Applicants claimed for bathroom damage from wind-driven rain. The FSP first blamed a leaking shower screen, then said gradual deterioration caused the damage. AFCA found the damage was excluded, but ordered the FSP to reimburse expert report costs and pay $500 non-financial loss.

Damage from gradual deterioration is excluded under the policy, but the FSP's incorrect contractor findings forced the applicants to obtain their own expert reports.

Issues

Subjects and remedies

home or building damagepay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 514662 Determination Page 1 of 4 Case number: 514662 31 July 2018 1 Overview 1.1 Dispute The applicant lodged a claim under his home insurance policy with the financial services provider (FSP) for damage to his en suite bathroom. The applicant considers the damage was caused by wind driven rain. The FSP initially denied the claim on the basis that the damage was caused by water leaking from a shower recess. The FSP now says the damage was caused by wear and tear and gradual deterioration over time. The applicants dispute the FSP’s decision and seek cover for the cost of repairing the damage to the bathroom. 1.2 Issues and key findings Is the FSP liable for the damage to the bathroom? The available information establishes that the water damage to the bathroom was caused by gradual deterioration, which allowed wind driven rain to enter around the window frame during regular rainfall events. The policy does not provide cover for damage caused in this manner. Accordingly, the FSP is not liable for the damage. Are the applicants entitled to compensation? The applicants are entitled to compensation because they were required to engage their own experts to establish that the initial findings of the FSP’s contractors (that the shower was leaking) were incorrect. 1.3 Determination This determination is substantially in favour of the FSP. The FSP is not liable for the damage to the bathroom. However, the FSP is required to:  reimburse the applicant for the costs incurred in obtaining AC’s report dated 17 August 2018 and RK’s report dated 11 August 2017, subject to provision of appropriate invoices, and  pay the applicant the amount of $500 as compensation for non-financial loss. Case No: 514662 Determination Page 2 of 4 2 Reasons for determination 2.1 Is the FSP liable for the damage to the bathroom? Policy provides cover for storm damage subject to exclusions The applicant ’ s policy provides cover for damage caused by the events listed in the policy, including the insured event of storm. However, the policy contains general exclusions for damage which is caused by gradual deterioration or wear and tear. The policy also states that the FSP will not pay for damage caused by the applicant failing to maintain his home in good repair and condition (that is, keeping it watertight, structurally sound, secure and well maintained). Damage was caused by water entering through bathroom window As outlined above, the FSP initially denied the applicant ’ s claim on the basis that the damage had been caused by water leaking from the shower screen. The FSP based its denial on reports provided by its builder (JP) and plumber (PB), who advised that they had carried out spray tests which showed that the shower screen was leaking. The applicant disputed the FSP’s denial and engaged his own plum ber (AC) and architect (RK). Both AC and RK advised that wind driven rain was entering the bathroom around the timber window frame. The FSP’s plumber (PB) re -attended the property and carried out further tests which confirmed that the shower screen was not leaking. PB agreed that water was entering through the bathroom window frame. Damage was caused by gradual deterioration In his submissions to FOS, the applicant advised that water entered the bathroom during periods of heavy rain or storm. The applicant ’ s engineer (RK) has confirmed that water has seeped in over time during periods of extreme rainfall, gradually causing deterioration of the surrounding areas. The FSP says that the unsealed gaps around the bathroom window has allowed water entry into the wall cavity causing the damage observed. The FSP’s builder (PB) advised there were gaps around the window frame and splits in the timber. However, the applicant’s architect ( RK) advised that:  there is no requirement for sealant between the window render and the brickwork, and  window frame jambs should be installed to abut the brickwork with tolerance for differential movement between dissimilar building materials. Case No: 514662 Determination Page 3 of 4 RK advised that the applicants’ window was in good condition and capable of withstanding the external elements. However, this is not consistent with his advice that water is entering around the window (ie it is not watertight). Further, photographs of the window frame clearly show that there are visible gaps at the junction between the window frame and the wall, indicating that the frame no longer abuts the brickwork. There are also signs of deterioration to the timber. Based on the available information, I am satisfied that the water damage to the bathroom has occurred over time, as a result of gradual deterioration which has allowed wind driven rain to enter during regular weather events. FSP is not liable for damage For the reasons outlined above, I consider the damage to the bathroom was caused by gradual deterioration. The policy excludes damage caused in this manner. Accordingly, the FSP is not liable for the damage. 2.2 Are the applicants entitled to compensation? FOS may award compensation Under the Terms of Reference, FOS may award compensation (capped at $3,300) for consequential loss suffered by an applicant in connection with their claim. FOS may also award compensation (capped at $3,000) for non-financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind. Applicants are entitled to compensation As outlined above, the FSP now accepts that the damage to the bathroom was caused by water entering around the window frame and not by a leak from the shower screen (as initially advised by its contractors). The applicant engaged his own plumber (AC) and architect (RK) in order to dispute the initial findings of the FSP’s contractors. This has prolonged the claim and caused the applicant additional stress and inconvenience. In the circumstances, I consider the FSP should be required to reimburse the applicant for the costs incurred in obtaining AC’s report dated 17 August 2018 and RK’s report dated 11 August 2017, subject to provision of appropriate invoices. The FSP is also required to pay the applicant the amount of $500 as compensation for non-financial loss. Case No: 514662 Determination Page 4 of 4 3 Supporting information 3.1 FOS approach to this dispute This dispute was the subject of a recommendation issued on behalf of the Financial Ombudsman Service (FOS) Australia on 18 May 2018. The recommendation was rejected by the applicants. This dispute has been determined based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. All of the material provided by the parties has been reviewed and considered (whether or not it is expressly referenced in this determination).

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.