Home / Financial Firm (Unknown - Insurer) / Determination 510709
Determination 510709
Claimed cracking and mould damage linked to 2012 water leak; earth movement exclusion
Summary
The applicant claimed further cracking and mould damage in 2016 as related to a 2012 water leak that had been cash settled. AFCA found the applicant had not established the damage was caused by an insured event or the 2012 leak, and that the claimed cracking was caused by earth movement, so no further action is required.
The insured bears the onus to prove a prima facie claim linked to a covered event, and the expert evidence from site inspections was more persuasive than the applicant's non-inspecting expert.
Issues
- Claim denial primary · not upheld
“the claimed cracking damage is because of earth movement. Damage caused by earth movement is excluded under the policy.”
- Claim amount dispute secondary · unclear
“the issue of the adequacy of the settlement is not the subject of this determination.”
Subjects and remedies
home or building damageno remedy
Text of the determination
Determination
Case No: 510709 Determination Page 1 of 7
Case number: 510709 13 August 2018
1 Overview
1.1 Dispute
The applicant held a home insurance policy with the financial service provider (FSP).
In 2012, he lodged a claim under the policy for damage from water leaking from a hot
water service.
The claim was accepted and cash settled.
In 2016, the applicant identified cracking to the building and had concerns about
mould being an ongoing issue. He claimed both related to the 2012 event and asked
the FSP to indemnify him for the claimed additional damage.
The FSP reviewed expert opinion and concluded it had no further liability under the
2012 claim. It says:
mould remediation completed in 2012 was satisfactory
the claimed current cracking damage is not related to the 2012 water event.
The applicant disputes this decision.
The case manager provided the parties with a recommendation on the issues in
dispute. The recommendation was in favour of the FSP.
As the applicant has not accepted the recommendation, the dispute has been
referred to me for determination.
1.2 Issues and key findings
Is the FSP liable for the claimed additional damage?
The available information establishes on the balance of probabilities no insured
event, including the 2012 water leak, is the proximate cause of the reported cracking
and mould at the insured property in 2016. The available information establishes the
claimed cracking damage is because of earth movement. Damage caused by earth
movement is excluded under the policy. The FSP is not liable for the claimed
additional damage.
1.3 Determination
This determination is in favour of the FSP.
The FSP is not required to take any further action in relation to the claimed additional
damage.
Case No: 510709 Determination Page 2 of 7
2 Reasons for decision
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have considered
all the material submitted by the parties, both before and after the recommendation. I
am satisfied the documentation I have relied on has been provided to both parties.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
No new information provided after recommendation
After the recommendation was rejected, the parties made no further submissions and
provided no new information.
2.1 Is the FSP liable for the claimed additional damage?
The applicant must establish on the balance of probabilities he has suffered a loss
caused by an event to which the policy responds. This is known as a prima facie
claim.
In the circumstances of this dispute, the applicant must establish on the balance of
probabilities the cracking damage and the mould damage in January 2016 was
caused by an insured event or by the water leak from the hot water pipe which was
the subject of a claim in January 2012.
Mould remediation was satisfactorily completed in 2012
The recommendation states the applicant no longer disputes the mould remediation
was satisfactorily completed in 2012.
In any event, having considered all the available material, I am satisfied the mould
remediation was satisfactorily completed in 2012. This is because the photographs of
the subfloor provided in June 2012 by the company which undertook the mould
remediation show the subfloor both before and after the remediation. No mould is
shown in the photograph taken after the remediation.
Further, the specialised treatment is described. Samples were taken and analysed by
an independent laboratory after the specialised treatment. The samples passed and
were certified.
Mould experts attended and photographed the property in February 2016. They
noted the mould was slightly elevated but the premises were dry. Photographs taken
of the subfloor show the subfloor to be dry and free of visible mould. The March 2016
laboratory report detailed no visible mould or high moisture level readings.
I am satisfied the available material establishes on the balance of probabilities the
applicant has not established a prima facie claim in relation to the mould.
Case No: 510709 Determination Page 3 of 7
Background to the 2016 claim
In relation to the external brick cracking damage, the parties rely on extensive
material dating back to 2006.
By way of background, the following chronology is set o ut from the material provided.
Date Action
September 2006 Blockage in storm water drain caused external damage including
foundation movement.
Insurer’s Civil
engineer (SC)
report
31 October 2006
Previous long - term differential settlement relat ed movement and
damage noted.
Insurer’s Scope
of Works
February 2007
Nine underpinned locations identified in sketch B in rooms identified as
the family room, bedroom 4 and bedroom 3.
