Home / Financial Firm (Unknown - Insurer) / Determination 513095

Determination 513095

Fire claim settlement amount, policy cancellation and emergency accommodation

FirmFinancial Firm (Unknown - Insurer)
Decided2018-08-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$5,000
Non-financial loss$750
Amount claimed—
SourceAFCA PDF

Summary

Applicants whose home was damaged by fire disputed the building settlement, the purported policy cancellation and emergency accommodation. AFCA ordered $5,000 for landscaping, interest on the delayed settlement, $750 non-financial loss, and confirmed the policy remains in force.

The FSP's purported cancellation did not comply with section 59 of the Insurance Contracts Act 1984 and was therefore void under section 63, while the building settlement was found fair.

Issues

Subjects and remedies

home or building damagepay compensationpay interestpay non financial lossreinstate policy or contract

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 513095 Determination Page 1 of 5 Case number: 513095 9 August 2018 1 Overview 1.1 Dispute The applicants lodged a claim against their home and contents policy with the financial services provider (FSP). A fire had severely damaged their home on 20 April 2017. The FSP accepted the claim and concluded the home could be rebuilt. The applicants’ preference is to be cash settled. There are other issues involved: insurance cover for their property; there was an extension to the emergency accommodation payments; compensation for items allegedly taken by a contractor’s staff. The case manager provided the parties with a recommendation on the issues in dispute. The recommendation was partly in favour of the applicant and partially in favour of the FSP. A copy of the recommendation is attached to this determination. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were correct and are adopted in this determination. Further submissions provided after the recommendation have been considered. Are the applicants entitled to further payments? The FSP is required to make the additional payments identified in the recommendation and it is also required to pay the applicants $750 compensation for non-financial loss. 1.3 Determination This determination is partially in favour of the FSP and partially in favour of the applicant. I agree with the case manager’s reasons for the recommendation and the recommended outcome. The FSP is required to pay to the applicants: an additional $5,000 (landscaping); interest on $276,321.00 from 13 December 2017 to 25 May 2018; $750 compensation for non-financial loss. The policy remains in force. Otherwise, the FSP is not required to take any further action. Case No: 513095 Determination Page 2 of 5 2 Reasons for determination 2.1 Were the findings in the recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied the documentation I have relied on has been provided to both parties. I am satisfied the case manager’s recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. 2.2 Are the applicants entitled to further payments? Applicants seeking various payments The applicants suffered a loss when a fire severely damaged their home on 20 April 2017. The FSP accepted the claim and assessed the extent of damage. The FSP treated the contents as a total loss and cash settled the applicants as provided by the terms of the policy. The applicants said there is no issue with this part of their claim. However, there are issues in relation to the balance of the claim. The applicants sought a cash settlement on the basis the home is a total loss. They also referred to the FSP’s letter (dated 6 November 2017) in support of their position, with the letter stating their home is a total loss and their policy was cancelled. They are also seeking the payment of the sum insured safety net, in addition to cover for demolition costs, landscaping, unsecured renovation material and emergency accommodation. FSP has accepted most items Despite the FSP’s letter to the applicants on 6 November 2017, the FSP’s experts concluded the house could be repaired. The policy allows the FSP to select the method of settling the claim. The sum insured safety net is only payable if the cost to repair or replace the building is more than the sum insured. The sum insured was $428,900, whereas the FSP accepted a repair quote of $402,246.38. The FSP accepted the builder’s comments that the L-shaped patio did not require replacement and could be cleaned, since it had only suffered smoke damage instead of structural damage. In the absence of information to the contrary, both the accepted quote and the decision to clean (rather than replace) the L-shaped patio is fair in all the circumstances. The FSP accepted the applicants required payment for emergency accommodation. The policy provides for up to 10% of the sum insured or the cost of accommodation Case No: 513095 Determination Page 3 of 5 for up to 12 months from the date of the event. The event occurred on 20 April 2017 and the FSP paid $525 per week from 12 May 2017 for the following 12 months. The available information does not show the FSP unnecessarily delayed the claims process. The time lines show the FSP responded within a reasonable period to the