed there was evidence of water damage to the ceilings in the office and bathroom areas. This damage is apparent in the photographs included in TE’s report. TE advised that the damage to the ceilings had occurred when stormwater entered through the roof due to an inadequate and poorly maintained drainage system. In particular, TE noted that:  a large amount of cement render had been left on the office roof, preve nting effective drainage of rainwater during storms  the box gutters were partly blocked and the roof drainage system had been inadequately designed and poorly maintained, with evidence of ineffective past repairs  the parapet flashing above the bathroom had become detached from the brick wall, so that funneled storm water directly into the bathroom and workshop areas. TE reported that there was water staining to the timber roof framing in the area around the spray booth, although he found no evidence of structural damage to the roof frame. While he was advised by the applicant that there was water damage to the spray booth (and a light fitting above), he was unable to verify this damage. TE observed the following issues with the roof, which may have allowed water to enter the workshop area:  an opening in the cladding and framing near the parapet (within one metre of the spray booth). While a temporary steel sheet had been installed to cover the gap, this was not watertight  patches of flat sheet flashing, aged flexible sealant and rusty roof sheets in the area around the exhaust system above the spray booth  blocked, inadequate and damaged box gutters and undersized downpipes which would result in storm water overflowing the drainage system. The numerous close- up, colour photographs included in TE’s report clearly show the deficiencies with the roof and drainage system which he identified as allowing water entry to the property. In May 2018, the applicant provided a report from her builder (NC). In his report, NC stated that he had taken notes during his inspection of the property in May 2015. Case No: 516292 Determination Page 4 of 8 NC’s notes reflect that there was extensive damage to the roof and box gutters, roof framing, internal ceilings and electrical services. NC advised that all of this damage had been caused by strong winds and rainfall during ‘recent storms’. However, he did not provide any further information about how and where water had entered the building. The date of May 2015 specified in NC’s report precedes the storms in June 2015 which the applicant has identified as causing the loss. However, it is possible this was an error on the part of the NC, given the three year period between his inspection and the preparation of his report. Both TE and NC also identified a crack in the external brickwork over the entry shutter. However, Google images establish that this crack was present prior to the storm and the applicant has confirmed that this damage does not form part of the claim. Applicant has established prima facie claim for storm damage The reports prepared by the FSP’s engineer (TE) confirm that the applicant’s property suffered water damage due to rainwater entering the building. On this basis, I am satisfied that the applicant has established a prima facie claim for storm damage under the policy. In these circumstances, the FSP is required to show that it is entitled to rely on an exclusion under the policy or is otherwise entitled to deny the claim. FSP is unable to rely on policy exclusions or conditions The FSP has sought to rely on the exclusion for damage caused by water seeping or percolating through the roof or walls of the property. However, the ordinary meaning of ‘seeping’ or ‘percolating’ refers to water entering through porous substances. This exclusion does not apply in the present case, given given the means by which water entered the applicant’s property. The FSP has also relied on the policy condition which requires the applicant to take ‘reasonable care’ to maintain the building in a sound condition. However, the courts have held that, in order for an insurer to be able to rely on a policy condition of this type, it is necessary for the insurer to show that the insured person:  was aware of the risk of his or her actions (in a subjective sense), and  delibe rately ‘courted’ the danger (by failing to take adequate measures to avoid it) or showed reckless indifference as to whether or not the danger eventuated. Accordingly, the FSP’s ability to rely on breach of the policy condition depends on the extent to which the applicant was aware of the risk of damage to the property due to the condition of the roof drainage system (for example, because of past damage during previous storms). Case No: 516292 Determination Page 5 of 8 In the present case, there is insufficient information to establish the extent of the applicant’s awareness of the issues with the roof, in part due to the delays experienced during the claim process. Delays by applicant have prevented accurate assessment of claim As outlined above, there have been significant delays during the claim process. These delays were primarily due to the time taken by the applicant to provide a builder’s report, after she agreed to do so. The applicant has not provided any explanation for the delay. Further, the initial document provided by the applicant ’s builder (NC) was a quotation (rather than a report) which provided very limited information about the nature of the damage and how it occurred. Accordingly, it was necessary for the FSP to arrange its own assessment. These issues led to a delay of approximately one year before a comprehensive assessment of the property was undertaken, which has made it difficult to determine the extent of the damage caused by the storm. I am satisfied that the FSP took reasonable steps to progress the claim. The FSP offered to appoint a builder to assess the damage and, when this offer was declined, regularly followed up the applicant in an attempt to obtain her builder’s report. During the period while the claim was delayed, the applicant did not take appropriate steps to make the property watertight and prevent further damage, in circumstances where she was aware there was water entering the building. While the applicant says