Movement damage claim from broken stormwater pipes declined for faulty workmanship
Text of the determination
Determination | Case number: 513502 Page 1 of 10
Determination
Case number: 510699 23 January 2019
1 Determination overview
1.1 Complaint
The complainants held a home and contents insurance policy with the financial firm
(the insurer).
The complainants lodged a claim for movement damage to their property. The
complainants submit the damage is accidental as it was caused by the builders
cracking two stormwater pipes during the construction of the property.
The insurer declined the claim on the basis the damage was due to faulty
workmanship. The insurer also argued the complainants did not take reasonable
steps to rectify the issues.
The com plainants dispute the insurer‟s decision and want the claim accepted.
1.2 Issues and key findings
Is the insurer entitled to decline the claim?
The insurer is not entitled to decline the claim because:
the damage was caused by leaking pipes
this does not fall within the policy exclusion for faulty workmanship
the insurer has not shown the complainants failed to take reasonable care
the pipes were likely damaged in 2011.
Therefore, the insurer is required to indemnify the claim pursuant to section 2.1.
1.3 Determination
This determination is in favour of the complainants.
The insurer is required to indemnify the complainants pursuant to section 2.1.
Determination | Case number: 513502 Page 2 of 10
2 Reasons for determination
2.1 Is the insurer entitled to decline the claim?
Relevant background
These relevant facts are not in dispute:
on 22 July 2009 the complainants signed a contract with WH to construct a
dwelling
on 15 February 2010, the complainants filed proceedings against WH in the
Queensland Civil and Administrative Tribunal (QCAT) alleging numerous defects
on 12 May 2010, the complainants reached a settlement with WH – this included
an agreement that the complainants would engage another builder to rectify
defects
on 20 May 2010, the complainants moved into the address
on 27 September 2010, the complainants first took out a policy with the insurer
in February 2011, the complainants engaged HCC to complete remediation works
– these included removing defective paths around the perimeter of the building and
constructing new ones
from July 2012, the complainants noticed cracks and doors sticking – this
worsened over the following years
around 2015, the complainants sought to claim for defective works against WH
with the Queensland Building and Construction Commission (QBCC)
after investigating the matter, QBCC did not accept WH was liable
in July 2016, the complainants lodged a claim for this damage with the insurer
When QBCC were investigating the dispute, two leaks were identified. One was
described as a „major underground storm water break‟ adjacent to the rain water tank.
This is on the western side of the property.
The second was under the carport slab on the eastern side of the property.
Policy provides cover for accidental damage subject to exclusions
The complainants are required to show that, on the balance of probabilities, they have
suffered a loss caused by a risk insured against under the policy. This is known as
establishing a prima facie claim.
If the complainants are able to establish a prima facie claim, then the onus shifts to
the insurer to show that, on the balance of probabilities, it is entitled to rely on an
exclusion under the policy or is otherwise entitled to decline the claim.
Determination | Case number: 513502 Page 3 of 10
The complainants‟ policy provides cover for accidental loss or damage to their
property, subject to the conditions and exclusions. The courts have defined
„accidental‟ to mean “unintended and unexpected”.
The complainants submit the damage to the property was caused by the cracking of
the stormwater pipes at the property. The complainants say this is accidental and
should be covered under the policy.
Cause of damage was the two broken pipes
Four engineers have inspected the property to identify the cause of damage. One was
appointed by QBCC (LR), two by the complainants (PW and O) and one by the
insurer (F).
Three of the engineers (LR, PW and O) concluded the main cause of the damage
were the broken pipes. The insurer‟s engineer (F) agreed this was one cause but also
attributed the other primary cause to defective workmanship.
F‟s conclusion about defective workma nship is not persuasive. The defective works F
referred to in his conclusion included the use of non-pressure grade PVC pipes, non-
compliant rubber ring joints and inadequate clearance between pipes, carport slab
and perimeter beam. However, there is no dispute two pipes were cracked and this
caused the damage. F does not explain how these cracks could have been caused by
these workmanship issues.
F also referred to water ponding at the front verandah and contributing to the cause of
damage. PW identified this issue as well. PW did not accept this was the cause. F
says the associated damage from this ponding is due to defective workmanship.
However, it is unclear if this ponding has simply contributed to the substantive
foundation movement caused by the two water leaks.
Given this, the panel is persuaded by the three engineers who all conclude the cause
of the damage were the two broken pipes.
Damage was not caused by faulty workmanship
The insurer has argued the claim falls within a policy exclusion for defective
workmanship. Part of this was based on F‟s report which, for reasons set out above,
the panel is not persuaded by.
The insurer also says that if the breakages were caused by construction works, then
this is faulty workmanship. This is because the damage was due to the contractors
failing to meet their duty of care.
