Home / Financial Firm (Unknown) / Determination 514957

Determination 514957

Fixed fee charged after debt advisory engagement terminated; caveat lodged over property

FirmFinancial Firm (Unknown)
Decided2018-10-23
ProductOther · Other
OutcomeFor the complainant in part
Amount awarded$20,818
Non-financial loss$3,000
Amount claimed$41,635
SourceAFCA PDF

Summary

The applicant terminated a debt advisory engagement and disputed the $41,635 fixed fee and the caveats lodged by the FSP. AFCA found the FSP entitled to half the fee, ordered a refund of $20,817.50, found the PM Property caveat unjustified, and ordered $3,000 non-financial loss.

The agreement was unclear on payment and only part of the work was completed, so AFCA decided a fair fee based on the work done, namely half the fixed fee.

Issues

Subjects and remedies

financial hardshippay interestpay non financial lossrefund fees or chargesrelease security

Related

All Financial Firm (Unknown) determinations · Find similar determinations

Text of the determination

Determination Case No: 514957 Determination Page 1 of 19 Case number: 514957 10 October 2018 1 Overview 1.1 Dispute The applicant entered into an Engagement Agreement (Agreement) with the financial service provider (FSP) on 24 October 2017 to obtain debt advisory services in relation to the liquidation of the applicant‟s company for an Australian Taxation Office (ATO) debt of around $140,000 and other debts of around $1.5 million. The applicant terminated the Agreement on 19 January 2018 and says the FSP did not provide the services for which she paid. The applicant has rejected a preliminary view provided by FOS, on the basis that it did not address many of the claims raised in her correspondence of 12 February 2018 and 5 March 2018. I agree with the applicant that the preliminary view did not address all the claims she has raised, which I will address in this determination. The claims raised are set out in section 2.1 below. I acknowledge that the applicant has put forward significant information in making the claims against the FSP and in rejecting the preliminary view. I have considered all the applicant‟s information, but have only referred in this determination to information considered necessary to determine the claims raised which could potentially have caused a loss. 1.2 Issues and key findings Is the applicant bound by the Agreement she signed? The applicant is generally bound by terms of the Agreement she signed for the reasons set out in section 2 below. Did the FSP provide the services under the Agreement and is it entitled to be paid the fixed fee? Having regard to FOS approach to fairness in all the circumstances, the available the information, the claims made by the applicant, and work completed by the FSP on the ap plicant‟s behalf , the FSP is entitled for the reasons set out in section 2 to charge the Applicant half of the fixed fee. Therefore, if the applicant accepts this determination, the FSP is required to refund to the applicant $20,817.50. Case No: 514957 Determination Page 2 of 19 If the FSP had disclosed certain information to the applicant, is it likely she could have retained T Property? It has not been shown that the actions of FSP affected the sale of T Property for the reasons set out in section 2. Did the FSP fail to tell the applicant it had changed the terms of the sale of T Property agreed to with W bank? Even if the FSP did not tell the applicant about a change to the terms of the sale of T Property, this did not prejudice the applicant and it has not been shown that it caused any loss. Was the FSP entitled to lodge a caveat over T Property The FSP was entitled under the Agreement to lodge a caveat over T Property. Was the FSP entitled to lodge a caveat over PM Property? The FSP was not entitled to lodge a caveat over PM Property for the reasons set out below. The FSP is required to remove the caveat within 14 days of the applicant accepting this determination. The FSP should also pay the applicant non-financial loss compensation of $3,000 for the stress and anxiety this caused. Did the FSP fail to contact the applicant’s creditors? Even if the FSP did not contact all the applicant‟s creditors within the two -week period or at all, there is no information to show that the applicant reasonably suffered a loss as a result. Did the FSP breach the conflict of interest clause under the Agreement when it referred the applicant to JN lawyer? If the applicant was told by JN lawyer that he could not act for her in relation to the caveat lodged by the FSP over T Property, it was open to the applicant to engage the services of another lawyer to represent her. The applicant is not entitled to any compensation in respect to this aspect of the dispute as it has not been shown that this claim led to any loss. Did the FSP engage in inappropriate behaviour towards the applicant? The available information is insufficient to establish a claim for loss against the FSP in this regard. Is the FSP entitled to be paid a “ success fee ” under the Agreement? On the available information, the applicant has no obligation to pay the FSP a “ success fee ” under the Agreement for the reasons set out in section 2. Case No: 514957 Determination Page 3 of 19 1.3 Determination This determination is partly in favour of the applicant. If the applicant accepts this determination within 30 days, then within 14 days of receiving notice of acceptance, the FSP should:  pay the applicant half of the fixed fee being $20,817.50 and non-financial loss compensation of $3,000 (a total of $23,817.50 is to be paid to an account nominated by the applicant in writing with her acceptance)  withdraw the caveat lodged over PM Property and provide the