applicants’ enquiries about items to be included in the scope of wor ks. The information indicates the work could have been completed within 30 weeks. This means the repairs could have been completed by May 2018. This means there is no reason to extend the period for the emergency accommodation benefit. The FSP also paid $1,069.20 for the pool pump, as quoted by a supplier. The FSP also paid the full settlement amount of $2,000 in relation to the unsecured renovations benefit (floorboards). FSP required to make further payments The applicants raised the issue of damage to the front yard : lawn; roses; sprinklers. The FSP was only prepared to pay $1,650 for the damage based on the quote it obtained. The applicant obtained a quote for $17,110. One of the photographs showed two heavy skips in the front yard. The damage from those alone would be more than the suggested ‘watering, fertilising and weeding of the garden’, as suggested by the FSP’s contractor. H owever, there is no information that indicates the fire or the FSP’s contractors caused damage to the back yard. As such, the recommended additional payment of $5,000 (the policy limit is $10,000) to the applicants is fair in all the circumstances. The FSP’s letter (dated 13 December 2017) indicated only $125,925.38 would be paid to the applicants, as the applicants’ bank required $276,321.00. This issue has been resolved with the full amount being paid to the applicants (they indicated they received payment on 25 May 2018). The FSP is required to pay interest on $276,321.00 from 13 December 2017 until 25 May 2018, in accordance with section 57 of the Insurance Contracts Act 1984. FSP had incorrectly cancelled the policy The FSP purported to cancel the policy (letter dated 6 November 2017) because the house was a total loss. However, this proved to be incorrect as its experts concluded the building was repairable. The applicants said they have unsuccessfully sought alternative insurance because of that letter and this led to them lodging a dispute. The FSP learnt the applicants had demolished their house, leaving only a fenced off swimming pool. The FSP said the applicants had a duty to notify it about having demolished the building. The FSP provided a statutory declaration from its underwriting section indicating the FSP would not cover a building that is subject to a demolition order or similar statutory order. However, the applicants decided to demolish the building, rather than the building having been the subject of a demolition order. Case No: 513095 Determination Page 4 of 5 The FSP’s purported cancellation had failed to comply with the Insurance Contracts Act 1984 (Act). The reasons are fully outlined in the recommendation. FSP’s contractor paid applicants compensation The applicants raised allegations of theft of contents by a contractor’s when clearing debris from the house. The contractor opted to pay the applicants $7,044.00 on a without prejudice basis for the sake of its own reputation and that of the FSP. That amount was to cover those items the applicants alleged had been taken, although they provided no information in support of their allegations. As such, the payment is fair in all the circumstances. Applicant provided further submissions The applicants rejected the recommendation whilst the FSP accepted it. The applicants provided further submissions after the recommendation. The applicants said the main reason for lodging a dispute was due to their inability to obtain insurance for the swimming pool area while their house, which they had demolished, was being rebuilt. The applicants referred to the FSP’s cancellation letter (6 November 2017) and said they had been unable to obtain insurance cover from any other source. They indicated they had never hidden their intention of demolishing the house. The applicants said the FSP has never reinstated their policy and it should make full payment in relation to their claim. The applicants outlined the issues associated with having no insurance cover for the swimming pool, such as potential public liability concerns. The applicants said they disagreed with the time frame used in relation to the emergency accommodation benefit. The applicants believe they should be entitled to a further period of cover, until the beginning of August 2018. They said they were not the reason for the delay, referring to the FSP’s final decision (letter dated 13 December 2017) and funds only being made available on 25 May 2018. The applicants also raised the issue of the $7 ,044 compensation an FSP contractor paid to them, as they do not believe the amount is sufficient. Outcome largely remains unchanged The recommendation, which the FSP accepted, concluded the policy remained in force until cancelled in accordance with the Act and, since the purported cancellation was void, the policy remains in force. The FSP had confirmed the house could be repaired and, given the policy allows the FSP to decide how it is to settle a claim, the FSP was entitled to opt for repairing the house. The repairs could have commenced around the time when P provided a quote (27 October 2017). Further, the FSP promptly responded when the applicants raised issues about the scope of works. There is no