Home / Financial Firm (Unknown - Insurer) / Determination 508434

Determination 508434

Building claim settlement amount and handling of leak damage

FirmFinancial Firm (Unknown - Insurer)
Decided2018-08-31
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded$79,013
Non-financial loss$3,000
Amount claimed$103,185
SourceAFCA PDF

Summary

A landlord claimed for a leak-damaged rental building, rental loss and tenant costs. AFCA ordered the insurer to pay repairs at the insured's quote, rental benefit, expert report costs with interest, and $3,000 non-financial loss, but refused tenant, rent-increase and professional time claims.

Where the insurer had a reasonable time to obtain its own scope of works and did not, the insured's quote is accepted, and claim handling delays justify non-financial loss compensation.

Issues

Subjects and remedies

home or building damagepay claimpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 508434 Determination Page 1 of 7 Case number: 508434 24 August 2018 1 Overview 1.1 Dispute The applicant lodged a building claim in 2014 following a leak, which the financial services provider (FSP) now accepts. She also claimed for rental-related costs, reimbursement for her time disputing the decision and compensation for the claim experience. The FSP agrees to consider some rental costs but says repair costs, scope of works and timeframes are not yet certain. It had said it was arranging a further plumbing test to ensure the scope of works is accurate. The applicant argues the FSP had ample time to arrange these. She now wants the FSP to cash settle repairs and tenant relocation costs based on her quote for $86,185. 1.2 Issues and key findings How should the parties finalise the building claim? The FSP is required to pay $68,805 based on the applicant’s quote as it had a reasonable time to obtain its own quote and did not do so. Did the FSP handle the claim reasonably? The FSP is required to compensate the applicant $3,000 for non-financial loss because I am persuaded it did not handle the claim reasonably overall. Is the FSP required to pay the applicant’s other claims? The applicant has established her claim for 16 weeks rental benefit during the combined repair and settling period. The FSP is required to pay the applicant $6,000 for this aspect of the claim. 1.3 Determination This determination is substantially in favour of the applicant. Within seven days of the applicant accepting this determination, the FSP is to pay the applicant the amounts outlined in section 2. Case No: 508434 Determination Page 2 of 7 2 Reasons for determination 2.1 How should the parties finalise the building claim? Building claim no longer in dispute but claim not yet settled The applicant lodged a claim for building damage on 27 June 2014, after a leak from a broken stormwater pipe. The FSP partially declined the claim. In March 2018, while the dispute was before the Service, the FSP accepted the claim in full based on the applicant’s engineering report by RI . As the parties no longer dispute the cause of damage, this determination will not consider this issue. Based on RI’ s advice, the FSP asked the applicant on 21 May 2018, to allow it to complete further plumbing tests. The FSP said these should be carried out to ensure no other leaks were occurring and if so, allow for these within the scope of works. On 12 June 2018, the applicant agreed to allow the tests. The Service invited the FSP to provide the plumbing test instructions, results, scope of works by 30 July 2018 and again by 6 August 2018. It did not do so. However, the FSP emailed correspondence to its loss assessors (CC) on 7 August 2018, requesting they arrange the plumbing tests and obtain a scope of works. Applicant wants FSP to pay her quote On 14 August 2018, the applicant gave the Service a scope of works and repair quote by RV, which the Service forwarded to the FSP. The applicant wants the FSP to settle the claim based on the quote for $86,185, because she says:  she last heard from the FSP on 21 May 2018  the FSP did not follow up the plumbing tests in a reasonable time  she is concerned allowing tests, visits and approvals now will delay claim and dispute settlement by a further two to three months. FSP had sufficient time to obtain its own quotes The FSP is required to pay the applicant $68,805, based on RV’s quote , because it had a reasonable time to obtain its own scope of works and repair quote and did not do so. The balance of $17,380 is for scope of works item two: tenants’ ren tal, storage and protection works, which this decision considers separately in section 2.3. I consider this a fair outcome in all the circumstances, especially given:  the protracted claim and dispute history  the applicant has correctly disputed the partial decline since May 2016. The FSP is also required to:  reimburse the applicant $2,667.50, which she paid for RI’s report Case No: 508434 Determination Page 3 of 7  pay $1,540 for RV’s report (to RV if the applicant has not yet paid, or to the applicant if she provides payment confirmation to the FSP within seven days of the date of this decision). The FSP is to pay interest on the amount of RI’s invoice from that date until the date of settlement, in line with section 57 of the Insurance Contracts Act 1984 (the Act). If the applicant has already paid for RV’s report, interest is also payable on that amount. 