applicant with written confirmation the caveat has been withdrawn. If the FSP does not make the payment within 14 days of notice of acceptance, then the compensation figure will accrue interest at a rate of 3% per annum until payment is implemented. If the applicant does not accept this determination, the FSP is not required to take any of the steps set out above. Case No: 514957 Determination Page 4 of 19 2 Reasons for determination 2.1 The applicant rejected the recommendation The applicant rejected the preliminary view on the basis that it did not address all the claims that she had raised in her submissions to FOS. The applicant has raised the following claims:  the FSP did not give her the opportunity to read the Agreement  the FSP failed to provide the services under the Agreement and is not entitled to payment of the fixed fee of $41,635 (GST inclusive)  because the FSP failed to disclose information about the liquidator possibly agreeing to accept a lesser amount for the ATO debt, this resulted in the sale of T Property  the FSP failed to tell her it had changed the terms of the sale of T Property  the FSP was not entitled to lodge a caveat over T Property  the FSP was not entitled to lodge a caveat over PM Property  the FSP failed to contact the applicant‟s creditors  the FSP breached the conflict of interest clause under the Agreement when it referred the applicant to JN lawyer  the FSP engaged in inappropriate be havior  the FSP is not entitled to be paid a “ success fee ” under the Agreement. 2.2 Is the applicant bound by the Agreement she signed? The applicant is generally bound by the terms of the Agreement The applicant says that she was prevented from reading the Agreement prior to signing it and should not be bound by the Agreement. Generally, FOS accepts that at law if a person signs a document they know will have legal effect, they will be bound by that agreement whether or not they have read it, unless there are some extenuating circumstances such as misleading conduct or illegitimate duress. While the applicant says she was prevented from reading the Agreement, she has not provided any information establishing any form of illegitimate conduct by the FSP in precuring her signature, for example coercion or misleading conduct. In my view, based on the information available, the applicant is generally bound by the Agreement she signed. As stated above, the applicant signed the Agreement knowing that it will give rise to legal obligations, she is therefore generally bound by the terms even if she did not read it. I deal with whether or not the FSP provided the agreed services and the appropriate fee below. Case No: 514957 Determination Page 5 of 19 2.3 Did the FSP provide the services under the Agreement and is it entitled to be paid the fixed fee? The parties have provided different versions of events The applicant says the FSP did not provide the contracted services under the Agreement and therefore she is entitled to a refund of the fixed fee of $41,635 (inclusive of GST) (which she says she paid under protest to settle the sale of T Property). The applicant also says that she is entitled to compensation for losses suffered because the services were not provided as agreed. The FSP says that it prov ided its services properly and it refutes the applicant‟s claims. In this regard, the FSP confirmed in its email of 13 February 2018:  after the engagement, the scope of work increased substantially after discovering the applicant‟s personal company tax returns had not been completed for several years, resulting in a further yet to be quantified ATO liability  the applicant delayed supplying essential information to enable the accountant to perform the initial review and assessment of her matter  there was delay in the preparation of T Property, including listing and auctioning the property and  the FSP developed a statement of financial position, which showed negative equity and further disclosure by the applicant of her liabilities. The FSP says because of the above, its work was rapidly increasing, priorities changed in view of the negative equity position, and the timeframe required to deliver on her desired outcomes was also increasing. The FSP did not provide a project plan FOS asked the FSP whether a project plan was created (as set out in Schedule A, item D of the Agreement). The FSP advised FOS it had not created a formal project plan as it was an optional piece that it decided to omit due to the sense of urgency with the applicant‟s position. While the Agreement does use language to suggest the project plan is optional, FOS is of the view that generally one ought to be produced. Nevertheless, the supporting information submitted by the applicant and FSP highlight various occasions on which they discussed:  the main objectives of the applicant in engaging with the FSP  the priority of work and what would be done  strategies to try to reduce the debt and how that might occur  the urgency of a statement of position and discussion surrounding the drafting of this document  the ongoing work the FSP was doing in relation to the applicant‟s desired outcomes. Although the FSP did not prepare a formal project plan document, it did discuss with the applicant the plans, strategies and objectives it developed to try to manage her debt in an efficient manner. Further, the applicant and FSP were in regular contact Case No: 514957 Determination Page 6 of 19 throughout the term of engagement which is evidenced by the correspondence provided. All discussions pertained to the applicant‟s current position, what information the FSP required from her to carry on its services, and arrangements of meetings. Therefore, although a written project plan