The panel disagrees. Based on the insurer‟s interpretation of faulty workmanship, this
would extend to any damage accidentally caused whilst undertaking construction
works. For instance, whilst constructing a specific area, the contractor unintentionally
caused damage to another area (i.e. a neighbour‟s property).
Determination | Case number: 513502 Page 4 of 10
The panel does not accept a reasonable person in the position of the parties would
interpret the exclusion interpreted so broadly. Instead, such a person would likely
interpret this exclusion to apply to the specific works the contractors were engaged to
do which did not comply with appropriate building practices.
Even if this is incorrect, the panel does not accept a person of average intelligence
and education would readily understand the exclusion to apply in such a manner. For
instance, it is unlikely such a person would readily interpret this exclusion to include
unintended damage to property that was not subject to the works being done by the
contractor.
Alternatively, the panel does not agree it is fair in all the circumstances to interpret the
exclusion so broadly.
Therefore, the panel does not accept the exclusion for faulty workmanship is
engaged.
Insurer has not established the complainants failed to prevent further damage
The insurer says that as the complainants did not take reasonable steps to mitigate
the damage, this is excluded.
This type of provision has been judicially considered. It requires the insurer to show
the following:
the complainants were aware of the risk
the complainants deliberately, or recklessly courted the risk
Whilst the complainants were aware of damage, there is no dispute they did not know
the cause until 2015. Therefore, the panel does not accept they were aware of the
risk until the leaks were identified. By then, damage had occurred and the risk
manifested.
Further, the information shows the complainants attended to repairs to one of the
damaged pipes and attempted to mitigate the second one. This does not show they
deliberately, or recklessly, courted the risk when they became aware of it.
Therefore, the panel is not satisfied the complainants failed to take reasonable steps.
Information shows the damage occurred whilst the insurer was on risk
The insurer has argued the damage occurred before it first came on risk. This position
is mainly based on the fact the complainants have said they noticed damage
occurring when moving into the property.
The complainants submit the damage to the pipes likely occurred when HCC
conducted remediation works given the following:
Determination | Case number: 513502 Page 5 of 10
the carport slab had been installed by HCC – if there was a leak here, it would
have been readily identified
HCC were engaged to remove and replace all the perimeter paths – if there was a
leak on the western side, this would have been identified. Particularly given there
was about 530mm of rain between May 2010 and July 2011
given HCC used a bobcat to do the works, it is highly likely this caused damage to
the pipes
two experts engaged in early 2010 (QBP and SB) did not identify any foundational
movement – however, they did identify the fact the perimeter paths were not
graded away from the property
cracking only started in 2012
The complainants‟ arguments are compelling. Regarding the insurer‟s position, the
panel is not persuaded given the following.
An unsigned statement from the male complainant to QCAT noted the damage
identified was „slightly sticking doors‟. No other information has been provided of the
damage noticed by the complainants prior to 2011 that could be associated with
foundation movement.
For the sticking doors, it is not apparent this was caused by foundation movement or,
if it was, the foundation movement was caused by a leak.
Both QBP and SB reported that a number of bedroom doors were binding and
required easing. Neither indicated this was due to foundation movement.
Even if it is arguable the sticking of doors was due to foundation movement, it is not
clear this was from the leaks. Both QBP and SB identify the perimeter paths do not
provide fall away from the property. This means that rain falling on the perimeter
paths could be going underneath the slab. This could readily explain foundation
movement causing slight sticking of the doors.
Given all this, the panel accepts that on balance, the pipes were damaged by HCC.
This occurred in 2011 when the insurer was on risk
Evidence is not clear that the property is a total loss
After careful consideration of all the available information, the panel is satisfied the
insurer is liable for the foundation damage being claimed by the complainants.
As the panel is satisfied the damage to the pipes likely occurred in early 2011, the
relevant policy period is the first year of insurance.
The complainants say the cost to repair the property would likely exceed the sum
insured at the time ($250,000). They have provided evidence from PW supporting
this.
Determination | Case number: 513502 Page 6 of 10
PW‟s evidence is set out in an email. No scope of works has been included in his
email nor any costing. Further, PW does not confirm what sum insured he is referring
to.
The other engineers appear to accept the damage is repairable. LR recommended a
set of works to remediate the damage. O agreed with LR. F, whilst not following the
same process, agreed the damage was repairable.
Given this, the panel is not persuaded the evidence shows the sum insured is
payable. Therefore, the panel considers it is fair in all the circumstances for the
dispute to be resolved in the following way.
