Home / Financial Firm (Unknown - Insurer) / Determination 511229
Determination 511229
Denial of garage water damage claim as not caused by a sudden and accidental event
Summary
The applicant's garage was damaged by a waterproofing membrane that failed over time, and the FSP denied the claim. AFCA found the damage was not caused by a sudden and accidental event, so the FSP could deny it and the applicant's engineer report fee was not reimbursed.
The insuring clause requires damage from a sudden and accidental cause, and gradual breakdown of a waterproofing membrane does not satisfy it.
Issues
- Claim denial primary · not upheld
“The FSP is entitled to deny liability for the claim; the breakdown of the waterproofing membrane was plainly not sudden”
- Product terms interpretation secondary · not upheld
“The insuring provision requires the damage to have resulted from any sudden and accidental cause”
Subjects and remedies
home or building damageno remedy
Text of the determination
Determination
Case No: 511229 Determination Page 1 of 4
Case number: 511229 27 July 2018
1 Overview
1.1 Dispute
The applicant’s claim for damage to his garage was denied by his insurer, the
financial services provider (FSP).
The applicant disputes this as he says the policy responds. The applicant is also
seeking reimbursement of the engineer report (F) he obtained to support his position.
1.2 Issues and key findings
Can the FSP deny the claim?
The FSP can deny the claim because:
the policy insures the applicant for loss or damage caused by a sudden and
accidental cause
F’s evidence is that the damage was due to a waterproofing membrane having
broken down and failed over time
this does not show the cause of the garage damage was due to a sudden event
The FSP is not required to reimburse F’s report fee given it did not advance the
applicant’s position.
1.3 Determination
This determination is in favour of the FSP.
The FSP is entitled to deny liability for the applicant’s claim.
Case No: 511229 Determination Page 2 of 4
2 Reasons for determination
2.1 Can the FSP deny the claim?
Applicant is required to show a prima facie claim
The applicant is required to show, on the balance of probabilities, he has suffered a
loss caused by a risk insured against under the policy.
This is known as a prima facie claim.
Both parties have provided an opinion from engineers. Their reports are summarised
in section 3.1. However, even if I accept F’s evidence, this does not assist the
applicant’s position for the following reasons.
Applicant has not established a prima facie claim
The insuring provision of the policy says:
We insure You up to the Sum Insured shown on the Schedule for Section 1 , against
accidental Loss or Damage to Your Insured Property which occurs during the Period of
Insurance.
The policy defines “Loss or Damage” to mean:
means direct physical loss of, destruction of, or damage to property from any sudden and
accidental cause not otherwise excluded by this Policy
F’s report describes the loss in the following way:
It is the opinion of [F] that the waterproofing membrane is likely to have been effective at
the time of construction (and purchase by the owner) but has broken down and failed over
time due to two principle factors discussed below
The applicant says that at the point the membrane failed, this would have been
sudden and accidental. Therefore, the insuring provision is satisfied.
I do not accept this.
The insuring provision requires the damage to have resulted from any “sudden and
accidental cause”. F’s opinion clearly describes the cause of the gara ge damage as
the breakdown of waterproofing membrane which “failed over time”.
This shows that whilst the breakdown was accidental, it is plainly not sudden.
Therefore, I am not satisfied the applicant can establish a prima facie claim.
Accordingly, the FSP is entitled to deny liability for the claim.
Further, as F’s report did not assist the applicant’s position, I do not accept the FSP
is liable to reimburse this cost.
Case No: 511229 Determination Page 3 of 4
3 Supporting information
3.1 Expert reports
Record Key points
FSP’s expert (MCS )
Report
30 June 2017
rear solid brick wall of the garage has undergone rotation and
possibly minor settlement.
based on soil test results the proximate cause of the movement is
inadequate depth of foundation as the bearing capacities of the soil
at foundation dept h are inadequate.
moisture in the brickwork causing efflorescence is most likely
caused by leakage from the end of the drainage pipe outflowing
into the rain head due to a poor water seal around the pipe or
possibly as a result of the movement of the rear wall.
this is considered to be a long - term event.
partial collapse of the ceiling along the rear wall of the garage was
caused by the movement of the brick wall.
water damage to the ceiling adjacent to the roller door is caused by
a breakdown in the wat erproofing membrane either due to
differential movements between the garage structure and the two
storey building structure resulting in a failed membrane or an
inadequate applied membrane at the time of construction.
this is considered to be a constr uction fault and has been occurring
over an extended period of time.
Applicant’s expert (FMG )
Report
2 November 2017
some evidence of a moisture drip from the wall capping on the
south wall.
efflorescence to the masonry at the south - east corner of the
g arage.
deformation of the capping over the southern wall of the house.
ponding of rain water on the balcony, particularly at the south - west
corner.
observable damage to the ceiling of garage and the reported
partial collapse of the ceiling i s consistent with damage as a result
of moisture into the ceiling void.
moisture ingress into the plasterboard ceiling lining may cause the
lining to degenerate, weakening the lining and its bond to the
framing and is consistent with the reports of a part ial collapse and
the movement of the ceiling at the north - east corner of the garage.
several possible sources of moisture into the garage ceiling.
ingress of stormwater through the surface of the balcony, ie. failure
of the waterproofing of the balcony.
the waterproofing membrane is likely to have been effective at the
time of construction, but has broken down and failed over time due
to two principles factors.
inadequate detailing of the waterproofing.
review of the drawings, showing the waterproofing membrane is
under the flooring sheets, and should be applied on the top of the
flooring sheets.
the improper application and/or improper product selection of the
Case No: 511229 Determination Page 4 of 4
waterproofing membrane during construction is the most significant
contributing factor to the breakdown and failure of the
waterproofing.
building movement, as a result of inadequately detailing and
allowance within the waterproofing membrane for building
movement, the inevitable movement of the building can result in
(cracking) failure of the wa t erproofing membrane.