reason that suggests the emergency accommodation benefit should be extended beyond the 12 months maximum payment period. Case No: 513095 Determination Page 5 of 5 The $7,044 compensation paid to the applicants is fair in the circumstances in the absence of more detailed information. The applicants made serious allegations about a contractor’s staff stealing their contents. However, the applicants have provided no information in support of these allegations. Compensation for non-financial loss The recommendation concluded there was no information that supported an award of compensation to the applicants for non-financial loss. FOS takes a conservative approach to awarding compensation for non-financial circumstances. The applicants said the cancellation of the policy caused an unusual degree of interference with their expectation of peace of mind. The finding themselves uninsured would be disturbing. The applicants also expressed concern about a lack of public liability cover in relation to the swimming pool. I am satisfied that the applicants were caused inconvenience and concerns by the FSP. I find because of this an award of $750 is an appropriate amount of compensation that should be paid for non-financial loss. However, apart from that, the outcome in the recommendation remains unchanged. Recommendation Case No: 513095 Recommendation Page 1 of 14 Case number: 513095 24 May 2018 3 Overview 3.1 Dispute The applicants’ home was damaged by fire on 19 April 2017 and the financial services provider (FSP) accepted the building and contents claim. The FSP settled the claim for contents and for specified and unspecified personal items. The applicants worked with the FSP to correct and update the scopes of works and quotation for the building repairs. However, some items remain in dispute. The FSP says the building was not a total loss, and could have been repaired. The applicants dispute this assessment, saying that the items still in dispute would increase the total cost of repair to at least the sum insured amount of the policy. They say this means they should also have access to the safety net feature of the policy. The applicants also question the FSP’s dec ision to cancel the policy. Although they decided to demolish the main home building, they are concerned about the public liability risks associated with the partly fenced swimming pool. Further, the applicants seek an extension to the 12 months of emerge ncy accommodation provided by the FSP. 3.2 Issues and key findings Is the FSP required to pay any additional amount with respect to the building damage claim? The FSP is required to pay an additional amount of $5,000 with respect to the building damage claim to allow for damage to the garden and landscaping caused during claim processing. However, no further adjustment to the claim settlement amount needs to be made because:  There is no evidence that the front and L-shaped patios could not be restored to pre-e vent condition by cleaning, as included in the FSP’s scope of works  The FSP’s settlement is based on the higher of two quotations it received from building consultants, and is considered fair in all the circumstances. Was the FSP’s cancellation of the building policy valid? The FSP’s cancellation of the building policy was not valid because: Case No: 513095 Recommendation Page 2 of 14  the applicants decided to demolish the building  the policy requires applicants to notify FSP if circumstances about the risk change  the FSP say had it been advised of the demolition of the building, it would have cancelled the policy  the FSP has not shown it cancelled the policy as required by the Insurance Contracts Act 1984 (the Act). Is the FSP required to pay more than the policy limit for emergency accommodation? The FSP is not required to pay more than the policy limit for emergency accommodation because:  the repair of the building, as specified in FSP’s scope of works, likely would have been completed within the 12 month policy limit for emergency accommodation  there is no evidence the FSP caused unreasonable or significant delays in the processing of the claim. Is the FSP required to pay compensation for non-financial loss? The FSP is not required to pay compensation for non-financial loss because there are insufficient grounds for such a payment. 3.3 Recommendation This recommendation is partly in favour of the applicants, and partly in favour of the FSP. The FSP is required to pay an additional $5,000 with respect to damage caused to the garden and landscaping during the processing of the claim. The FSP is required to pay interest, at the statutory rate, pursuant to section 57 of the Act on the $276,321 (the amount of the claim settlement which was not paid at the time the of the claim decision letter was issued). This should be calculated from 13 December 2017 (the date of the claim decision letter) until the date these funds were paid to the applicants. The FSP is not required to pay:  Any additional amount with respect to the claim for the building damage.  Any additional amount for emergency accommodation.  