was not formulated or provided to the applicant, FOS is satisfied the FSP did carry out certain work for the applicant under the terms of the Agreement including that set out in section 3.3 below, which a formal project plan would have detailed. Some terms of the Agreement are unclear about the payment The applicant says the terms of the Agreement are unclear in that:  the terms of the Agreement are not clear and the fixed fee option was not explained to her. Schedule A states “ [FSP] will provide a proportion of the following services on a per diem basis, or the full services on a Fixed Fee Agreement ” . She cannot see anywhere in the agreement where there is an option to elect a fixed fee  the fee should not be payable because the Agreement sets out a timeframe for completion of services as the settlement of the T Property (16 February 2018), whereas Schedule A sets out the timeframe for completion of services prior to the auction. Further, the FSP did not prepare a Project Plan  Term 3 sets out the completion date and the required payment date as the settlement of the property. However, Schedule A sets out the completion date prior to the house being auctioned (which is misleading and is inco nsistent)  the Agreement was terminated on 19 January 2018 and not 15 January 2018 and settlement of T Property was on 16 February 2018. Therefore, the Agreement was not terminated after the end date referred to in term 3 of the Agreement (term 3 says timing of the payment is upon completion as disbursement at property settlement or similar). The end date is therefore ambiguous. The FSP in contrast says:  a fixed fee arrangement was agreed to by the parties ($41,635 inclusive of GST)  the applicant is liable to pay the fixed fee because she signed the Agreement, which clearly says the fee the applica nt agreed to pay on „property settlement‟  work was commenced in good faith and proceeded based on the fee being paid at the time of property settlement, which a t the time of the Agreement had not been determined and  on termination of the Agreement „ these are similarly clearly defined, payable in full in accordance with the terms, and due at settlement of [T Property]. I note the FSP acknowledges in its email to the applicant of 13 February 2018, “… substantial work did/does remain post [T Property] s ettlement to deliver on your desired outcomes” . I agree that the Agreement is not as clear as it could be in terms of payment of the fee (some of the issues I have identified under the Agreement as giving rise to interpretation issues are set out in section 3.2 below). These, briefly include: Case No: 514957 Determination Page 7 of 19  the Agreement refers to a fee applying on either a fixed or hourly basis  the fixed fee is described as a completion fee and payable on „ As disbursement at property settlement or similar.‟ The Agreement, however, does not describe which property settlement  an early termination fee applying (different to the fixed fee) if the Agreement is terminated early. Although there is a question whether the FSP could have charged an early termination fee, for the reasons explained below I do not have to determine the issue. The fee the FSP is entitled to charge in this dispute should be based on what is fair in the circumstances Under paragraph 8.2 of its Terms of Reference, FOS is obliged to decide a dispute and provide a remedy which in its opinion is fair in all the circumstances. Given the circumstances described above where not all work was completed and the lack of clarity in the Agreement , it is appropriate to decide the FSP‟s remuneration based on what is fair in all the circumstances in this case. It is my view that the FSP has undertaken significant work on behalf of the applicant in relation to her financial affairs between the date of engagement, 24 October 2017, and the date the arrangement was terminated on 19 January 2018. Further information on the services provided is set out in section 3.3 below. It would be unfair for the FSP to have conducted the work it has undertaken for the applicant for free and without payment. Given this approach and having regard to fairness in all the circumstances, the applicant should be held to compensate the FSP for the work it undertook during the above period, so that a fair outcome is achieved. In forming a view as to what is a fair and reasonable fee for the FSP to charge, it is appropriate to consider that the parties intended that the “ fixed fee ” would apply if the services were completed. In fact, the Agreement refers to „completion‟, albeit the applicant chose to terminate the agreement before all the work was completed. However, as acknowledged by the FSP, the work it was engaged to perform was only partly completed. Despite this, the full fixed fee of $41,635 inclusive of GST was charged and paid by the applicant under protest (the fee paid was meant to apply when all work was completed). Having regard to fairness in all the circumstances, the available the information, the claims made by the applicant, the work completed by the FSP albeit only part of the work, the FSP is entitled to charge the Applicant half of the fixed fee ($20,817.50). As a matter of fairness, this represents the total fee due to the FSP (incorporating all fees it could have charged including the fixed fee and early termination fee). Therefore, if the applicant accepts this determination within 30 days, the FSP is required to refund to the applicant $20,817.50. Case No: 514957 Determination Page 8 of 19 2.4 If the FSP had disclosed information to the applicant, could she have retained T Property? It is unlikely that the applicant could have retained T Property? The Applicant says that the FSP sent a letter