Fire control measures settlement amount disputed
Summary
The applicant disputed the FSP's settlement for council-required retrospective fire control measures on units 6, 7 and 8, claiming $118,670.49. AFCA ordered the settlement increased to $38,942.50 plus statutory interest, rejecting the bounding construction and asbestos costs.
The council-approved sprinkler scope required fire control costs, including the water upgrade and extra certification, while costs for bounding construction the council did not approve were excluded.
Subjects and remedies
home or building damagepay claimpay interest
Text of the determination
Determination
Case No: 511180 Determination Page 1 of 5
Case number: 511180 23 July 2018
1 Overview
1.1 Dispute
In August 2015, the applicant and the financial services provider (FSP) received a
determination from FOS. The determination said that upon receipt of evidence that
the amounts have been paid, the FSP was required to reimburse the applicant the
cost of the retrospective fire control measures in relation to units 6, 7 & 8.
The FSP made an offer, however, the applicant remains dissatisfie d with the FSP’s
offer of settlement for this part of the claim.
1.2 Issue and key findings
Is the amount offered by the FSP fair in the circumstances?
The FSP’s settlement of the claim is not fair in all the circumstances. This is because
it does not include all costs of the fire control measures required by Council. The
settlement should be increased to $38,942.50, to reflect the reasonable costs of the
retrospective fire control measures.
1.3 Determination
This determination is partially in favour of the applicant.
The FSP is to increase its settlement to $38,942.50.
The FSP should also pay interest on the settlement at the statutory rate form the date
the applicant submitted the documents until the date of settlement.
Case No: 511180 Determination Page 2 of 5
2 Reasons for determination
2.1 Is the amount offered by the FSP fair in the circumstances?
Prior determination allowed retrospective fire control measures
It is not in dispute that FOS have determined that the FSP is required to reimburse
the costs associated with retrospective fire control measures. The determination
states:
As such, if the Applicants proceed with the repair and/or rebuilding of the damaged units,
then upon provision of appropriate documentary confirmation that the Council requires the
measures and upon receipt of evidence that the amounts have been paid, the FSP is
required to reimburse the Applicants the cost of the retrospective fire control measures in
relation to units 6, 7 & 8.
The determination noted the applicant had provided a statement from their builder to
the effect that if the council required retrospective fire control measures, then an
additional $51,150 will need to be paid.
The applicant has submitted claims totalling $118,670.49 for the retrospective fire
control measures.
Council approved residential sprinkler system
The applicant has provided minutes of a development application meeting with
council that confirmed two options were provided in a fire safety report that Council
would support:
To provide bounding construction to the units in accordance with the current
building code of Australia; or
Provide a residential sprinkler system throughout the entire building.
The scope of works (SOW) approved by the Council included installation of a
residential sprinkler system and the reinstatement of a smoke detection and alarm
system throughout the building.
The applicant engaged a fire service consultant to liaise with Council and engineers,
plus supervise installation of the sprinkler system, automatic smoke detection
system, automatic fire monitoring service, exit signage and fire extinguishers.
Having reviewed the available information, I am satisfied that the Council required
the installation of the residential sprinkler system and the FSP has agreed to this plus
the other fire control measures supervised by the fire service consultant.
FSP has accepted the cost of some fire control measures
The FSP says they will pay the following fire control measures totalling $36,204.50:
Building certification services -$2,740
Fire sprinkler design and documentation -$3,300
Installation of fire sprinkler system -$15,004
Fire extinguishers -$280.50
Installation of fire alarm system -$9,680
Case No: 511180 Determination Page 3 of 5
Exit and emergency lights -$1,155
Fire consultant -$4,045
The applicant says this does not cover all the fire control measures.
Council approved water service upgrade
The applicant says the water service upgrade was necessary for the installation of
the residential sprinkler system as confirmed by Council with respect to the dual
check valve backflow prevention device installed on the fire sprinkler service.
The FSP says the upgrade to the water service is for all 8 units as the previous water
service was only adequate for one unit.
Having reviewed all the available information, on balance, I am satisfied that the
water service upgrade was necessary to support the residential sprinkler system and
therefore the FSP is to reimburse the applicant the sum of $1,308. The Council fees
for the water meter and for water, sewer and stormwater do not relate directly to this
upgrade and are therefore not claimable under the fire control measures.
FSP is liable for additional certification costs
The FSP says that certification has already been approved and allowed for in the
original SOW
The applicant says that additional certification was required for the retrospective fire
control measures.
Having reviewed all the available information, on balance, I am not satisfied that the
fees for the fire service consultant are the only additional fees for the fire control
measures. Some additional planning fees were required and I am satisfied that an
additional amount of $1,430 is fair in the circumstances for this additional certification
with respect to the retrospective fire control measures.
Bounding construction not confirmed by Council
The minutes of a development application meeting with Council confirm that Council
would support the development application if it included either bounding construction
to the units or a residential sprinkler system throughout the entire building.
The SOW approved by the Council does not reference bounding co nstruction nor
does any of the Council approval documentation provided.
On balance, Council approved the SOW with a residential sprinkler system but not
bounding construction to the units. Given this, the FSP is not liable for any of the
costs with respect to bounding construction to the units.
FSP not liable for additional asbestos removal
The FSP says asbestos removal was allowed for in the original settlement for all
claims.
The applicant says the SOW did not include any costs for unit 7 , where the walls
were not damaged but were required to be removed for the bounding walls.
Case No: 511180 Determination Page 4 of 5
Given that the FSP is not liable for any of the costs with respect to the bounding
construction to the units, the FSP is not liable for these costs.
Settlement should be increased
Based on the available information, I am satisfied that the FSP should increase its
settlement to $38,942.50, to cover the retrospective fire control measures required by
council.
Case No: 511180 Determination Page 5 of 5
3 Supporting information
3.1 FOS Approach
As advised to the parties, FOS has considered it appropriate to expedite this dispute
in accordance with the Operational Guidelines to the FOS Terms of Reference, due
to the nature of the dispute. Accordingly, this dispute has not been the subject of a
FOS recommendation and has proceeded directly to determination.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.