Any compensation for non-financial loss. The purported cancellation of the building policy was not valid, and the policy remains in force until cancelled in accordance with the requirements of the Act. Case No: 513095 Recommendation Page 3 of 14 4 Reasons for recommendation 4.1 Is the FSP required to pay any additional amount with respect to the building damage claim? Front and L-shaped patios could be restored to pre-event condition by cleaning The FSP says the claim settlement allowed for the cleaning of the front and L-shaped patios. It says these components of the building were smoke damaged but did not suffer structural damage. A report from the FSP’s building consultant P, dated 8 November 2017, states that:  the powder coated steel tubing of the fro nt patio has no visible smoke staining, just surface grime from usual airborne dirt.  the front patio structure would respond to a general clean and be returned to an improved pre-loss condition.  The rear L-shaped patio had minor smoke residual staining to the top of the vertical support posts, and that this would more than likely respond well to a general clean and also be returned to an improved pre -loss condition.  Should a clean not be successful, a variation (to the scope of works) could be processed, detailing the specific parts which did not respond to the cleaning. The applicants have indicated that the struts of the patio were affected by the fire , and the roof was destroyed beyond repair. However, no expert evidence has been provided to support this contention. The applicants feel the amount offered by the FSP is not sufficient, saying an amount of $20,000 is an appropriate amount for the cost to fix this damage and the damage to the surrounding paving. However, in light of the information provided by P, and in the absence of any expert report or evidence to the contrary, I am unable to find that the FSP’s assessment (that the patios will, on the balance of probabilities, respond to cleaning) is incorrect. Landscaping amount provided by FSP needs allow for damage to lawns and roses The applicants have provided a quotation for the removal of all plant material and lawn from both the front and rear yards, and the installation of new turf, new lawn edging, replacement plants and new reticulation. The amount of the quotation is $17,110. The FSP has provided a report and quotation from a property maintenance contractor, PB, based on an inspection on 11 November 2017, which indicates the garden needs weeding, fertilising and watering. PB noted that the reticulation could not be inspected as there was no power, but said that the reticulation wiring was intact. PB’s quotation for the work it says is required is $1,650, including an amount $550 (including GST) for the replacement of any sprinklers which might need replacement. Case No: 513095 Recommendation Page 4 of 14 The applicants say skip-bins used by the FSP damaged the lawn, and covered the roses in the garden. They say the roses were of sentimental value, as they were a gift from a relative. The policy allows for up to $10,000 for gardening and landscaping. This provides for the costs of replacing landscaping and garden features of the same or similar variety and of a size suitable to commence the re -establishment of the garden. It is conditional on the trees, plants or shrubs being totally destroyed by the event, or having been totally destroyed by the work required to repair the home after an event. I accept that the process of repairing a seriously damaged home building often involves disruption to the garden, and that any such damage should be rectified by the party which caused the damage. Any such rectification should be performed or paid for regardless of any policy provisions which might allow for or seek to impose limits for this type of damage. In this case, the quotations provided by the parties are extremely polarised, which the FSP’s quotation be on the low end of the scale, and the applicants’ quotation being on the high end of the scale. I also note that the FSP says the back garden suffered no damage at all, so the component allowed for this area on the applicants’ quotation is not valid, however the applicant says the FSP’s contractor did not look at the back yard. While I am unable to factor in any sentimental value for the roses the applicants say have been damaged during the claim process, I accept that the damage needing rectification is likely to be more extensive than simply watering, fertilising and weeding of the garden, as the replacement of some of the sprinklers. After considering the material pro vided, and noting the FSP has already paid $1,650 for this item, I am of the view that it is fair in all the circumstances that the FSP contribute an additional amount of $5,000 for the damage to the landscaping at the applicant’s property. FSP’s settleme nt for building damage fair in all the circumstances The FSP’s settlement for the building damage is based on the higher of two quotations it obtained from building consultants (SBC, and P) for the repairs. SBC provided a cost of $321,487.10, while P provided a cost of $402,246.38 It is generally accepted that an insurer is entitled to settle a claim based on the cost they would incur to perform the repairs. In this case, I consider the settlement amount paid by the FSP to be fair in all the circumstances. However, the claim