to W bank on 2 November 2017, saying it was acting for the applicant in relation to T Property and requested details of the loan, such as balance and any arrears. However, the FSP made no attempt to discuss with the bank whether it would agree to provide the applicant with the equity in T Property so she could pay the ATO debt. She also says the FSP did not tell her the liquidator could potentially agree to the ATO debt being dramatically reduced , and this information was not shared until two days after the auction of T Property (so the FSP would get paid its fixed fee from the sale proceeds). The FSP says that the applicant was aware of the proposal to put to the liquidator whether she would be prepared to accept a lower amount for the ATO debt on a commercial basis. Even if I were to accept the FSP failed to inform the applicant of the possibility the ATO debt could be reduced prior to the auction of T Property, I do not accept the bank would have agreed to release to the applicant the surplus funds from the sale of T Property or for the property not to be sold. My reasons for this include:  the applicant owed $1.5 million debt  she was in default of her loan obligations and was not working and therefore not earning an income  W bank held security over the property (for an outstanding debt of $693,894.49 at the time) and had judgment for possession on the PM Property and  it appears, the bank‟s loans were cross collateralized by both security properties. It also appears the applicant had decided to sell T Property before she entered into the engagement with the FSP. In this regard, the applicant has said in her submission to FOS: “ I also provided to you three exclusive authorities for sale which are clearly long before the engagement of [FSP] as well as a contract of sale prepared by my previous lawyer. ” 2.5 Did the FSP fail to tell the applicant it had changed the terms of the sale of T Property agreed to with W bank? Even if the FSP did not tell the applicant about a change to the terms of the sale of T Property, this did not prejudice the applicant In rejecting the recommendation, the applicant says:  the recommendation did not consider her claim that the FSP caused her to breach an agreement with W bank relating to the sale of T Property Case No: 514957 Determination Page 9 of 19  the FSP placed her in a position where W bank lost trust in her because the bank‟s terms for the sale of the property were not met and the FSP did not tell her of the new terms  the FSP did not provide the bank with a copy of the signed contract within the required timeframe. The terms of the sale the applicant refers to is the bank‟s requirement s (which the bank‟s lawyers told the FSP about) that the purchaser pay a 10% deposit and the contract provide for a 60-day settlement. The FSP says:  it had a verbal discussion with the applicant notifying her of the new sale terms . However, it acknowledges it did not confirm this in writing  its objective was to minimise costs that would be incurred if the FSP sold the property  given the applicant was in default of her loan obligations on T and PM Properties, that would likely have created distrust between bank and the applicant in any event. Despite the banks terms, the contract of sale entered into for T Property provided for a 7.5% deposit and a settlement of 90 days. The applicant says because the FSP changed the sale terms, the bank required her to place all proceeds of sale of T Property towards repaying the loan on that property, with the surplus funds paid to reduce the bank‟s loan on the PM Property (to which, she agreed because she was concerned the bank would take PM property). She says that the situation created by the FSP, meant she lost the opportunity to use the equity from the sale of the property to satisfy other debts and finalise her liquidation. She now finds herself in a position where the bank will not allow her to redraw funds under the loan secured by the PM Property loan, even though she has paid more than is required and is ahead with her mortgage. Having reviewed all the available information, e ven if I were to form the view the FSP did not sufficiently inform the applicant of the change to the sale terms, it had no adverse consequences for the applicant. This did not result in the applicant having to sell T Property, nor in the bank deciding not to release to the applicant the surplus funds from the sale of the property. My reasons for saying this are:  the applicant had debts of around $1.5 million (including her company being in liquidation with the ATO chasing a debt of around $140,000) and was in default of her loan obligations with W bank and other creditors  W bank accepted the contract of sale on the different terms and settlement was effected. In fact, the new terms the FSP negotiated likely assisted in a successful outcome for all parties involved in the sale  the applicant was in default of her obligations under her loans with the bank. The e mail by W bank‟s lawyers to the FSP dated 13 November 2017 , says the loan balance at 7 November 2017 (excluding any outstanding costs) on T Property loan was $730,768, with arrears of around $58,000 Case No: 514957 Determination Page 10 of 19  the bank had court orders relating to its security. In relation to this, the applicant has said W bank had obtained judgment for possession of PM Property, and she accepts that ' … it cannot be through the fault of [FSP] that judgment was made'. Therefore, payment of funds to the loan was critical. In my view, the information shows that the applicant had no choice but to sell the property, and the bank required payment of funds be made to both loans. The applicant is not entitled to further compensation