Home / Financial Firm (Unknown - Insurer) / Determination 509586

Determination 509586

Home contents claim delay and non-financial loss compensation

FirmFinancial Firm (Unknown - Insurer)
Decided2018-05-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant complained about delay and poor management of her contents claim and sought non-financial loss compensation. AFCA found a short delay in requesting a report but declined to award compensation.

The claim could reasonably be held pending the police report number, and the applicant did not establish that she supplied the information earlier, so the TOR threshold for non-financial loss was not met.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 509586 Determination Page 1 of 4 Case number: 509586 25 May 2018 1 Overview 1.1 Dispute The applicant held a home contents insurance policy (the policy) with the financial services provider (FSP). On 9 November 2017, the applicant lodged a claim seeking cover for loss and damage to the insured contents. The FSP, in its investigation of the claim requested supporting information from the applicant, in particular a police report number. The applicant remains dissatisfied with the FSP’s overall management of her claim as well as the delay in its finalisation. 1.2 Issues and key findings Is the applicant entitled to compensation for non-financial loss? The available information establishes there was a slight delay in the FSP applying for the police report once being provided with the police report number. However, it does not support a decision whereby the FSP should be required to pay the applicant compensation for non-financial loss in line with the FOS Terms of Reference (TOR). Accordingly, the FSP is not obliged to pay the applicant compensation for non- financial loss under the claim. 1.3 Determination This determination is in favour of the FSP. The applicant has not established an entitlement to compensation for non-financial loss arising from the FSP’s management of the claim. Case No: 509586 Determination Page 2 of 4 2 Reasons for determination 2.1 Is the applicant entitled to compensation for non-financial loss? The FSP is not obliged to pay the applicant compensation under the claim I have considered the available information and note the following:  the applicant arranged the policy with the FSP to cover her contents and personal items whilst they were move to and stored at a storage facility  the applicant purchased a new house in or around August/September 2017  a claim was lodged by the applicant seeking cover for the loss of or damage to the insured property (contents and personal items) in November 2017  the applicant says she approached the Police on three separate occasions. However, the Police only issued a police report and associated police report number (PRN) on one of these occasions  there was some confusion regarding the policy and lodgment of the claim which has since been resolved  the FSP requested the applicant for details regarding the PRN in order to obtain a copy of the report which it deems necessary under the claim and in line with the policy wording  the applicant says she provided this information to the FSP in September/August 2017 whilst attending a branch office of the FSP  the FSP denies this and says this information was not made available despite numerous request until 23 January 2018. It was reasonable to place the claim on hold pending receipt of the PRN I acknowledge the applicant’s concerns that the FSP has unreasonably delayed the settlement of her claim. Further, that this delay is the result of the FSP’s mismanagement and poor level of service provided under the claim. I accept the applicant has shown there did occur loss of and damage to her property insured under the policy. It is the circumstances under which this loss and damage o ccurred that is relevant to and determines the FSP’s liability to the applicant under the claim. Considering the circumstances of the loss, I am satisfied it was reasonable for the FSP to request the applicant provide a copy of the relevant PRN. This information is correctly considered relevant to the FSP’s ability to assess its liabi lity under the applicant’s claim . Accordingly, I determine it was reasonable for the FSP to place the applicant’s claim on hold until such time it was provided with the PRN for its consideration. The FSP is not responsible for the extended delay experienced under the claim The applicant claims she provided the FSP with the requested information in August’/September 2017, when she attended a branch office of the FSP. The applicant says she provided the FSP with:  a list of all missing items Case No: 509586 Determination Page 3 of 4  the PRN  inventory of personal items and guarantees  receipts for her rings  photos of the damaged items The FSP maintains it has made investigations into this claim by the applicant however there is no evidence of the above occurring. Rather, the FSP says it had continuously requested the applicant to provide the PRN details from 10 November 2017 till the report was received on 23 January 2018, resulting in the extended delay. I acknowledge the applicant’s position in this regard . However, the applicant has not been successful in establishing to any reasonable degree she did provide the FSP with the requested information as claimed. There is no evidence of the applicant attending the FSP’s branch office to submit the information. There is no record of this in the policy file notes, claim file notes or any evidence from the applicant of the claimed visit to the branch office. I note the applicant says she attended the branch and spoke to FSP representatives there who remembered her previous visit, however, again there is no information to support this claim such as a statement from one of the representatives. Without evidence to the contrary, I am not satisfied the applicant has established she did provide the claim related information to the FSP at any time earlier than 23 January 2018. Therefore, I am not satisfied it would be reasonable to hold the FSP responsible for the approximately two and half month delay. The TOR allow for an award of compensation for non-financial loss up to a maximum award of $3,000. Such an award is subject to consideration as to whether there has occurred an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the a pplicant’s expectation of enjoyment or peace of mind. I note the information shows the FSP, having received the requested details of the PRN, did delay submitting its application for a full copy of the report by around four weeks. I accept this is a less than ideal level of service, however, I am not satisfied this in itself reasonably gives rise to award of compensation for non-financial loss in line with the FOS TOR. Accordingly, having considered all the information, in line with section 9.3 b) (i) of the FOS TOR, I determine the FSP is not required to arrange payment to the applicant by way of compensation for non-financial loss under the claim. 3 Supporting information 3.1 TOR 9.3 9.3 Other compensation ... b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the Financial Services Provider Compensate the Applicant for non-financial loss but only where: Case No: 509586 Determination Page 4 of 4 (i) An unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; or (ii) In the case of a Dispute pertaining to an individual’s privacy rights – injury has occurred to the Applicant’s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. …

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.