Home / Financial Firm (Unknown - Insurer) / Determination 513961

Determination 513961

Refusal of water ingress damage claim following burst water main

FirmFinancial Firm (Unknown - Insurer)
Decided2018-06-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed for water ingress damage in March 2017 after a 2016 burst main, and the FSP refused it because causation was unproven. AFCA found a prima facie claim, ordered the FSP to meet the claim unless it commissions invasive testing at its own cost with make-good, and gave no figure.

Once the applicants establish a prima facie claim the insurer must establish an exclusion, and it is unfair to require the insured to bear the cost of investigation given the uncertain cause.

Issues

Subjects and remedies

home or building damagepay claimrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 513961 Determination Page 1 of 8 Case number: 513961 19 June 2018 1 Overview 1.1 Dispute The applicants hold a defined events policy of insurance with the financial services provider (FSP) covering a residential building for $318,000. On 13 and 14 June 2016 a main water pipe burst behind the back of the home releasing 102,000 litres of water which caused water inundation to the building. The FSP accepted the claim and made payment. The applicants say this was accepted on the proviso that if additional damage was found due to the claim the FSP would also make payment for same. Works to repair the building were completed on 2 August 2016. On 30-31 March 2017 300mm of rain fell over a 48-hour period inundating the ground floor. The FSP declined the further damage on the basis the applicants have not established the reported water leak relates to the original claim. The applicants say this leaking membrane was damaged by the prior event in 2016 and seek payment from the FSP for the current damage. 1.2 Issues and key findings Is the FSP entitled to refuse the applicants’ claim? The panel is satisfied that the applicants have established a prima facie claim under the terms of the policy. However, it is fair in the circumstances that the FSP be given the opportunity to arrange an independent engineer/building consultant to conduct invasive investigations to determine the cause of the leak. Such investigations must be at its cost including reinstatement following the testing irrespective of the outcome. 1.3 Determination This determination is substantially in favour of the applicants. If the FSP seeks to investigate this claim further, then it must within 30 days of acceptance of this determination appoint an independent engineer/building consultant to undertake relevant invasive investigations at its cost, including the make good of any damage incurred during those invasive investigations, irrespective of the outcome. At that time, the FSP can make an informed decision based on the independent engineer/building consultant’s opinion. Otherwise the FSP is to me et the applicants ’ claim as per the terms of the policy. Case No: 513961 Determination Page 2 of 8 Case No: 513961 Determination Page 3 of 8 2 Reasons for determination 2.1 Is the FSP entitled to refuse payment of the applicants’ claim? The policy provides cover for escaped water subject to exclusions The policy provides cover for water which has escaped from a water main or fixed pipe. The cover is subject to exclusions but the FSP is not relying on these exclusions. The FSP says the applicants have not established the damaged water proof membrane relates to the original claim. The parties agree that the wall had been subject to over 100,000 litres of water The FSP and the applicants agree that in June 2016 a water main burst and released approximately 102,000 litres of water which inundated the home. The parties agree that the FSP settled the damage to the home arising from the water ingress. The claim settlement was based on the scope of works provided by builders. It appears that one of the FSP’s experts, (ASB), noted the water proof membrane may have failed. The FSP paid the claim but it is unclear whether the applicants were notified of this potential issue. No destructive testing was undertaken by either the FSP or applicants during the original claim. The parties agree that water ingress occurred after heavy rain in March 2017 The parties agree that water ingress occurred after heavy rain in March 2017 causing damage to the insured building. The experts do not agree on the cause of damage to the water proof membrane The following expert opinions were provided:  ASB stated water had penetrated the waterproof membrane of the relevant wall due to the burst pipe. However, it believed that the wall was not adequately waterproofed as water had seeped through. The email with this report indicated a lack of certainty and this is likely due to a lack of destructive testing to confirm.  (S) could not conclusively determine if the failure of the membrane was due to the burst pipe or gradual deterioration. S was of the opinion that the membrane had exceeded its life expectancy but destructive testing was required to confirm.  (Q) had the benefit of exposing the top of the existing water proof membrane and its protective sheeting. Q deemed the membrane to be in good condition and without weathering or deterioration. Q believes the membrane was performing as designed but after 100,000 litres of water penetrated the rear wall it either compromised the water proofing or structural integrity of the masonry wall. Q also believed destructive testing was required to confirm the opinion. Although the applicants’ expert Q considered the damage sustained in June 2016 due to the water leak may have compromised the waterproofing or structural integrity of the retaining wall, Q considered that destructive testing would be required to confirm this. Q provided a quote to conduct such destructive testing which included:  removal and reinstatement of a site fence Case No: 513961 Determination Page 4 of 8  cap off all plumbing and electrical points  deconstruction and reconstruction on completion of works of the rear verandah  excavation of a trench, the entire length of the rear elevation of the home to allow sure up of the trench and allowing for a safe work area  clean up the masonry wall to expose the waterproof membrane for inspection purposes  engaging of expert consultants to report and  removal of all excavation material. The quote provided was for $49,775.25. Additional evidence indicates no water ingress or leaks existed in 2015 The pre-purchase inspection reports and pest inspections indicate that no evidence of water ingress or pests attracted to water such as termites were discovered. The available evidence suggests that in the 14 months prior to the damage the water proof membrane was functioning adequately. The evidence from the applicants is that during moderate to heavy rain that water ingress now occurs. It appears unlikely that the water proof membrane experienced a s udden deterioration within 14 months without an external influence. This is particularly given the evidence of Q who noted the uncovered membrane appeared to be in good condition. Q believed hydrostatic pressures resulted in the damage to the water proof membrane rather than deterioration. S also considered it a possibility that the burst pipe could be responsible for the failure but due to the home’s age considered it more likely it had deteriorated. S did not have the benefit of exposing the membrane tha t Q did and accordingly the evidence of Q is preferred. Based on the evidence provided, the applicants have established a prima facie claim that the water proof membrane has been damaged by the burst water pipe. Unfair in circumstances for applicants to bear costs of investigation The panel accepts that the applicants have established a prima facie claim under the terms of the policy although the panel is concerned that the exact cause of the damage has not been properly identified. The available information suggests that the events of June 2016 have compromised the waterproof membrane or alternatively caused structural damage due to hydrostatic pressure to the masonry wall. Alternatively, the water proof membrane may have deteriorated over time, in particular given the building was 50+ years old. The panel notes that the FSP offered to arrange for invasive investigations of the applicants’ property. It offered to undertake an invasive assessment of the wall to determine the cause of damage to the waterproofing membrane. It did so on the basis that if the assessment identified that waterproofing membrane has exceeded its life expectancy, that the damage caused by the invasive testing would not be Case No: 513961 Determination Page 5 of 8 covered by the FSP. In the circumstances of this particula r dispute, the panel does not consider this fair. The panel considers it is fair that if the FSP is to investigate this claim further then the FSP should do so at its own cost. If the FSP is to investigate the claim further then it should appoint an independent engineer/building consultant to undertake the relevant invasive investigations at its cost. The FSP should be responsible for any damage caused by the invasive testing and the reinstatement of the property irrespective of the outcome. Once the FSP has received the relevant report it must then make an informed decision based on the observed facts. If the FSP elects not to conduct the invasive testing then it is to meet the applicants claim for the damage sustained. Case No: 513961 Determination Page 6 of 8 3 Supporting information 3.1 Relevant Policy provisions “ Your building and/or contents are covered for loss or damage caused by the sudden and unexpected escape of liquid from any: • water main; • fixed water pipe (but not a garden hose); .. What is not covered You are not covered under this Insured Event for: • loss or damage caused by any escape of liquid of which you were aware and failed to notify us of within a reasonable period; • loss or damage resulting from a leaking or faulty shower recess or shower base; • loss or damage caused by any gradual escape of liquid; .. • exploratory or restoration costs if we have not accepted a claim under this Insured Event. Your building and/or contents are not covered under this Insured Event for loss or damage as described in the General Exclusions listed on pages 75 to 78. ... Under this policy there is no cover provided for any loss, damage or liability caused directly or indirectly by or in any way connected with: .. Wear and tear and lack of maintenance, including rust, corrosion and deterioration (except in some instances relating to the Insured Events ‘Escape of liquid’ and ‘Legal liability’ claims); ” 3.2 Expert Reports The following expert reports have been provided: Record Key points A pplicants’ expert (T) Pre - purc hase report 30 April 2015  The report located no defects/safety hazards found.  