The applicant says she is entitled to further compensation as she has suffered loss because of the FSP‟s actions discussed above. The losses she claims are:  the lost opportunity to use the equity from the sale of the property to satisfy other debts and finalise her liquidation  the sale of T Property worth around $950,000  loss of rental income of $38,000 per annum derived from T Property  costs and fees associated with selling the property (real estate agent fees $22,282.50 and legal fees of $1,488.67)  costs of improving the property for sale of $25,000. Given that I have found that the FSP did not breach any obligation it owed the applicant in this regard, she is not entitled to any compensation. I also do not accept the applicant ‟s claim that because she was unable to finalise the liquidation because of the FSP‟s actions, she could not renew her practicing certificate and this resulted in loss of income of around $1,400 per month from the date T Property was sold. 2.6 Was the FSP entitled to lodge a caveat over T Property? The FSP had a right to lodge a caveat The FSP lodged a caveat over the applicant‟s property to ensure it was paid the fixed fee. The applicant says she only paid the fixed fee under protest after the FSP refused to agree that the fee would be paid into her solicitor‟s trust account after settlement of T Property, until the dispute about the fee was resolved. The FSP says it would not have lodged a caveat if the applicant had agreed to sign an authority saying the fee would be paid to the FSP at settlement of T Property. Based on the available information, the FSP had a right to lodge a caveat under the charge clause in the Agreement based on the fee it claimed. Case No: 514957 Determination Page 11 of 19 2.7 Did the FSP breach the conflict of interest clause? The applicant has not shown she has suffered any loss in relation to this claim The applicant says:  the FSP breached clause 5 of the Agreement which relates to „No Conflict‟ when she was referred to JN lawyer to act for her in relation to the sale of T Property  the lawyer said he could not provide any advice to her in relation to the FSP‟s lodgment of the caveat over T Property, because of his relationship with one of the FSP staff members  she was prejudiced by this situation as she could not afford another lawyer. I do not accept that the applicant suffered any prejudice even if the FSP should not have referred her to JM lawyer because of a relationship that existed between a FSP staff member and the lawyer. If JN told the applicant he could not act for her in relation to the caveat issue because of his relationship with a FSP staff member, it was open to the applicant to engage the services of another lawyer to represent her interests. In addition, the information shows that she could not have altered the course of events in any case regardless of representation. The applicant is not entitled to any compensation in respect to this aspect of the dispute and it has not been established she incurred any loss as a result. 2.8 Did the FSP represent to the applicant that it would act as her legal adviser? The information does not show the FSP represented it would act as the applicant’s lawyer The applicant says:  she entered into the Agreement, because she was misled by the FSP to believe it would act as her lawyer  the FSP failed to provide her with „advice regarding the liquidation of my company‟, which the applicant says was what she wanted and this was made clear in her text message to a FSP staff member leading up to the initial meeting. She was therefore left with the impression that the FSP was providing legal advice and representation on the liquidation of her company  the FSP left the liquidator, B Finance ‟ s lawyers and W bank with the view that it was acting as the applicant‟s lawyers. Correspondence provided by both parties shows the FSP disclosed it was not acting as her lawyer. The FSP also advised (to a third-party creditor and the applicant) that it will not be accepting service on her behalf in an email dated 2 December 2017: “ You may also wish to provide us a copy of the Complaint in this matter. However, we confirm that we are not acting as solicitors for [applicant] and are not able to accept service of the Complaint on behalf of her” I don‟t have any documents yet but will ask for them from the solicitor (I won‟t accept service on your behalf though). ” Case No: 514957 Determination Page 12 of 19 The terms of the Agreement also make clear that the FSP will be providing debt management and advisory services and no mention is made of legal services. There is no information to show the FSP misled the applicant or other parties about its role as the applicant‟s lawyer . Even if I were to accept the FSP did so (which I do not accept), the applicant has not shown what loss she has suffered because of this claim. 2.9 Did the FSP engage in inappropriate behaviour towards the applicant? There is insufficient information to establish the applicant’s claim The applicant says two FSP staff members engaged in inappropriate behaviour at a meeting on 6 December 2017, namely she was subjected to a conversation between two FSP staff members about „sexual encounters the previous evening‟ by one of them. The applicant also says:  she “ felt physically sick at the disgusting way these two men behaved. It was unprofessional and completely unacceptable behavior ”  the FSP should pay her non-financial loss compensation  the behavior prevented her from being able to meet with the staff member to try and resolve their dispute. The FSP denies the discussions took place. FOS is a dispute resolution service whereby we can review claims about a member which has led to a loss by its customer. FOS is not a court and cannot cross examine parties in a dispute or call on third parties to give evidence. FOS does not review customer service issues as such issues relate to the member‟s practice and policy and will generally reflect staff training and other matters. Such matters are more appropriately dealt with by the member. In the absence of any further information, I am unable to form the view about the discussion that took place or whether any action that the FSP has responsibility for would warrant compensation. 