Determination 509939
Further building and temporary accommodation payments sought after fire
Summary
After a house fire the insurer cash settled $155,000 and paid temporary accommodation, and the complainant sought more for building variations, asbestos and electrical works and extra accommodation. AFCA found no further building or accommodation payment owed but ordered $500 for non-financial loss because the insurer's inadequate initial scope caused delay.
The complainant's evidence did not show extra costs beyond the insurer's allowance, while the insurer's insufficient scope caused an unreasonable delay warranting modest compensation.
Issues
- Claim amount dispute primary · not upheld
“I am not satisfied the complainant has shown any extra work required will exceed the insurer's allowance for possible variations”
- Delay secondary · upheld
“the insurer's failure to fully scope the repairs delayed the assessment of the claim and interfered with the complainant's peace of mind”
Subjects and remedies
home or building damagepay non financial loss
Text of the determination
Determination | Case number: 509939 Page 1 of 8
Determination
Case number: 509939 5 December 2018
1 Determination overview
1.1 Complaint
The complainant lodged a claim for fire damage to his home with the financial firm
(the insurer). The insurer accepted the claim and settled him for $155,000. This
included $17,650.85 for variations. The insurer also paid for temporary
accommodation until 2 December 2017.
The complainant says the variations will exceed the amount allowed. Therefore, he is
seeking an additional amount as well as an extension of his temporary
accommodation.
The insurer says the complainant has not provided evidence to show the additional
variations are either required or exceed the allowance already provided. The insurer
does not agree further temporary accommodation is required.
1.2 Issues and key findings
Should the insurer pay more for the building damage?
The insurer is not required to pay more for the building damage. This is because the
evidence does not show the complainant will require additional work that will exceed
the amount already allowed by the insurer for unseen variations.
Should the insurer pay for more temporary accommodation?
The insurer is not required to pay for more temporary accommodation because the
information shows its allowance of 16 additional weeks above the policy limit was fair.
Should the insurer pay non-financial loss?
The insurer should pay $500 for non- financial loss because the insurer’s failure to
fully scope the repairs delayed the assessment of the claim and interfered with the
complainant’s peace of mind.
1.3 Determination
This determination is substantially in favour of the insurer.
Determination | Case number: 509939 Page 2 of 8
The insurer is required to pay $500 in non-financial loss.
The insurer is not required to take any other action in relation to this complaint.
Determination | Case number: 509939 Page 3 of 8
2 Reasons for determination
2.1 Should the insurer pay more for the building damage?
Insurer has allowed $17,650.85 for unseen variations
These relevant facts are not in dispute:
the complainant lodged a claim on 15 August 2016 for fire damage to his home
the insurer issued a cash settlement of $155,000 less excess on 20 June 2017 for
the building repairs
the insurer agreed to cover temporary accommodation until 2 December 2017 –
this included an additional 16 weeks above the 12 month limit allowable under the
policy
The insurer’s settlement of $155,000 was based on the following:
R’s quotation of $122,077.28
R’s variation of $15,271.87
an allowance of $17,650.85 for unseen variations that may arise during completion
of repairs
The complainant says the cost of the variations will exceed the amount allowed in the
insurer’s offer. However, for reasons to follow, I do not accept the evidence shows
this.
Fireplace
The complainant says this needs to be replaced as the fire originated from here.
In support, he provided a quotation from CL and a report from MA.
MA’s report included a scope of works that MA said should be added to R’s. This
included the replacement of the fireplace and for the flue to be reinstated. However,
when addressing this point, MA’s report simply says:
We also noted the close proximity of the wood heater flue to the timber frame.
Consideration should be given that more clearance be provided
I do not accept this shows R’s quote f or the fireplace is insufficient. There is no
explanation or reasoning provided as to why the fireplace should be replaced based
on this comment alone.
Further, the comment is equivocal. It says “consideration should be given that more
clearance be provid ed”. It does not say that more clearance is required and this
means the fireplace should be replaced.
Determination | Case number: 509939 Page 4 of 8
R’s scope of works is consistent with S’s initial scope of works. Both were based on a
visual inspection. Neither believed that the fireplace needed to be replaced.
Given this, I do not accept the evidence shows the fireplace needs to be replaced or
any variation is required to R’s scope of works on this issue.
Asbestos
The complainant provided a quote from A regarding the extra cost for removing
asbestos. The insurer has questioned whether A attended the site in providing this
quote or solely based it on the complainant’s submissions about what is required.
The complainant did not address this.
I accept there are areas of the home that likely have asbestos and require removal.
Particularly the ceiling linings quoted by R.
However, I do not accept the complainant’s submission that A’s quote represents the
additional cost he will incur. For instance, numerous items being quoted upon were
based on R’s scope of works. In effect, they are duplicating works that have already
been allowed.
This would require those amounts to be credited to A’s quote. If I simply refer to the
specific items referred to in A’s quote that completely replicates R’s quote, there is a
minimum of about $3,150 worth of works that should be credited.
There are also additional items that are not included in either R’s or MA’s scope of
works. They are:
downstairs laundry, hallway and office ceilings
snake room wall
cladding on gables of roof structure
The complainant provided photographs of the snake room wall saying these require
asbestos removal. However, it is not apparent from the photographs this is the case
or why MA did not include it in their scope of works.
Given the limited evidence, I do not accept these items should be added to the scope
of works.
