The applicant, represented by his son, disputed the FSP's building repair scope and cash settlement offer after a washing machine leak. AFCA found the relationship had broken down, ordered a cash settlement of $74,696.24 with $1,500 non-financial loss, and refused temporary accommodation costs.

The FSP's discretion to cash settle must be exercised fairly, and the settlement is increased to reflect variation risk and the absence of a lifetime guarantee once the applicant takes over repairs.

Issues

Subjects and remedies

home or building damagepay claimpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 515036 Determination Page 1 of 8 Case number: 515036 4 July 2018 1 Overview 1.1 Dispute The applicant holds a home building and contents insurance policy with the financial services provider (FSP). He lodged a claim on 12 July 2017, after a washing machine leak damaged his building and contents. The FSP accepted liability and settled the contents claim for the sum insured. It arranged trades to conduct make safe works. It prepared a quotation for repairs and offered to either cash settle the claim, or undertake repairs. The parties remain in dispute about the amount required to complete repairs. The FSP maintains its latest offer is sufficient to return the property to its pre-loss condition. It is prepared to undertake the repairs or cash settle the claim for the amount quoted by its builders. The applicant says the initial scope of works overlooked relevant damage, and was insufficient to complete the repairs. The applicant no longer trusts the FSP to complete the repairs and seeks a cash settlement based on the quotations he has provided. 1.2 Issues and key findings Is the FSP liable to cash settle the applicant’s claim ? I accept that the relationship between the parties has broken down and it is fair in the circ umstances that the FSP cash settle the applicant’s claim. Is the FSP’s offer with cash settlement fair in all the circumstances? No. I am satisfied it is fair in the circumstances that the FSP increase the cash settlement to $74,696.24 to reflect the likelihood of variations and additional risk assumed by the applicant in the completion of the repairs of the property. Is the applicant entitled to compensation for non-financial loss? The applicant is entitled to compensation of $1,500 for non-financial loss pursuant to paragraph 9.3 of the Terms of Reference. Case No: 515036 Determination Page 2 of 8 1.3 Determination This determination is partly in favour of the applicant. The FSP is required to pay the applicant the following amounts in full and final settlement of their building claim and dispute:  $74,696.24 as a total amount for building repairs  $1,500 as compensation for non-financial loss. The FSP is not required to pay interest on the settlement amount. Case No: 515036 Determination Page 3 of 8 2 Reasons for determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the information in dispute. This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute it had been referred directly to an Ombudsman for determination in line with the operational guidelines to the FOS Terms of Reference. I have decided this dispute based on what is fair in all the circumstances, having regard to the relevant law, terms of the policy, good industry practice, codes of practice and previous determinations. During the course of this dispute, the applicant was represented by his son. For the purposes of this determination, submissions made by the applicant’s son have been treated as if they have been made by the applicant himself. 2.1 Is the FSP liable to cash settle the applicant’s claim ? The FSP has a discretion under the terms of the policy Under the terms of the policy, the FSP has a discretion to settle a claim for damage to the applicant ’ s property by either:  arranging for its contractors to repair the damage to the property  paying the applicant the FSP’s cost of undertaking the repairs. Whilst the FSP has such a discretion the discretion must be exercised fairly and consistently with the principles of reasonableness and utmost good faith. Relationship between parties has broken down During the initial stages of the claim, the FSP appointed its builder (AO) to undertake make safe works, assess the damage and prepare a scope of works for the necessary repairs. However, after the applicant expressed dissatisfaction with the scope and settlement offer, it advised the applicant it was willing to either:  authorize AO to undertake the repairs  cash settle for the amount of A O ’s quotation , $31,549.10. The applicant provided quotations from his preferred trades, both of which significantly exceeded AO’s. He sought to have the FSP’s offer increased to reflect his trades. The FSP obtained a further quotation from another builder, PI. PI’s quotation included additional works, which it said were necessary. It confirmed works could be warranted. The FSP eventually increased its offer to cash settle the applicant’s claim to $47,432.63 rather than complete the repairs. Again, this offer was rejected by the applicant. By this stage it is clear that the relationship between the applicant and the FSP and its contractors had broken down. Whilst the FSP remained prepared to Case No: 515036 Determination Page 4 of 8 complete the works it is clear that the applicant had lost faith in his ability for the FSP to complete the work as required. Fair in the circumstances for the FSP to cash settle the claim. I have had the opportunity of discussing the matter with the applicant. It is clear from those discussions that the applicant would prefer the repairs to completed by his chosen repairer. In the circumstances I consider it fair that the FSP exercise its discretion to cash settle the applicant’s claim with for the reasonable costs of carrying out the necessary repairs. 