Claim to be resolved in this manner
The parties must work together to determine the likely cost of repairs. This is to be
done through the following process:
engage an independent structural engineer (at the insurer‟s cost) to settle on a full
scope of works
obtain at least one quotation for this scope of works from a contractor prepared to
do the works for the complainants – if more than one quotation is obtained, then
the average of all the quotations is applicable
If the cost of repairs exceeds the sum insured ($250,000), plus the 30% „Home sum
insure d safeguard‟, then the insurer is to cash settle the claim in accordance with the
policy.
The „Home sum insured safeguard‟ applies in the following circumstances:
an insured event causes damage to the property
the property is a total loss
the damage resulted from a catastrophic event or the complainants arrived at the
sum insured using the insurer‟s calculator
The complainants‟ situation satisfies two of the three criteria. Whilst the third is not
engaged, the panel notes the following:
the policy was arranged with the assistance of the insurer‟s representative
the damage has likely exacerbated following the insurer‟s denial of the claim
Given this, the panel considers it is fair in all the circumstances that the safeguard be
applicable when determining the total sum payable for the cost of repairs.
If the cost of repairs is less than the sum insured and the safeguard, then the
complainants can choose whether to have the insurer repair the damage or accept a
cash settlement.
Determination | Case number: 513502 Page 7 of 10
The panel acknowledges the policy gives the insurer the discretion as to how to settle
the claim. However, the panel considers it is fair in all the circumstances the
complainants have the option to choose given:
the insurer had incorrectly denied the claim
it is now more than seven years since the pipes were damaged
even based on F‟s recommendation, the repair process could take years to
complete – this would potentially have the complainants waiting more than ten
years since the pipes broke for the damage to be repaired
it is appropriate for the complainants to have the choice of accepting a cash
settlement if they wish for finality to this ongoing matter
Interest is not payable on any cash settlement sum. This is because if it is based on
the cost of repairs, it will be pursuant to c urrent rates. If it is on the sum insured, the
panel has allowed an extra 30% even though the complainants‟ circumstances do not
technically fit the policy criteria for this benefit.
Determination | Case number: 513502 Page 8 of 10
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
Applicant Complainant
financial services provider financial firm
dispute complaint
claim claim
3.1 Our approach
As advised to the parties, we have considered it appropriate to expedite this
complaint in accordance with the Operational Guidelines to the FOS Terms of
Reference, due to the nature of the complaint. Accordingly, this complaint has not
been the subject of a recommendation and has proceeded directly to determination.
This decision has been made by a panel consisting of an Ombudsman, an individual
with extensive insurance industry experience and an individual with extensive
consumer representative experience.
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered for the purposes of this determination.
This complaint has been decided based on what is fair in all the circumstances after
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues considered
directly relevant to the outcome only.
Determination | Case number: 513502 Page 9 of 10
3.2 Relevant policy wording
Insured events – page 14
If you have selected Insured events cover:
We will indemnify you up to the limit shown in your Policy Schedule or any
applicable sub-limits in respect of physical loss of or damage to your home,
contents, or both, directly caused by any of the Insured events at the site
during the period of insurance.
Your Policy Schedule will show if you have selected Insured events for
your home, contents or both.
Accidental damage – page 14
If you have selected accidental damage cover:
You are insured against accidental loss or damage to your home, contents,
or both at the site during the period of insurance. This includes cover for
any of the Insured events.
Your Policy Schedule will show if you have selected Accidental damage
cover for you home, contents, or both.
Insured events – page 18
You are insured against loss or damage caused at the sire directly by the
following Insured events:
…
8. bursting, leaking, discharging or overflowing of fixed basins, shower
bases, or other fixed apparatus, fixed tanks or fixed pipes used to hold or
carry liquid of any kind.
We will also pay for water suddenly escaping from a waterbed or aquarium.
If we accept a claim because damage has occurred as a direct result of the
liquid escaping, we will also pay the reasonable costs of locating the cause
of the damage, and the costs of reinstating the property damaged or
disturbed in the course of work;
We do not pay for loss or damage:
a. which occurs as a result of your failure to take reasonable steps to
prevent further loss or damage once the event was discovered;
b. for repair or replacement of the apparatus, tank or pipe itself.
Determination | Case number: 513502 Page 10 of 10
…
14. erosion, subsidence, landslide or earth movement, but only if it is
directly as a result of one of the following Insured events:
a. explosion;
b. storm or flood;
c. earthquake or tsunami;
d. escaping liquid;
and it occurs no more than 72 hours after the insured event.
We will not pay for loss or damage caused by any other erosion,
subsidence, landslide or earth movement event.
We will not pay for – page 28
We will not pay for loss or damage:
…
2. resulting from or caused by:
…
c. inherent defects, structural defects, faulty workmanship, faulty design or
any gradual process;
…
f. settling, shrinkage or expansion in buildings, foundations, walls or
pavements;
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.