External works included repairs to cracked and disturbed brick veneer
w alling where located directly above or immediately adjacent to the
underpinned perimeter wall foundations.
Internal works included patch repairing painting etc in many rooms in
the house.
11 October 2007 Insurer’s builder quoted $49,635 including GST t o repair damage.
Claim cash settled.
Applicant’s
engineer DP
plans
25 July 2008
6 pins identified on plan.
August 2008 Part underpinning inspected by local council.
Water usage 29/12/ 11 - 17/4/12. 204,000 kilolitres of water used.
17/412 - 11/8/12. 80,000 kilolitres of water used.
11/8/12 - 15/12/12. 117,000 kilolitres of water used.
January 2012 Applicant’s plumber repaired burst hot wat er pipe.
Claim made for damage caused by hot water pipe under house.
Burst pipe located under study and spare room.
During 2012 Various experts assessed the claimed damage.
September 2012 FSP cash settled the claim resulting from the leaking hot water pipe for
$21,710.22 for repairs and 20 days accommodation.
January 2016 Applicant claimed mould returned to subfloor and cracking to external
brickwork appeared in the south - east corner of the window frame in the
lounge and claimed there was a crack in the brickwork in the south - east
corner of the house.
When the claim was made in 2012, the FSP arranged for an assessor to inspect and
photograph the damage in early February 2012. He noted the stumps under the
affected area had a considerable amount of packing on top which he said indicated
the house had been relevelled in the past.
Case No: 510709 Determination Page 4 of 7
The assessor also noted (and photographed) the external brick wall had cracking on
it and the soffit above the study window had separated. He also observed the internal
walls had evidence of pre-existing movement and patchwork indicative of damage
which occurred prior to 2012.
The assessor said the only damages consistent with the leaking pipe were cupping of
the floor and future possible movement of the foundations in coming months as the
subfloor dried out.
The FSP engaged a structural engineer (CE) who also inspected and photographed
the damage in March 2012. The engineer describes the internal damage in the family
room, bedrooms 3 and 4 and the subfloor.
The engineer noted the hot water pipe repair in a location under the floor of bedroom
3. The engineer also noted significant packing installed during the relevelling of the
floor following underpinning. He concluded the previous repairs to internal damage
caused by the blocked storm water in 2006 had been completed and the observed
internal damage is because of the recent leaking of the hot water pipe.
The engineer recommended four months pass to allow the soil to dry. He said during
that period further foundation movement will occur and it is likely cracks may reduce
in size and doors return to their original alignment.
The engineer’s recommendations related to internal damages only.
Four months later, scopes of work were prepared. The scopes of work did not include
the external brickwork but did include packing to bearers under bedroom 3, bedroom
4 and the south side of the living area.
The FSP’s builder was not prepared to carry out repairs because of pre -existing
stump packing issues and the claim was cash settled.
Parties rely on expert reports
Following the claim made in 2016, both parties provided reports from engineers. The
FSP’s engineer inspected and photographed the damage in April 2016. One of the
applicant’s engineers inspected the damage in April 2018. The other engineer
appears not to have inspected the property.
The FSP’s engineer says the 2012 leak in the hot water system has not caused or
contributed to the observed damage in the house. The FSP’s engineer makes
several observations. Particularly, I note:
following repair of the leak, the FSP’s engineer says if foundation soils were
moisture affected they would be expected to return to normal pre -leak moisture
levels after about two summers
past relevelling works can also cause cracking damage
there is damage remote from the leak in the hot water service
The applicant relied on two engineers. The engineer (JB) says the burst pipe line in
the subfloor washed out the soil, causing movement and possibly the failure of the
previous underpinning.
Case No: 510709 Determination Page 5 of 7
The applicant also engaged the engineer (DP) who says the water which escaped in
2012 was considerable and saturated the soil. DP says this considerable saturation
caused the footings to move and the brickwork cracking to appear.
Applicant’s engineers’ op inions are insufficiently persuasive
I do not find JB’s opinion sufficiently persuasive. This is because JB inspected the
property over six years after the 2012 leak. The photographs taken by the FSP’s
assessor contemporaneous with the claim do not show s ignificant “washing out of the
soil” so as to interfere with the previous underpinning. None of the contemporaneous
photographs show this kind of dramatic damage. The FSP’s engineer described the
subfloor area in April 2012 as wet only to 20mm below the surface.
Further, some of the external cracking damage noted by JB was not sufficiently
proximate to the area where the hot water service leaked.
Finally, JB appears to have limited material. It is not clear from the report JB was
aware of the damage and claim made in 2006 and of the repairs undertaken because
of that claim. Further, it is not clear from the report what material JB had from the
2012 claim.