2.2 Is the FSP ’s offer to cash settle the claim fair in all t he circumstances? Scope of works has been largely agreed After it became clear that the FSP’s builder PI initial quotation was based on an outdated and incomplete scope of works (SOW) PI provided a revised estimate, which increased its offer by $9,038.40. A further revision of the SOW resulted in an additional increase of $6,135.25. During this time the FSP remained willing to authorise its builders to undertake the necessary repairs, subject to the lifetime guarantee provided under the policy. The FSP agreed to include additional outstanding items identified by the applicant and requested revised quotations from AO and PI. It agreed to increase its offer to $62,606.28, being the higher amount from PI. The applicant, in an email of 30 April 2018, raised concerns with the extent of repairs to the bathroom, bins, cleaning and supervision. He says the time allowed for plumbing works is insufficient: PI have allowed for the replacement of one tap. The Kitchen sink tap. Every tapset in the unit has been removed and disposed of. Every tap needs replacing. Vanity taps, toilet stop, bath taps, shower taps, shower rose, Laundry tap and washing machine taps. The toilet pan is broken, requiring a new toilet suite. The bath is being changed. All this means tha t the plumber is virtually going to have to do a whole new rough -in of the unit. Not just a remove/refit like the PI quote states. This is going to take substantially more time than the 12 hrs allowed for by PI. With the fitoff of all the fixtures and fittings it will be more like the 40 hrs I have allowed. [sic] The FSP agreed to increase the scope to include the damaged plumbing and bathroom items, but considered 40 hours of work excessive and unnecessary. It agreed to provide further cover for removal of rubbish, and the total quotation increased by $965. The total offer is $63,571.38. he FSP remains willing to complete the repairs. The applicant says he requires a provisional sum, approximately $7,200, to account for a future variation request which may not be accepted: As I pointed out in my quote, if the windows are damaged by the removal/replacement of the reveals a variation will need to be claimed. If I cant claim a variation later, I will need to claim it now. [sic] Case No: 515036 Determination Page 5 of 8 Other than the possible variations I accept the SOW is largely settled svae for some additional plumbing work. FSP not responsible for additional plumbing costs The applicant says a further 28 hours labour for plumbing works is required. He says this is due to the bath being changed, and ‘the plumber is virtually going to have to do a whole new rough- in of the unit.’ The FSP says the applicant’s statement ‘describes that all the hot and cold pipework (rough- in) has been removed’. The applicant does not dispute the FSP’s view in this assessment. From the available material, it is unclear why plumbing works require replacement. There is no information indicating the inundation event damaged the plumbing works. While the FSP accepts liability for tap wear and fixings inadvertently removed by trades, the available information does not suggest the FSP’s trades disturbed or removed the fixed pipework. In the absence of any information establishing to the contrary, I accept the FSP is entitled to limit the extent of plumbing labour as identified in PI’s scope of works. FSP amended quotation is appropriate starting basis for settlement The cash settlement should reflect the likely cost to an insured of completing the repairs and being placed in the position they were in prior to the loss. It needs to take into account the risks of any repair process, the risk of variations and loss the lifetime guarantee on the work. I accept that the cost of repairs and quotations provided from various builders will vary and in some circumstances, it will vary significantly. The fact that the applicant’s quotes are significantly higher for the same repairs than the FSP’s quotes does not of itself establish that the quotation was inadequate. The FSP has expressed a willingness to have either AO or PI complete the repairs and provide a lifetime guarantee for those repairs. In these circumstances, I consider PI’s revised quotation represents a reasonable basis for determining the cash settlement amount, subject to any adjustments required to account for the possible variations and risks/contingencies. The cash settlement amount should be based on the reasonable cost of repairs taking into consideration the quotations provided by both the FSP and the applicant. The FSP’s offer of $63,571.28 (including GST) is based on r evised quotations provided by PI plus additional amounts authorised by its assessor for tapware and cleaning costs. The quotations were issued to correct errors (identified by the applicant) which resulted in the inclusion of additional plaster works, plans and permits as well as whitegoods and a bath. The applicant has provided several quotations from his own builders estimating the cost of repairs at between $84,182.40 and $107,937.50. The applicant also believes a further contingency of $7,200 should be allowed to take into account possible Case No: 515036 Determination Page 6 of 8 variations in the event that windows are damaged in the removal/replacement of the reveals. The revised quotation and offer made by the FSP represents a reasonable starting point for determining the cash settlement amount. I am not satisfied however that the offer is adequate for the applicant to be