2.10 Did the FSP fail to contact the applicant’s creditors? The applicant says the FSP’s failure to contact other creditors caused a loss The applicant says the FSP:  contacted four creditors within the two-week time frame as set out in the Agreement, namely the liquidator, W bank, PP Council and City of D. However, it failed to contact other creditors within the required time frame  failed to contact A bank, her body corporate and YV Water at all  potentially caused her a loss due to its inaction. Case No: 514957 Determination Page 13 of 19 Information about the YV water charges does not establish a loss The applicant says:  she had to pay $6,500 to YV Water, for which she was not responsible. The amount was allegedly for her previous tenant‟s water usage on T Property  the FSP was aware she was disputing this amount with YV Water, but it failed to act on this debt or dispute  because the FSP did not contact YV Water at all to negotiate an outcome, this weakened her position in the dispute, even though she attempted to contact YV Water on the settlement day of T property. However, YV Water was not prepared to negotiate at such late notice. Taking into account all the available information, even if I were to form the view that the FSP failed to contact YV Water, I cannot be satisfied that any negotiations with this organisation at an earlier point in time would have resulted in an agreement to accept a lower debt amount. FOS is not able to award compensation based on a position of speculation. Accordingly, it has not been shown that the applicant incurred a loss in relation to this claim. It has not been established the FSP caused a loss relating to the bank overdraft The applicant says:  the FSP told her that as part of their service, it would contact A bank and “… have the debt dramatically reduced. They did n ot contact them at all” .  she has suffered a loss of around $ 10,000 “ in additional fees and charges by the debt collection agency that my overdraft was sold to by [A bank] ” ‟ and says the FSP should be responsible for the debt. The applicant has provided no information to support her claim as set out above or the basis of the calculated loss. In my view, the applicant‟s claim for loss is speculative and therefore does not warrant any payment of compensation at FOS. Even if I were to form the view that the FSP failed to contact A bank, I cannot be satisfied that any negotiations with this bank would have resulted in an agreement not to cancel the facility, reduce the debt owing, or the bank deciding not to assign the debt to another party who is now seeking recovery from the applicant. It has not been shown the body corporate fees would have been reduced The applicant says the FSP did not contact her body corporate about fees of $6,828.77 for which she was being pursued. Even if I were to form the view that the FSP failed to contact the body corporate at the time, I cannot be satisfied that any negotiations with this organisation would have resulted in an agreement to accept a lower debt amount. Any such claim is based on speculation and cannot form the basis of any compensation at FOS. It is also the case that the applicant did have the opportunity to atte nd the VCAT hearing and put forward her arguments as to why she believed she was not liable for Case No: 514957 Determination Page 14 of 19 the full debt claimed by the body corporate. Although she says that she was unable to do so because she was “ suffering as a result of the conduct of [FSP] ‟”, t hat is a claim that would require expert medical evidence and is more appropriately dealt with in a court. The FSP did not cause any loss in relation to the B Finance debt The applicant says:  the FSP mishandled the debt she owed B Finance  if the FSP had done this job properly and looked at the loan documents and court documents, it would have seen that the payments that were dishonored by B Finance were in fact not taken on the day the loan contract allowed and she was not in breach of the contract  if the FSP had not represented themselves as acting as the applicant‟s lawyers, B Finance would not have contacted the FSP. The applicant seeks compensation for this ordeal by requesting that the FSP pay out the debt under the B Finance loan contracts. The FSP says that they were informed that the applicant was disputing money owed and claimed by B Finance and while the applicant promised many times to provide detail and documentation to support her claim, this was not received despite repeated requests. A review of the information shows:  the FSP wrote to B Finance ‟ s lawyers by email dated 2 December 2017, saying that they were instructed to act on behalf of the applicant and requesting copies of loan contracts, demands issued and debt balance  the FSP sent an email to the lawyers of 31 January 2018, saying they were „finally able to get in touch with the [applicant] ‟ but she no longer wishes for them to act for her  the FSP sent the applicant a SMS dated 18 January 2018, which says „.… the solicitors fo r B Finance are chasing a response ASAP. I‟ve sent you an email. Please call me.