decision letter of 13 December 2017 advised the applicants that only $125,925.38 was to be paid to the applicants at that time. The letter indicated that $276,321 was required by the applicants’ bank. In the circumstances, it is appropriate that interest at the statutory rate be paid on the funds which were not paid to the applicants at the time of the claim decision letter. Case No: 513095 Recommendation Page 5 of 14 The interest should be calculated from 13 December 2017, until the payment settlement is (or was) made. 4.2 Was the FSP’s cancellation of the building policy valid ? Applicants decided to demolish the building The applicants did not want to move back into the building, even if it was repaired. There is no doubt that the damage to the home was severe, and that the event was traumatic for the applicants and their family. It is accepted that they might have difficulty moving back to the home. In the circumstances, the applica nts’ decision to demolish the building, with a view to rebuilding afresh, is understandable. Policy requires applicants to notify FSP if circumstances change The policy provides that:  the applicants were required to notify the FSP of changes to circumstances which might affect their cover.  Once the FSP receives such notification, it will discuss specific changes to the cover, including (but not limited to) when cover will stop. The policy lists certain events which must be notified to the FSP as soon as the applicants became aware of them. These include when any insured plans to demolish the main building. If FSP were advised of demolition of building, it say it would have cease cover The FSP wrote to the applicants on 6 November 2017, advising the building (and contents) had been assessed as a total loss, and advised that future cover under the policy had ceased. The FSP has since conceded that information in this letter was incorrect, as the building was not a total loss. The FSP says that the applicants should have advised of their plans to demolish the building, as the property with no main building and with only an unfenced pool would have represented an unacceptable risk. The information the FSP has provided in support of this position indicates it wo uld not offer cover for a building which is subject to a demolition order or similar statutory order. In this matter, however, the building is not subject to a demolition order. The main home building no longer stands as it has already been demolished, and the only part of the building (as defined in the policy) which is still in place is the swimming pool. However, in the circumstances, the FSP cannot rely on the policy provisions with respect to what happens in the event of a total loss. This means that the cover under the policy did not cease, as suggested by the FSP in its 6 November 2017 letter, and the policy remains in force until it is cancelled in accordance with the Act. Case No: 513095 Recommendation Page 6 of 14 Section 59 of the Act provides that an insurer who wishes to exercise a right to cancel a contract of insurance shall give notice in writing of the proposed cancellation to the insured. It also specifies that any such cancellation notice needs to contain certain information, including the time at which the cancellation will take effect. Even if I were to accept that pursuant to section 60(1)(d) of the Act, the FSP accrued the right to cancel the policy, based on the information provided I am not satisfied that the FSP has properly exercised any such accrued right. That is because the FSP has not complied with the requirements of section 59 of the Act. Accordingly, pursuant to section 63 of the Act, the FSP’s purported cancellation of the policy is void. 4.3 Is the FSP required to pay more than the policy limit for emergency accommodation? Repair of building likely to have been completed within 12 month policy limit The policy provides cover for emergency accommodation, in similar alternative accommodation, for up to 12 months from the date of the event (or 10% of the sum insured, whichever is the lesser) where the home is unliveable as a result of an event covered. The fire event was on or around 19 April 2017, so arguably this is the start date for calculation of the 12 month period for emergency accommodation. However, it is understood that the applicants initially found accommodation with their daughter. The FSP subsequently paid emergency accommodation costs of the applicants, at a rate of $525 per week from 12 May 2017, for 12 months. According to the material provided, the repairs to the home, as specified in FSP’s scope of works, could have been completed within 30 weeks. The quotation provided by P, upon which the FSP based its settlement, was provided on 27 October 2017. Arguably, had the repair work begun on or around that date, they would have been completed by around 11 May 2018. This is based on a repair timeframe of approximately 28 weeks (although it is possible that the repairs may have taken longer than noted in the documentation provided.) I accept that from early in the claim, the applicants had concerns about repairing the home, and wanted a cash settlement. However, the home was not a total loss, and could have been repaired had the