placed in the position he was in prior to the loss or damage. As indicated earlier when making a cash settlement the FSP must do what is fair in all the circumstances and take into account the risks associated with the repair process, the likelihoods of variations and the risk assumed by the applicant in taking over the repair process. FSP is to cash settle building claim for $74,696.25 In my view it is fair that the FSP increase the cash settlement offer by 17.5% ($11,124.97) to take into account the following:  any variations to the scope of works which may be required during the course of the repairs (given such variations are not uncommon where the repairs are extensive, and the FSP would have been liable for any resulting increase in costs, if the repairs had been carried out by its contractors)  the additional risk assumed by the applicant owing to the absence of the lifetime guarantee  the passage of time (including any increase in costs since PI ’s revised quotations were provided). Rounding up the settlement to the nearest dollar brings the cash settlement to the building repairs to $74,696.25. 2.3 Is the applicant entitled to compensation for non-financial loss? Under the Terms of Reference, FOS may award compensation for non-financial loss (capped at $3,300) where an applicant suffers an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the applicant’s expect ation of enjoyment or peace of mind. FOS adopts a conservative approach to the award of compensation and expects applicants to be moderately robust and bear the usual inconvenience associated with an insurance claim. In the current dispute the FSP acknowledges that the claim has not been managed appropriately and its service was less than desirable. Human error had resulted in PI providing an initial quotation based on an incorrect scope of works and it is clear from the information exchanged that but for the applicant’s persistence a number of the items for repair would not have been properly scoped. The applicant acknowledges that the initial claims management and subsequent settlement of the contents claim met his expectations. He maintains however that the conduct for building scoping and quoting fell short resulting in a loss of confidence in the FSP’s ability to repair the property. This according to the applicant is now also affecting his health. Case No: 515036 Determination Page 7 of 8 In addition, the applicant says that his family were unable to enjoy the Christmas period together and whilst the unit was part of a holiday home he intended to make the property available to his recently married granddaughter to help her family start their lives in a positive financial position. I accept that these issues have impacted on the applicant. In my view the FSP’s failure to provide a complete scope of works caused extended delays and resulted in the applicant having to establish what had been overlooked. Whilst the FSP says the applicant did not provide an itemised quotation it has accepted additional repairs where required based on the applicant’s information. I am satisfied the FSP’s management of the claim has caused stress and inconvenience to the applicant and in the circumstances, I consider compensation for $1,500 for non-financial loss is appropriate. Other matters The applicant has also claimed temporary accommodation costs associated with providing accommodation for the family over the Christmas period. Whilst I accept the applicant would have been inconvenienced due to the delays in having the property repaired I do not believe it is appropriate to award compensation for the costs of temporary accommodation. In this respect I note that the property was a holiday home and not the applica nt’s primary residence. The terms of the policy do not extend to providing temporary accommodation benefits in these circumstances. Insofar as the costs were incurred due to the FSP’s poor management of the claim I note that during this time the FSP had offered to commence the repairs. I do not consider it appropriate in the circumstances to award compensation for the temporary accommodation and costs. Case No: 515036 Determination Page 8 of 8 3 Supporting information 3.1 Relevant policy terms About your cover Who we cover - You/Your You/Your refers to the person or persons named as the insured on your certificate of insurance and members of your family who normally live with you at the insured address. Temporary accommodation We do not cover • temporary accommodation costs: [ … ] - if the building was not your principal place of residence at the time of the loss or damage […] What we do not cover - general exclusions (cont’d) You are not covered under any section of your policy for damage, loss, cost or legal liability that is caused by, arises from or involves: Consequential losses or extra costs following an incident covered by your policy consequential loss (financial and non-financial loss) or extra costs following an incident covered by your policy […] […] How we settle building claims If we agree to pay a claim for loss, theft or damage to the building, we will decide if we will: • repair damage to the building; • rebuild the building; • pay you what it would cost us to repair or rebuild the building; […] If we rebuild (or pay yo u what it would cost us to rebuild), we will do so on a `new for old’ basis. If we repair (or pay you what it would cost us to repair), we will at our option do so on a `new for old’ basis or repair to a similar condition to what the building was in befor e the loss or damage occurred. Unless we tell you otherwise, we will deduct any amounts you owe us from any amount we owe you.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.