…‟ In my view, the information available does not show the FSP represented to B Finance that it was acting as the applicant‟s lawyer. The above email makes no such reference and refers to „SD Advisory‟. Nor do I accept the applicant‟s claim that the FSP conduct created an ordeal for which the FSP should be responsible to pay the applicant‟s debt to B Finance. 2.11 Is the FSP entitled to be paid a “ success fee ” under the Agreement? The FSP is not entitled charge a “ success fee ” and should not have lodged a caveat over PM Property The FSP says it may be entitled to a success fee of 25% of the amount by which the ATO debt is reduced. Case No: 514957 Determination Page 15 of 19 The applicant does not accept she is liable to pay any “ success fee ” to the FSP and says that she negotiated any possible reduction in the ATO debt with the liquidator and not the FSP. In general terms, the Agreement says that the FSP may be entitled to a “ success fee ” representing 25% of any reduced debt amount the FSP negotiates. The FSP has provided a file note dated 26 March 2018, setting out certain discussions with Ms M who appears to work in the liquidator‟s office. The discussion of 18 December 2017 confirms the approximate amount claimed by the ATO and refers to the option of the applicant making an offer to the liquidator on a commercial basis ( “ discussed (without prejudice basis) liquidator considering an offer of $50,000 ” ). While the file note is dated 26 March 2018, it refers to many conversations during 27 October 2017 and 20 December 2017, between the FSP and Mrs M. It appears the file note is not contemporaneous. The FSP says, based on its right to be paid a success fee, it lodged a caveat pu rsuant to the charge clause under the Agreement over the applicant‟s PM Property. I have reviewed an email from Ms M dated 26 March 2018 to the applicant, which largely says that on 18 December 2017 she discussed the matter with the FSP (Mr NB) and he indicated that an offer to settle the debt may be made and he undertook to come back to her by 12 January 2018, but this did not happen. In my view, the FSP is not entitled to recover any “ success fee ” in these circumstances because there is no information that shows the liquidator has agreed to accept a reduction of the ATO debt. Whether or not the ATO debt is ultimately reduced is speculative and if the liquidator agrees to reduce it, will require renewed discussions and negotiations based on the circumstances at the time (including, the applicant‟s financial position ). As such, any discussions the FSP may have had with the liquidator about the debt reduction are unlikely to form the final bases of any negotiated reduction i n the ATO debt. It follows the FSP has no valid basis to retain the caveat it has lodged on the PM Property, and it should be removed if the applicant accepts this determination. The applicant says the FSP ‟s lodgement of the caveat over PM Property has ca used her financial loss because she has not been able to refinance her remaining loan with W bank over PM Property. The applicant, however, has not provided any information to support her claim. I cannot therefore accept this claim and the applicant is not entitled to any financial loss compensation because the FSP lodged a caveat over the property. However the lodgement of the caveat by the FSP over PM Property would have likely caused the applicant stress and anxiety, for which the FSP should pay the applicant $3,000 by way of non-financial loss compensation. Case No: 514957 Determination Page 16 of 19 3 Supporting information 3.1 Some terms of the Agreement The Agreement says the applicant engaged the FSP to provide debt management and advisory services, which services included discussing available options and forming a project plan to deal with the outstanding debt as well as liquidation action. The FSP agreed to coordinate action and 'engaged' with creditors and other third parties that were relevant to the applicant‟s financial SCHEDULE A SERVICES PROVIDED (FSP) will provide a proportion of the following services on a per diem basis, or the full services on a Fixed Fee Arrangement: Service Description Anticipated Period to Complete a) Initial Phone Meeting t o review financial position and state of affairs; Preliminary discussion and assessment of your circumstances Provided on or about the date of this Engagement Agreement. b) Discovery; c) Engagement with Credit Provider(s) and other relevant parties Engagement with Credit Provider(s), introduction, preliminary negotiation of terms Engagement with relevant parties (incl. RE Agents, lawyer/convey ancer, mortgage brokers, discussions with Superannuation Fund), options. Two (2) weeks, by Fri 3/Nov/17 d) Preparation of a 'Project Plan' bas ed on option(s) (may be required) - and exec ut e Agree preferred option(s); Negotiate with Credit Provider(s); Documenting negotiated terms for settle; Project Plan - documenting tasks, responsibility and timeframes Eight (6) weeks, by Fri 15/Dec/17 e) Monit or and administration of the Project Plan Co - ordination of disbursements to Creditor(s) on terms negotiated Included within above f) 'Closing Summary' of outcomes achieved Reconciliation of account with Credit Providers (and others) Included within above Total Estimate To possible Property Contract Exchange (excluding any settlement period) Eight (8) weeks, Fri 15/Dec/17 3.2 Some interpretation issues with the Agreement Clause 2 of the Agreement says that upon acceptance of the Agreement, including payment of the Engagement Fee, the FSP will provide the services as outlined in Schedule A. It also says: Case No: 514957 Determination Page 17 of 19 “Anticipated Period to Complete‟ is an estimated time only and that while the FSP will endeavour to achieve this timing, it has relied upon information and involvement from you, your credit providers and other parties or advisers as may be engaged from time to time, and cannot be held responsible for any delay. ” Clause 3 refers to a total fee of $37,850 (excluding GST) and Schedule A Services Provided, says „[FSP] will provide a proportion of the following services on a per diem basis, all the full services on a Fixed Fee Arrangement.