There were no defects/safety hazards found in the surface water drainage. A pplicants’ expert (VT) Pest inspection 30 April 2015  Landscape timbers showed some signs of fungal decay  There were no visible leaks located which might attract termites.  All the moisture readings were normal at the time of inspection. Rainfall records 1 - 2 May 2015  The rainfall records indicate the property had been subject to heavy rainfall previously. Case No: 513961 Determination Page 7 of 8 4 - 5 June 2016 30 - 31 March 2017 23 - 24 February 2018  On 1 May 2015 the rainfall recorded was 48.8mm.  On 2 May 2015 the recorded rainfall was 165mm  On 4 June 2016 the recorded rainfall was 72.5mm  On 5 June 2016 the reco rded rainfall was 125mm  On 30 March 2017 the recorded rainfall was 125mm  On 31 March 2017 the recorded rainfall was 175mm  On 23 February 2018 the recorded rainfall was 66. 2mm  On 24 February 2018 the recorded rainfall was 138mm Leak Detection Test Report 29 June 2016  No leak was found to either the water supply lines or stormwat er lines.  No agricultural drainage pipe work at the base of the retaining wall through which we could conduct a camera inspection. However, a small cut out at the base of the wall and large stones in behind the wall. There may be an agricultural drain behind that point but it could not be confirmed.  There were definite signs of water flowing from the retaining wall through the cut out indicating the area is draining as intended. FSP Expert ASB Report 30 June 2016  The burst pipe caus ed water to seep through the double brick retaining wall of the house in the lower storage room, flooding a section of the floor area and resulting in damages.  Water has penetrated the waterproof membr ane of this wall due to the burst pipe, however in our opinion if this wall was proofed adequat ely seepage would not occur.  A scope of works estimated works in the sum of $5,596.80 which excluded cover for the retaining wall.  An email dat ed 30 June 2016 sending this report to the FSP indicates in bold and underline “As the recommendation on this claim is UNSURE – we will await your authority prior to proceeding with any insurance repairs at the above property”. This may refer to the fact an engineer had n ot viewed the property and no destructive testing was conducted to verify the opinion. Email from FSP expert ASB 12 April 2017  ASB re - states a previous opinion that the retaining wall had not been waterproofed adequately and allowed water ingress.  If this has occurred again then any other similar claims including storm would be declined in their opinion due to the membrane failure.  ASB were of the opinion that water ingress would continue to occur at the brick retaining wall until a sufficient memb rane is installed which would cost approximat ely $20,000 FSP’s expert (S) Building Consultant Report 7 July 2017  After the storm event on 31 March 2017 moisture was observed seeping from the Sout h facing double brick garage and storeroom.  S discussed the prior repair work to the mains pipe and believes that no work was done that could have damaged the retaining wall or membrane.  S recorded elevated moisture levels considered to be consistent with water ingress as described by the applicant s. Case No: 513961 Determination Page 8 of 8  S noted that a leak detection report indicated no issues with the main water supply, and that ground wat er was the likely source of inundation.  S noted the caus e of moisture ingress through the Southern brick wall garage and adjoining storeroom is a r esult of failed waterproof membrane system. S could not conclusively determine if the failure of the membrane was the result of the burst pipe or due to gradually deterioration given the concealed nature of the membrane. S is of the opinion that the membr ane has exceeded its life expectancy.  A scope of works provided by S includes works to the retaining wall including new water proof membrane. S also considers that the condition of the retaining wall to ens ure there is no damage to the wall or slab edge s hould be reviewed. The scope also allows for the installation of an agricultural drain at the base of the drainage sell. Applicant’ s expert (Q) Building Report 30 November 2017  The pipes originally damaged have been satisfactorily repaired.  Repairs have been completed in accordance with the scope of works.  Q exposed the top of the existing water proof membrane and its protective sheeting, the membrane was in good condition and appears to have been applied in accordanc e with relevant codes and has not wea thered or deteriorated over time.  Q believes that prior to the water pipe leak the membrane was performing as designed. However, aft er 100,000 litres of water penetrated the rear wall of the building it has compromised the water proofing or the structural integrity of the masonry wall, causing continued water ingress issues during heavy rain periods.  Q notes destructive testing would be required to confirm this.  Q provided a scope of works in the sum of $49,775.25 for exploratory works.  Q provided a pri or quotation which appears to be mostly internal works in the sum of $5,665.63.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.