applicants not sought an alternative method of remedy. I have considered the timeline of the claim, and do not accept that the FSP was responsible for any significant or unreasonable delays which might otherwise mean that it is not able to rely on the 12 month limit of the policy for emergency accommodation. I am therefore unable to find that the FSP should be required to pay any additional amount for emergency accommodation. Case No: 513095 Recommendation Page 7 of 14 4.4 Is the FSP required to pay compensation for non-financial loss? No grounds for a payment of compensation for non-financial loss Under its Terms of Reference, FOS may decide that the FSP compensate the applicants for non-financial loss (up to a maximum of $3,000) where an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the applicants’ expectation of enjoyment or peace of mind has occurred. However, FOS takes a conservative approach to compe nsation for non-financial loss. In this matter, the applicants were understandably keen to ensure the scope of works for the repairs included the correct items, and to the correct specification. The process required for this involved several iterations of the scope of works, with the applicants reviewing each iteration and seeking adjustments along the way. This process necessarily took time. However, after reviewing the exchanged material, I am unable to conclude that the FSP was responsible for any unreasonable or significant delays to the process. I am therefore unable to require the FSP to pay compensation for any non-financial loss suffered by the applicants in this matter. Case No: 513095 Recommendation Page 8 of 14 5 Supporting information 5.1 Other issues Safety net The applicants want the building claim to be treated as a total loss, as they believe that would give them access to the safety net feature of the policy. However, the policy clearly states that the safety net does not increase the sum insured. This indicates it does not operate to provide an automatic boost to any cash settlement which may be provided. I also note that the repair costs, outlined in the quotations from the building consultants used by the FSP, include demolition costs. The policy states that cost for necessary demolition of any parts of the building are additional to the sum insured. This means that in assessing whether the sum insured amount has been reached, the demolition costs should be excluded from consideration. Based on the information available, I am satisfied that the cost to repair the building does not exceed the sum insured. Accordingly, the safety net for the building cover is not triggered. Resolved issues When the dispute was lodged, there were some issues relating to the swimming pool at the property. It is understood that these issues are now resolved. In addition, it is understood that an issue relating to the alleged theft of some contents items, by a representative of one of the FSP’s contractors, has been settled by a payment of $7,044 to the applicant, made on a without prejudice basis. Neither of these issues are addressed within this recommendation. 5.2 Relevant law Insurance Contracts Act 1984 59 Cancellation procedure (1) An insurer who wishes to exercise a right to cancel a contract of ins urance shall give notice in writing of the proposed cancellation to the insured. (2) The notice has effect to cancel the contract at whichever is the earlier of the following times: (a) the time when another contract of insurance between the insured and the insurer or some other ins urer, being a contract that is intended by the insured to replace the first -mentioned contract, is entered into; (b) whichever is the latest of the following times: Case No: 513095 Recommendation Page 9 of 14 (i) 4 pm on the applicable business day; (ii) if a time is specified for the purpose in the contract — that time; (iii) if a time is specified in the notice — that time. … 60 Cancellation of contracts of general insurance 1) Where, in relation to a contract of general insuranc e: … (d) a person who is or was at any time the insured failed to comply with a provision of the contract… the insurer may cancel the contract. 5.3 Policy provisions Certificate of Insurance – 27 May 2016 to 27 May 2017 Details Sum insured Exce ss 1. Home Building Insurance Cover Selected: [highest level of cover] Property: [address] $428,900 $500 Product Disclosure Statement 2.9 Noti fy us about any change s You must notify us before or as soon as you become aware of any of the circumstances in this section 2.9 as they may affect your cover. We’ll then discuss specific changes to your cover, for example changes in premium, conditions, limits, exclusions or when cover will stop. We’ll confirm the agreed changes in writing, if applicable. You must notify us before or as soon as you become aware that:  …  any insured plans to demolish or relocate a building,  … 2.11 Cancelling your cover … When can we cancel your policy? We can cancel your policy (including any renewed policy) for any of the reasons described in the Insurance Contracts Act, including if you breach your duty of disclosure when initially entering into the insurance, do not comply with the terms of your polic y (including non-payment of