temporary repairs were carried out, these repairs (as shown in the photographs provided) were clearly ineffective - for example, there is an obvious gap between the edge of the temporary steel sheet i nstalled near the roof parapet through which rainwater could enter. Given the nature and extent of the issues with the roof (as identified by the FS P’s engineer (TE)), it is highly likely that further water damage occurred during regular rainfall events between the date of the storm and the date of TE’s assessment. The initial information provided by the applicant at claim lodgement suggested there was damage to the lighting and bathroom ceiling only. In response to the information provided at claim lodgement, the FSP established a claim estimate of $2,000 (reflecting its impression that the damage was relatively minor). However, the applicant is now seeking cover for the cost of repairs exceeding $70,000. FSP is required to cash settle applicant for $12,000 Having carefully reviewed the quotations provided by the applicant, I am not satisfied that all of the damage claimed was caused by the storm in June 2015. For example, the quotation provided by the applicant’s builder (NC) includes the replacement of all of the roof gutters, capping and flashing as well as sealing and waterproofing of the roof (at an estimated cost of over $17,000). Case No: 516292 Determination Page 6 of 8 However, the bulk of the issues with the roof (as identified by NC) are a consequence of poor design and lack of maintenance, rather than damage caused by the storm. The policy does not provide cover for damage caused in this manner. NC’s quotation also includes an allowance of $9,000 for electrical works, even though there is no evidence that the electrical services at the property have been tested by a qualified electrician and found to be water damaged. Further, I consider it likely that material additional damage occurred in the period following the storm, due to the extended delay in the applicant progressing the claim and her failure to undertake repairs during this period. The FSP says it should not be required to pay the claim due to the applicant’s delay and her failure to undertake repairs. I am satisfied that the FSP has suffered significant prejudice due to the applicant’s actions. In particular, it is difficult to identify the extent of the damage caused by the storm when a detailed assessment was not carried out until twelve months later and the property has remained exposed to further damage in the meantime. However, I am also satisfied that, on the balance of probabilities, the property suffered some damage in the June 2015 storms, in circumstances which are not clearly excluded under the policy. During claim lodgement, the applicant advised of damage to the lighting and the bathroom. The applicant has also provided copies of invoices for the repair of the spray booth and the replacement of the camera system. The spay booth had previously been inspected in February 2015, with no damage observed. These invoices are dated shortly after the storm and state that the items have suffered water damage due to a leaking roof. The FSP has not taken any steps to have the condition of these items assessed by appropriate experts. In these circumstances, I consider it is fair that the FSP pay the applicant the amount of $12,000 in full and final settlement of the claim for storm damage. In determining this amount, I have taken into account the passage of time. Accordingly, the FSP is not required to pay interest on the settlement amount. Case No: 516292 Determination Page 7 of 8 3 Supporting information 3.1 FOS approach to this dispute FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not been the subject of a FOS Preliminary View and has proceeded directly to Determination. This dispute has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered. While the parties have raised numerous issues in their submissions, for the purposes of this determination, commentary has been restricted to those issues which are considered directly relevant to the outcome only. The policyholder is a business. During the course of this dispute, the business has been represented by one of the owners (RN). For the purpose of this determination, the business and RN are referred to collectively as ‘the applicant’. 3.2 Annual inspections by FSP Applicant’s submissions do not alter outcome In her submissions, the applicant has stated that the FSP’s representatives carried out annual inspections of the property and therefore should have been aware of any pre-existing maintenance issues at the time of the storm. The FSP has advised that it does not have a record of any inspections other than an inspection report in relation to the auto spray booth in February 2015, which was prepared by an expert engaged by the applicant for insurance purposes. As outlined in section 2.1 above, I consider that a partial settlement of the claim is appropriate, in light of the applicant’s delays and failure to prevent further damage following the storm. In these circumstances, the applicant’s submissions do not alter the outcome. 3.3 Terms of policy Subject Terms Cover for If your Certificate of Ins urance indic ates that you have taken out cover under Case No: 516292 Determination Page 8 of 8 Subject Terms insured events Section 1, we cover you for loss, destruction, or damage to the Pr operty at the Premises being caused by any of the Defined Events listed below occurring in the Period of Insurance except as provided under We Will Not Pay. Defined event - storm Defined Event Storm, tempest, rainwater or hail We Will Not Pay We w ill not pay for loss, destruction or damage …  caused by water seeping or percolating through a wall, roof or floors … General conditions General Conditions The General Conditions set out below apply to all the Sections. You must comply with the General Conditions otherwise we may be entitled to refuse to pay a claim, or to reduce the amount you are entitled to receive … You must at all times take reasonable care … to maintain the Premises, structures, fittings, fixtures, furnishings, appliances, machinery, implements, plant, and Property in sound condition …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.