‟ The standard terms of the agreement define „Per diem‟s fees (if applicable) will accrue based on a standard eight (8) day on a minimum 15 minute incremental.‟ However, no other relevant information is provided in relation to this basis of charging on an hourly basis (e.g. hourly rate). It is unclear under the terms of the Agreement in what circumstances the FSP will provide some of the services described in Schedule A on a per diem basis or the full services on a fixed fee basis. The fixed fees were described as a completion fee and payable on „As disbursement at propert y settlement or similar.‟ The A greement, however, does not describe which property settlement and what has occurred is that the fixed fee was paid before „completion‟ of all the work by the FSP under the Agreement. The standard terms of the Agreement say that a fee is also payable prior to completion of the services and defines: “ early termination fee means the fee payable (plus GST) at the date of any termination of this agreement prior to completion of the Services, calculated as the „Total Fee‟ minus any paid „Fees‟ as specified in the letter of engagement, multiplied by the actual duration of Services (in weeks) as a ratio of the total anticipated duration of Services (in weeks) as determined from the Letter of Engagement (whereby the ratio is not to exceed a factor of one). ” The Agreement also says that upon termination of the agreement prior to completion of the services, the client agrees to immediately pay the FSP the early termination fee, plus out of pocket expenses. The relevant clause then goes to say, „for the purposes of clarity, the client is required to pay either the full total fee, as specified in the letter of engagement or the early ter mination fee, plus expenses.‟ 3.3 Some services provided by the FSP under the Agreement The available information shows the FSP did provide debt and advisory services. Correspondence provided by both parties shows:  the FSP‟s initiation of negotiations with the ATO court appointed liquidator  the FSP‟s preparation of a statement of position based on the information provided by the applicant (albeit the statement remained in draft because the FSP said it was an „evolving‟ document given the applicant‟s circumstances)  several discussions and meetings set with the applicant and her accountant  the FSP‟s negotiations with W bank, which ultimately led to the sale and settlement of T Property  the FSP arranging independent appraisals of T Property and meetings with the agent Case No: 514957 Determination Page 18 of 19  the FSP provided information and referrals in relation to several possibilities for dealing with the debt, including sale of T Property  the FSP dealt with several creditors and solicitors representing creditors on behalf of the applicant  the FSP dealt with the liquidator. 3.4 Some key dates Date Action 24 October 2017  The applicant entered into an engagement agreement. It was signed by both parties and a witness on the same day (24 October 2017).  Page 2 of the agreement states the total service fee the FSP charges to be $37,850 (plus GST)* in bold lettering 24 October 2017  The FSP contacts third parties and creditors providing authority to act on behalf of applicant 26 October 2017  The FSP orga nis es property appraisals for applicant 2 November 2017  The FSP refers the applicant to a solicitor to prepare contract of sale on applicant‟s investment (T Property) 14 November 2017  The FSP prepared a draft proposal 29 November 2017  The FSP repres ents the applicant and liaises with a creditor‟s solicitors in various email communications 2 December 2017  The FSP advises the applicant about possible courses of action in relation to debt with above creditor 4 December 2017  The FSP negotiates with a second creditor in relation to withholding action to enforce its judgment to allow auction to proceed 19 January 2018  The applicant sends the FSP an email highlighting for the first time her inc reasing concern  The applicant ter minates the Agreement in this email 25 January 25 2018  The FSP sent the applicant an email expressing surprise and requesting to meet to discuss as it does not want the Agreement terminat ed 5 February 2018  As the applicant did not respond, the FSP sent a follow up email acknowledging the termination and attached its full invoic e  The invoice refers to the fee due and payable to be its „full fee‟ 7 February 2018  The applicant responded alleging a complete lack of service and multiple breaches of Agreement  The applicant advised she will not be paying the invoic e 8 February 2018  The FSP lodged two caveats on both properties (T and PM) 12 February 2018  FOS dispute lodged Case No: 514957 Determination Page 19 of 19 16 February 2018  The applicant paid the full invoice as the settlement of the T Property occurred on this day and it would not be successfully settled if it remained encumbered  The FSP refused to withdraw the caveat on PM Property 26 March 2018  The FSP made an offer to withdraw the caveat provided applicant withdrew the FOS d ispute and signed release 27 March 2018  The applicant rejected the offer as believes she paid the sole invoice in full and the FSP does not have standing to keep the caveat on PM Property

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.