Home / Financial Firm (Unknown - Insurer) / Determination 511841

Determination 511841

Compensation sought for losses during vehicle repair delay

FirmFinancial Firm (Unknown - Insurer)
Decided2018-04-24
ProductGeneral Insurance · Motor
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$1,200
SourceAFCA PDF

Summary

The applicant sought $1,200 for additional staff costs caused by a repair period longer than he said he was promised. AFCA found no misleading statement or unreasonable delay and that the hire car offer complied with the policy.

A repair estimate given at lodgement was not a guarantee, and the policy limits hire car cover to a compact vehicle within the seven day guarantee.

Issues

Subjects and remedies

motor vehicle collisionno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 511841 Determination Page 1 of 4 Case number: 511841 24 April 2018 1 Overview 1.1 Dispute The applicant lodged a claim with the financial services provider (FSP) for damages to his vehicle. The FSP accepted the claim and authorised repairs. However a dispute arose regarding the length of time for the repairs. The applicant wants the FSP to compensate him for losses he says he incurred due to the delay. 1.2 Issues and key findings Is the applicant entitled to any compensation? I do not consider the FSP has erred in the assessment of the claim, or its actions to settle the claim. It follows the applicant is not entitled to compensation. 1.3 Determination This determination is in favour of the FSP. The applicant is not entitled to any compensation under 9.3 of our Terms of Reference (TOR). Case No: 511841 Determination Page 2 of 4 2 Reasons for determination 2.1 Is the applicant entitled to any compensation? Applicant says FSP should cover losses during repair period The applicant holds a comprehensive extras motor vehicle policy with the FSP, providing cover for accidental loss or damage to his vehicle caused by an incident. The applicant lodged a claim on 22 November 2017 for damage to his vehicle. The FSP accepted the claim and authorised repairs to his vehicle. A dispute arose regarding the length of time the repairs took place. The applicant says the FSP made a commitment that his vehicle would be back on the road within three days of being dropped off at the repairer. He says the FSP returned the vehicle seven working days after it promised to return the vehicle. He says he is now at a loss for the seven days and wants the FSP to pay for the cost of additional employees required during this period, which amounted to $1,200. FSP says it has fulfilled its obligations under the policy The FSP says it offered cover under the policy’s seven day repair guarantee, which included use of a hire vehicle, which the applicant rejected. The FSP says the applicant did not agree to this offer because it only offered a compact vehicle, not a large vehicle that he required. The FSP refers to the following policy provision in the product disclosure statement (PDS): We cover If we have agreed to pay your claim and cannot get your car repaired within 7 calendar days beginning on the day your car is driven to our assessment centre for assessment, then on the 8th calendar day we will pay the reasonable hire cost of a ‘compact’ category hire car until the car is repaired, but only if: –– the damage to your car happened in one incident; and –– your car has not been damaged as a result of hail or flood; and –– your car can be safely driven to the assessment centre; and –– your car does not require additional private work to be carried out; and –– all repairs to your car are carried out as we direct. The FSP says the applicant’s vehicle was delivered on 27 No vember 2017, so the applicant was entitled to a hire vehicle under the seven day repair guarantee from 5 December to 8 December 2017. FSP’s offer fair and reasonable The applicant says the FSP should have provided a hire vehicle similar to his own during the repairs. The FSP says the applicant was not entitled to a hire vehicle for the full duration of the repairs because the applicant did not select this optional cover on his policy. Case No: 511841 Determination Page 3 of 4 The certificate of insurance (COI) and PDS outline the cover provided regarding a hire vehicle. The COI confirms the applicant did not select the optional hire vehicle benefit under the policy, meaning the only cover provided for a hire vehicle is under the seven day repair guarantee. However, as outlined above, this benefit is limited to a ‘compact’ vehicle, not an equivalent vehicle to the applicant’s. Whilst the applicant says the FSP only offered an unsuitable vehicle, being the ‘compact’ vehicle, the FSP is entitled to rely upon the policy terms and limit its liability. I therefore consider its offer to provide a ‘compact’ vehicle from 5 December 2017 to 8 December 2017 to be fair and reasonable and it was not required to provide a larger vehicle or provide a vehicle for the entire repair period. On balance, FSP did not provide misleading information The applicant says the FSP made a misleading statement regarding the repair timeframe and he suffered loss as a result. The FSP provided a recording of the initial claim lodgement. The applicant’s co - worker who lodged the claim asked how long the repairs would take. The FSP consultant did not provide a timeframe and advised it would depend on the assessment of the vehicle. When considering whether an FSP engaged in misleading conduct, FOS will consider:  available documents  the recollections of the parties  all relevant circumstances, including the applicant’s conduct. We give more weight to written records created when the alleged conduct took place because they are more likely to accurately reflect what was said. If there are no records, we will decide what is most likely to have occurred based on the information we receive. The only information provided regarding an initial repair timeframe is the claim notes. On 27 November 2017, an FSP consultant wrote that the repairs would take three days. Whilst the applicant says the FSP guaranteed a three day repair timeframe, from the information provided there is nothing to suggest this was anything other than a repair estimate. The information provided also suggests the FSP kept the applicant regularly updated regarding the status of the repairs and why the repairs would take longer than anticipated after the initial assessment. Having considered the available information, I am not satisfied, on balance, the FSP provided misleading information to the applicant regarding the repair period. I therefore cannot find the FSP liable for any losses the applicant says he incurred as a result of the repair timeframe exceeding three days. Case No: 511841 Determination Page 4 of 4 Applicant not entitled to compensation for consequential loss The applicant wants the FSP to reimburse him for costs associated with hiring contractors to fulfil his business’s obligations. He says he hired the contractors because the vehicle was unavailable for seven days. Under paragraph 9.3 of the TOR, FOS may award compensation for consequential financial loss or damage (capped at $3,500). The FSP says the PDS excludes loss of this kind. The FSP says it assessed the claim and completed repairs within two weeks and has therefore fulfilled its obligations under the policy. Whilst the PDS excludes this loss, FOS can consider a claim for consequential loss if indirectly caused by the FSP’s conduct. H aving considered the available information, I cannot see any error on the FSP’s part to warrant an award for compensation. This is because I cannot see the FSP provided any misleading information to the applicant and I do not consider a repair period not exceeding two weeks to be excessive, therefore the FSP did not unreasonably delay the claim. In the circumstances the applicant is not entitled to compensation under paragraph 9.3 of the FOS TOR.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.