Therefore, when taking into consideration all of the available information, it does not
show the insurer’s allowance for asbestos to be insufficient.
Electrical works and smoke alarms
The complainant has provided evidence to show the electrical supply will need
upgrading to comply with relevant legislations.
The insurer has not disputed these additional works are required.
Determination | Case number: 509939 Page 5 of 8
The complainant has provided a quote from J totalling $5,855. There is nothing to
suggest this is unreasonable.
The complainant also says that the electricity provider (E) will charge around $2,200
for their works. The insurer has not accepted this given it is not a firm quote.
However, the complainant has noted E will not provide a quote until the works are
done.
It is clear that E will be required to undertake works. The estimate provided does not
appear to be unreasonable. Therefore, I will accept on balance the additional
electrical works required will be about $8,055.
I do not accept this includes smoke alarms. The evidence is not clear that the
electrical works cannot proceed unless the complainant installed smoke alarms.
Further, J says these need to be installed to comply with regulations. However, it is
not clear if this need is associated with the works or due to the fact the house was
non-compliant prior to the event.
Stairwell handrails, tile underlay and shower screen
Neither R nor MA say the handrails require replacement due to the fire damage. I do
not accept the insurer is liable for this.
MA has included additional items related to removing and replacing the tiled bedded
floor. MA does not explain why these are needed on top of R’s quote.
The complainant says:
the shower screen needs replacement as it is custom fitted once a bathroom is
sheeted and tiled
the tile underlay obviously needs replacing as you need to remove it before
removing the wall sheets
However, MA does not say this in its report.
Given this, I am not satisfied the evidence shows R’s quote is insufficient on these
items.
Front door
The complainant said water coming through the damaged roof has reached the
ceiling and run down the front door, requiring its replacement.
In support are two photographs. One shows a damaged ceiling with black marks,
possibly mould, and the door with a fair degree of water stains.
This door was not included in MA’s scope.
Determination | Case number: 509939 Page 6 of 8
The insurer says that from the complainant’s photograph, it is not clear if it is the
external or internal side. Having reviewed the limited pho tographs, I agree.
The complainant has not provided photographs to confirm if the damage is the
external or internal side.
After the conciliation, the complainant said he would provide a report from a carpenter
to report on the cause of damage for the door. This was not forthcoming.
Given this, and the fact it is not included in MA’s scope, I am not satisfied the
limitation information shows the front door requires replacement due to this claim.
Insurer not liable to pay any additional sum towards the building damage
Having carefully considered all of the available evidence, I am not satisfied the
complainant has shown any extra work required will exceed the insurer’s allowance
for possible variations.
Therefore, the insurer is not liable to pay any addition sum towards the building
damage.
2.2 Is the complainant entitled to further temporary accommodation?
Complainant is seeking additional temporary accommodation
The policy provides a 12 month limit for temporary accommodation.
The insurer has paid this 12 month benefit as well as an additional 16 weeks. This
additional 16 weeks was in recognition of the insurer’s contribution to the delays.
The complainant is seeking an additional amount. He says it took the insurer about 10
months before it issued a cash settlement. The complainant says this was because
the insurer’s initial estimates were too low. Therefore, the insurer should not be able
to rely on the policy limit.
Insurer’s allowance is fair
Having reviewed the circumstances of the claim, I am satisfied both parties
contributed to the delay.
It is clear the insurer’s scope of works were insufficient. This was reflected by the fact
that it initially offered to cash settle the claim for $97,381.08 on 10 October 2016. This
was increased by more than 50% when a cash payment was made on 20 June 2017.
There is a gap of over 8 months here.
The insurer recognised that it contributed to this delay and allowed an additional 16
weeks. This is close to four months. The insurer says the complainant contributed to
Determination | Case number: 509939 Page 7 of 8
the delay as he said he would get an engineer and then four months later, noted this
was not required.
The complainant says the delay was six weeks from the engineer’s inspection to
completion. He also says that this was not the sole cause of that delay as he was
disputing other items during this time.
I do not accept these arguments assist the complainant.
According to the complainant’s chronology, he informed the insurer on 10 November
2016 that he would be engaging an independent engineer. By 17 March 2017, he
noted the engineer’s report would not assist him.
This is more than four months.
Further, whilst I accept he was disputing other items during this time, it is clear the
insurer was not in a position to progress the claim until the engineer’s report was
received. Given this, and the fact the engagement of the engineer did not advance the
complainant’s position, I do not accept the insurer caused this time delay.
Therefore, I accept the insurer’s allow ance of 16 additional weeks to be fair in all the
circumstances.
2.3 Should the insurer pay non-financial loss?
Insurer to pay $500 for non-financial loss
We may award compensation if the insurer caused the complainant to suffer an
unreasonable degree of physical inconvenience, time taken to resolve a situation,
interference with their peace of mind or loss of enjoyment of an asset.
Compensation is awarded conservatively.
It is clear the insurer’s initial scope of works were insufficient and the delay in
addressing this caused the complainant to suffer an unreasonable degree of delay
and interference with his peace of mind.
The allowance of additional temporary accommodation as part of the insurer’s
settlement would have mitigated this to a degree. However, I accept an amount of
$500 for non-financial loss to be fair in all the circumstances.
This is taking into account the extent of the delay and interference and the fact the
additional temporary accommodation paid reimbursed the complainant’s financial loss
d ue to the insurer’s delay.
Determination | Case number: 509939 Page 8 of 8
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
disputes previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.