I do not find DP’s opinion is sufficiently persuasive either. This is because DP has not
inspected the damage, but relied on information provided to him by the applicant. It
appears the material provided by the applicant to DP is also limited. Specifically, it is
not clear if DP was aware of the 2006 and 2012 reports and findings , and of the
exact nature of the repairs done by the applicant after the 2006 and 2012 claims
were cash settled.
Further, DP has not commented on the rebuttal material from the FSP’s engineer.
The FSP’s engineer considered DP’s report and said site inspections and
independent measurements are essential in forming a professional opinion about the
cause of damage.
Generally, I accept an opinion from an expert who has not inspected the damage is
less persuasive than an opinion formed from a site inspection.
In addition, the FSP’s engineer rebuts DP’s opinion saying:
if a bearing failure had occurred due to the leak in 2012 any associated damage
would have occurred in 2012 but the damage was only claimed in January 2016
DP does not consider the substantial packing of the stumps in the subfloor
which shows previous attempts to relevel the floor and indicates the house has
a history of building movement
bearing failures tend to be localised and associated damage would have
occurred in a discrete area within the vicinity of the bearing failure
DP takes no account of the previous repairs carried out in several locations
including areas remote from the hot water service where the leak occurred.
The applicant questions the expertise of FSP’s engineer. However, both reports are
completed by forensic engineers. The reports indicate the engineer comprehensively
inspected and photographed the property and conducted a level survey.
Case No: 510709 Determination Page 6 of 7
The exterior cracking damage was not caused by the water leak in 2012
I am not satisfied the applicant has established on the balance of probabilities the
claimed additional cracking damage to the exterior of the home was caused by the
2012 leaking event or any other insured event.
This is because, for the reasons stated, I do not find the applicant’s engineers’
opinions sufficiently persuasive. Further, the photographs show damage is not just
localised to the area where the leak occurred. In addition, the available material
establishes there was external damage already in 2006. I accept the available
material establishes some underpinning was done in 2008. However, the applicant
has not established the external damage was repaired with the cash settlement
provided by the FSP in 2007.
In all the circumstances, I am not satisfied from the available material the FSP is
liable for the claimed damage because the applicant has not established on the
balance of probabilities the claimed mould damage and claimed external brick
damage in 2016 was caused by an insured event or by the water leak in 2012.
The applicant also says the FSP only partially settled the 2012 claim because the
foundations were not repaired after the 2012 event.
The FSP’s engineer (CE) recommended four months be allocated to allow the soils
to dry. The property was inspected and scopes of work were provided to the parties
in August 2012, well within that timeframe.
The scopes of work included work to repack and generally level the existing stumps,
namely:
Provide packing to bearers which are no longer in contact with the stumps und er bedroom
3, bedroom 4 and the south side of the living area as required
The scopes of work were agreed to by the applicant and the claim was cash settled.
The available material shows the 2012 damage was assessed, scopes of work were
prepared and approved by both parties and the claim was cash settled relying on the
scopes of work. The available material does not establish the applicant’s contention
that the 2012 cash settlement covered interior damages only.
In a recent review, the FSP acknowledged the 2012 settlement was inadequate and
has made a further offer of settlement to the applicant. However, the issue of the
adequacy of the settlement is not the subject of this determination.
Case No: 510709 Determination Page 7 of 7
3 Supporting information
3.1 FOS Approach
It is an accepted principle of general insurance law that an insured bears the onus to
establish on the balance of probabilities that they have suffered a loss caused by an
event to which the policy responds. This is known as a prima facie claim. Once so
established, the onus shifts to the insurer to prove on the balance of probabilities that
an exclusion applies if it seeks to deny or limit its liability for the loss.
3.2 Case law and proximate cause
Case law establishes:
The proximate cause of the loss is the dominant or effective or operative cause
of the loss whether or not that be the last in time or the sole cause.
If there are several causes operating contemporaneously, each must be
examined for the qualities of reality, predominance and efficiency as t he active,
efficient cause that sets a relevant chain of events in action. If one cause would
have caused the harm in any case, and the other would not have done so in the
absence of the first, the first is the proximate cause.
A common sense approach is taken to determine proximate cause.
3.3 Relevant policy extracts
The relevant policy extracts are referred to in the recommendation and the FSP’s
Notice of Response dated 7 February 2018. Both the policy document and the Notice
have been exchanged with the applicant.
3.4 Other relevant material considered and relied on
Parties’ submissions, emails and photographs and all attachments to all
submissions including;
o Assessment reports.
o Expert reports.
o FSP’s claim file notes.
o Scopes of work and quotations.
o Correspondence between the parties.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.