premium), or make a fraudulent claim. We will give you prior written notice of the cancellation and, if you ask us, give reasons for cancelling the policy. The policy will be cancelled with effect from the earlier of:  when you enter into anot her contract of ins urance that is intended to replace this policy, and Case No: 513095 Recommendation Page 10 of 14  the time specified in the notice. … 4. Home and Contents cover … Insured events Depending on whether you have Building cover or Contents cover, we will insure your buildin g and/or contents at the site against loss or damage caused by the following events if they occur during your period of ins urance. … Fire Covered Loss or damage caused by fire where there was a flame. Loss or damage caused by smoke from:  a bushfire,  a fire on your property, or  a fire originating from your neighbour’s property. … 4.4 Additional benefits This summary of additional benefits is a reference tool only. For furt her details of the relevant terms and conditions, limits and exclusions on cover, refer to the page numbers shown. Building additional benefits If we agree to pay a claim for loss or damage to your building, we will also pay for the additional benefits listed below that are directly related to that loss or damage. Some additional benefits are paid in addition to the sum insured and some are paid as part of the sum insured. … Benefits paid in addition to your building sum insured Sum insured safety net [Highe st level of cover] If the cost to repair or replac e your building is more than your sum insured, we will pay the extra cost to: • repair the damage, or • replace your building. The sum insured safety net does not increase your sum insured or any other additional benefit. If you increase your building’s value (by renovating or extending fo r example), you need to let us know and increase your sum insured appropriat ely to avoid being underinsured.  Up to 30% of sum insured Demolition and removal of debris We will cover the cost of any necessary demolition of your home or parts of it, and the removal of resulting debris from the site (including any trees or branches that have caused damage to your building and need to be cut down).  Up to 10% of sum insured Case No: 513095 Recommendation Page 11 of 14 Not covered  the cost of removing or lopping trees or branches that haven’t caused damage to your building, or  the cost of removing tree stumps still in the ground. Emergency accommodation If your home is unliveable, we will cover the cost of similar alternative accommodation for you and any other insureds. This expense will only be pa id if you actually incur costs for emergency accommodation, and only while your home remains unliveable.  Up to 10% of sum insured or the cost of accommodation for up to 12 months from the date of the event, whichever is less … Gardens and landscaping If we agree to pay a claim for loss or damage caused by any of the following insured events – fire, explosion, lightning, earthquake, malicious acts, riot or civil commotion, impact or storm (not including rain), we will cover the costs of replacing lands caping and garden features of the same or similar variety and of a size suitable to commence the re - establishment of your garden. We will only pay this benefit if your trees, plants and shrubs:  are totally destroyed by the event or have been totally destro yed by the work required to repair your home after an event,  were living specimens before the event, and  were not being produced for commercial purposes.  Up to $10,000 … 7. Lodging a claim … 7.3 How we settle your claim Repairing or replacing When we agree to pay a claim for loss or damage: We may choose to pay:  the reasonable cost of repair, or  the reasonable costs of replacement to new condition with property of the same size and specification or with items as near to original as is currently possible, or  a cash amount. If we agree to pay cash, we’ll pay the amount it would reasonably cost to repair or replace the property. Where a building is not being replac ed, the amount we’ll pay will be less a reasonable deduction for depreciation due to wear and tear and age of the property. We will pay: Case No: 513095 Recommendation Page 12 of 14  to match materials, items or construction with those that existed before the loss or damage occurred or, where that is not possible, with the nearest similar materials, items or construction, and  only those costs that directly apply to the part of your property that has suffered the loss or damage. How your claim will affect your sum insured … • Total loss: If we pay a claim under part of the policy for the total sum insured, then your insurance cover under the relevant part of the policy will end, and no refund will be given. If you were paying by mont hly instalments, the balance of your annual premium will be deducted from your claim. You’ll need to take out new insurance cover for any replacement property. We’ll continue to cover your legal liability as the owner or occupier of the site until the end of your period of insurance, unless cancelled earlier. However this cover will cease immediat ely if:  construction, alterations, additions or demolition commences on your home,  you sell the land, or  you take out a new policy for either building or liability insurance at the site. Partial loss: If your claim is deemed to be a partial loss (that’s anything less than the total sum insured), onc e your claim has been paid w e’ll continue to cover you up to the full sum insured until your policy expires. … Glossary of defined terms … partial loss when the value of the loss or damage is less than the full sum insured under the policy. … total loss when the property insured is damaged or destroyed to such an extent it cannot be rebuilt or repaired and/or the total sum insured under the policy has been exhausted. 