Claim declined for damage to retaining wall during neighbour's builder works

FirmFinancial Firm (Unknown - Insurer)
Decided2018-07-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed for damage to their retaining wall and property during a neighbour's builder works, alleging vandalism or malice. The FSP denied the claim. AFCA found no malicious act or vandalism and that the wall damage was excluded as part of retaining wall construction.

Vandalism requires wanton or malicious damage, and the builder's works were done to rebuild the wall without intent to damage the applicants' property.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 511275 Determination Page 1 of 3 Case number: 511275 11 July 2018 1 Overview 1.1 Dispute The applicants claimed for damage to their property they say was caused by the neighbour’s builder. The applicants say this constituted vandalism or is a malicious act. The insurer, the financial services provider (FSP), denied the claim on the basis there was no insured event and the loss was a result of a civil dispute. A case analyst provided the parties with a recommendation on the issues in dispute. The recommendation was in favour of the FSP. A copy of the recommendation is attached to this determination. 1.2 Issues and key findings Were the findings of the recommendation correct? The findings contained in the recommendation were correct and are adopted in this determination. Further submissions provided after the recommendation have been considered. Can the FSP deny the claim? The FSP can deny the claim because the evidence does not show the applicants’ retaining wall was damaged by a malicious act or constituted vandalism. 1.3 Determination This determination is in favour of the FSP. I agree with the case analyst’s reasons for the recommendation and the recommended outcome. Case No: 511275 Determination Page 2 of 3 2 Reasons for determination 2.1 Were the findings in the recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case analyst’s recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. 2.2 Can the FSP deny the claim? Evidence does not show there was vandalism or a malicious act The applicants say the neighbour’s actions are vandalism or a malicious act. This is because they wilfully and knowingly extended the excavation into their property. I do not accept this for the following reasons. It is plain the neighbour had engaged and authorised a builder to reconstruct a failing retaining wall. This was adjacent to a shared driveway available to both the applicants and their neighbour. The retaining wall appears to extend to a small extent along the applicants’ property where a letter box was atop it. The applicants were aware of these works and had communicated with the contractor about it. An email was sent on 8 July 2017 providing some information about the boundary points. Between 8 and 11 July 2011, the retaining wall was demolished. This included the small portion on the applicants’ property. The applicants say to the extent this excavation affected the retaining wall on their property, this was vandalism or a malicious act. I do not accept this. It is clear the builder’s brief was to demolish and reinstate this retaining wall. It is likely the contractor engaged for this purpose believed this included all of the retaining wall. Whilst I appreciate the applicants did not consent to this, there is nothing to indicate the contractor was aware of this point. It is probable the works were done without appreciation of this significance. Therefore, I do not accept the evidence shows on the balance of probabilities the damage to the applicant’s property was done maliciously or with such intent that it could constitute vandalism. Case No: 511275 Determination Page 3 of 3 As such, I agree with the case man ager’s recommended outcome. Recommendation Case No: 511275 Recommendation Page 1 of 4 Case number: 511275 28 March 2018 3 Overview 3.1 Dispute The applicants hold a home and contents insurance policy with the financial services provider (FSP). The applicants lodged a claim on 15 August 2017, saying their property had been damaged by their neighbour’s builder. The FSP declined the claim, saying no insured event had occ urred and the loss was a result of a civil dispute. The applicants dispute this and say the FSP is liable for the damage 3.2 Issues and key findings Have the applicants established an entitlement to cover? On balance, I am not satisfied the applicants have established an insurable event has occurred. As such, the applicants have not established an entitlement to cover. 3.3 Recommendation This recommendation is in favour of the FSP. The FSP is not required to take any further action. Case No: 511275 Recommendation Page 2 of 4 4 Reasons for recommendation 4.1 Have the applicants established an entitlement to cover? Applicants have duty to establish a claimable loss The applicants are required to show, on the balance of probabilities, they have suffered a loss caused by an event insured for under the policy. This is known as establishing a prima facie claim. If established, the onus shifts to the FSP. In such a case, the FSP must show, on the balance of probabilities:  the policy does not cover the loss or damage, or  the FSP is otherwise entitled to deny the claim. Policy covers defined events and accidental damage The applicants’ policy provides cover for a series of insured events and optional cover for accidental damage. The certificate of insurance (COI) confirms the applicants took out the accidental damage cover. Under insured events, the policy provides cover for vandalism and malicious acts. The policy does not define ‘vandalism’ or ‘malicious acts’ so we may use their natural and ordinary meaning from the Macquarie dictionary (online version) being: vandalism: wanton or malicious destruction or damage of property. malicious: full of, characterised by, or showing malice. In this context it is also necessary to consider the meaning of ‘malice’: malice: desire to inflict injury or suffering on another. The policy defines accidental damage as: Damage that is caused unintentionally to your home or contents. Relevant to this dispute, accidental damage cover excludes damage to retaining walls. No evidence of malicious damage The applicants lodged a claim on 15 Aug ust 2017, saying their property had been damaged by the neighbour’s builder who was doing excavation works. The purpose of these works was to build a new retaining wall on a shared driveway between the properties. The work involved removing the existing retaining wall on the neighbour’s property, cutting into the slope and building a new higher wall. The applicants say that the actions of the builder are malicious and consistent with vandalism. They say that the occurrence was a malicious act because it was done with evil intent and resulted in the destruction of property. The applicants have provided photos, letters and a list of invoices paid which includes: Case No: 511275 Recommendation Page 3 of 4  costs incurred for reinforcing staircase and building a new letter box  costs for council permits  engineering costs  costs for security to attend the property while the neighbour’s builder was on site. The FSP appointed builder (M) to inspect the applicants’ property. M prepared a report that says: Upon inspection of the property I found the following: The neighbour had a builder working on the home externally, the neighbours driveway is also used by Mr insured as he has stairs leading to his home, this has now been blocked off by the builders. The stairs had brick work built near it according to Mr insu red and up the neighbours property which was used as a retaining wall… it is my opinion the damage is a civil matter [sic] As a result, the FSP says that no insured event has occurred and therefore there is no claim. Having considered the information provided by both parties, on balance, I am not satisfied that t he applicants’ loss was a result of a malicious act or vandalism . This is because:  the applicants consider the excavation work to be ‘damage’ but accept the new retaining wall is fit for purpose and built within the neighbour’s boundary  the intent of the builder was to construct a new retaining wall  the builder did not seek to intentionally damage the applicants’ property  the builder’s actions are therefore not malicious or consistent with vandalism from an insurance perspective While the accidental damage cover responds to any ‘unexpected’ damage that has occurred, the applicants have not established that the letter box or staircase was damaged, rather the existing letter box was moved by the builder . The applicants have since built a new letter box to replace the existing one. There is a specific exclusion for retaining walls within the accidental damage cover. As such, any damage relating to the construction of the retaining wall itself is excluded under the policy. On balance, I am satisfied the applicants have not established an entitlement to cover and the FSP is entitled to decline the claim. FSP not required to pay compensation The applicants lodged the claim with the FSP on 15 August 2017. The FSP’s assessor M attended the premises on 16 August 2017. The submissions provided by both parties suggest there has been ongoing communication between the FSP and the applicants. I do not consider there have been any delays by the FSP in the management o f the claim. The applicants say they have suffered psychological trauma as a result of the conduct of the site manager. While I empathise with the applicants’ experience, the FSP cannot be held liable for the actions of the site manager. Case No: 511275 Recommendation Page 4 of 4 The applicants also say that their family has suffered loss of income as they had to take time away from work to monitor the actions of the site manager. Again, the FSP is not liable for this loss, noting compensation may only be considered where the actions of the FSP have contributed to the situation. In this dispute, while the applicants have had issues with the neighbour and the contractors building the wall, these were not caused by the FSP. 5 Supporting information 5.1 FOS Approach There has been a full exchange of the relevant material between the parties and each party has had the opportunity to address the issues raised. I have reviewed and considered all the material provided by the parties. While the parties have raised various issues in their submissions, for the purposes of this recommendation, I have restricted its commentary to those issues which I consider directly relevant to the outcome only. 5.2 Relevant policy sections Cover Description Defined e vents The events we cover (p22) We cover your home or contents when certain things happen. These are known as ‘listed events’. You can make a claim if a listed event takes place and causes loss or damage to your home or contents during the policy period. Vandalism or a malicious act (p26) If loss or damage is caused by van dalism or a malicious act. Covered  Vandalism or a malicious act. Accidental damage Accidental damage (p47) You can choose to cover your home and contents for accidental damage – that is, mishaps around your home that are caused unintentionally. […] Covered under Buildings Insurance  Damage to your home that is caused unintentionally. […] Not covered […] damage to:  retaining walls