5.4 Information considered Record Key points FSP’s builder (MC) Quotation 4 Aug 2017  Total estimate for repairs – as per SBC Scope of Work - $278,933.72 incl GST  Includes $13,904.65 for demolition FSP’s builder (MC) Quotation 31 August 2017  Quotation based on Scope of Works  Total includes: o demolition $13,904.65 - excl GST ($15,295.11 incl GST) o P. Sum Landscaping on comple tion $1, 000 - excl GST ($1,100 incl GST )  Total $274,193.11 (excl GST) o Without demolition & landscaping - $ 259 , 288.46 (excl GST) o Without demolition & landscaping - $ 285,217.31 (incl GST) Case No: 513095 Recommendation Page 13 of 14 FSP’s builder (MC) Quotation 4 Sep 2017  Quotation based on Scope of Works  Total includes: o demolition $13,904.65 - excl GST ($15,295.11 incl GST) o P. Sum Landscaping on completion $1, 000 - excl GST ($1,100 incl GST )  Total $276,348.00 (excl GST) - $303,982. 80 (incl GST) FSP’s building consultant (P) Quotation Undated (sent to FSP on 27 Oct 2017)  Based on Scope of Works provided by SBC (and completed on Scope of Works template)  Total cost of repair $402,246.38 (incl GST) o includes an allowanc e for demolition $13,500 (excl GST) $14,850 (incl GST) FSP’s building consultant (P) Report Undated (b as ed on inspection 8 Nov 2017 )  Report specifically addresses the issue of the colorbond steel patios attached to the front, side and partial rear sections of the premises.  Structural engineer’s scope of works included recommendation to clean the patios to remove soot staining  This report provides an opinion, from a builder’s perspective  Patios examined and no structural damage was noted to raise concerns about structural integrity of each patio  Steel tubing of patio to front door entry area, and the L - shaped patio to the rear of the premises, was examined.  Front patio powder: o coated steel tubing has no visible smoke staining – just surface grime from usual airborne dirt o Patio structure would respond to a general clean and be returned to an improved pre - loss condition.  L - shaped patio: o had minor smoke residual staining to top of vertical support posts where it met a horizontal member and roof sheeting. o Extent of staining was light, and would more than likely respon d well to the general clean and be returned to improved pre - loss condition  Should cleaning not be successful, a variation will follow detailing the specific parts of the patio that did not respond, and the cost to remove and replace these. FSP’s building consultant (SBC) Quantity Surveyor Detailed cost estimate 18 Jan 2018  Report based on SBC Scopes of Works 11 Jan 2018 & 4 Jul 2017, and SBC Causation Inspection report 4 Jul 2017  TOTAL incl GST $378,570 o Includes Contingency allowanc e (2.5% ) o Builders margin (12%) o Demolition $48,394.00 excl GST ($ 53 , 233. 4 0 incl GST) o Professional fees $3,500 excl GST ($3, 850 incl GST)  Based on constru ction period of 20 - 24 weeks  Rectification cost without demolition/prof fees - $ 292 , 261 excl GST ($321,487.10 incl GST) FSP’s building consultant (SBC) Documents  Fire damage partial loss Scope of works and Specification 4 Jul 2017  Partial loss fire reinstatement Inspection Report Case No: 513095 Recommendation Page 14 of 14  4 Jul 2017 Applicant’s landscaper Quotation 31 Oct 2017  Front – removal of old existing lawn (approx. 80sqm) and all plant vegetation; new lawn edging, new reticulation, new turf, new plants to be installed - $9,200  Rear - removal of old existing lawn (approx. 60sqm) and all plant vegetation; new lawn edging, new reticulation, new turf, new plants to be installed - $6,900  TOTAL - $16,100 (excl GST) $17, 110 (incl GST) FSP’s Property Maintenance firm (PB) Report/Quotation Inspection date 11 Nov 2017  Inspected gardens to front and rear of property  Garden beds need to be weeded, fertilised and watered.  Reticulation inspected not complet ed as there was no power – but wiring still complete. Likely some pop - up sprinkler will need replacement  Cost to: weed gardens, fertilise and tidy gardens; check/test reticulation - $1,500 (excl GST) allowing $500 for new sprinklers $1,650 (incl GST) FSP’s assessor (CL ) Reports  9 & 25 May 2017  4 & 25 Jun 2017  13 Jul 2017  5 , 15, 18 Aug 2017  15 Sep 2017  31 Oct 2017  15 & 23 Nov 2017. FSP’s claim decision letter to applicants 13 December 2017  Claim accept ed  P building consultants prepared a scope of works totaling $402,246.38 – a copy was previously forwarded to you.  [name of bank] advis ed us that they require $276,321 of the settlement money.  The balance remaining $125,925.38

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.