2.2 Did the FSP handle the claim reasonably? FOS may award compensation for non-financial loss Under paragraph 9.3 of the Terms of Reference, FOS may consider an award of compensation for non-financial loss. This is only awarded where an applicant has established they experienced an unusual degree time taken to resolve a claim, or extent of stress or inconvenience. The applicant says FSP’s claim decisions and handling caused stress The applicant says the claim handling approach distressed her because she needed to spend extensive time instead:  meeting with various FSP representatives (assessors, engineers)  reading and deciphering reports and conclusions  following up exclusions, assumptions and suppositions  obtaining expert information and advice. She says constant site visits had to be arranged at times to suit multiple parties. She states these took time away from her completing paid contract work and preparing for examinations. The applicant also argues that the FSP’s position , that it was reasonable to maintain its decision by being only able to rely on contemporaneous expert opinion, is inaccurate. She says she provided and maintained consistent arguments which were not considered at the time, even though she had some relevant expertise (a Diploma of Building and Construction). She says the FSP also failed to properly reconsider its decision after she provided an engineer’s (TD’s) report supporting her views. In her view, the FSP’s claim decision and complaint response emails show it aimed to continually limit liability without looking at the claim in detail and on its own merits. FSP said it would consider compensation in claim settlement The FSP argued its claim decision was based on the available expert reports. It asserted there was no reason to fully accept the claim until it received RI’s report. The FSP acknowledged the applicant spent considerable time disputing the claim. It offered to consider recognising her efforts during claim settlement, upon obtaining the scope of works and other documents. Case No: 508434 Determination Page 4 of 7 FSP is required to compensate the applicant $3,000 non-financial loss I accept stabilisation waiting periods and expert site visits are necessary in insurance claims where a building is damaged by ground movement. I also accept the possibility of a second ongoing leak, which RI raised in his report, added to the complexity of this claim, at least from 28 March 2018 onwards. However, in reviewing the timeline, I am persuaded the FSP did not handle the claim reasonably at multiple points. Before its notice of response, the FSP did not internally raise or appropriately respond to an internal dispute resolution complaint. The applicant had to continue disputing HC’s views and the FSP’s decision over a further two years. After the FSP overturned its partial decline, although wanting to ensure all damage is captured in the scope of works is in line with good faith, it then did not finalise the claim acceptance in a reasonable time. I also accept all the above caused the applicant an unusual extent of stress and inconvenience. For all these reasons, the FSP is required to pay the applicant $3,000 in non-financial loss compensation. 2.3 Is the FSP required to pay the applicant’s other claims? Applicant argues she lost opportunity to increase rent The applicant’s building is a rental property. She wants the FSP to compensate her for her lost opportunity to increase the rent. By this, she means the difference between the amount she received in rent and the increased amount of rent she says she would have been able to charge tenants, if the FSP had decided and handled the claim correctly. The FSP refused to accept this claim because it says the policy does not provide such cover. It also argued it was the applicant’s own decision not to increase the rent. I agree the policy does not provide this cover. I also regard the applicant’s cla im in this regard to be subject to too many uncertainties to allow for any meaningful calculation. I am satisfied that the FSP is entitled to deny this aspect of the applicant’s claim. Applicant’s claim for rental benefit is unchallenged The FSP’s policy i ncludes a benefit covering rental payments following an accepted claim if the property is uninhabitable. The full wording is contained in section 3.2. The applicant provided real estate correspondence confirming monthly rental at July 2017 is $1,500. RV estimated repairs will take four weeks. Case No: 508434 Determination Page 5 of 7 In May 2018, the applicant also claimed for a further 12-week period. She based this claim on the FSP’s builders’ (JL’s and AN’s ) quotes respectively, in which they recommended the property is given time to settle during repairs, after re-levelling work finishes. The FSP did not challenge this. The FSP agreed the policy covers rent payments while the property is uninhabitable during repairs. It said it would not consider payment until obtaining a timeframe for the repair period. It noted rental payments are based on the lease agreement amounts rather than market value, but provided no other reasons challenging the applicant’s above claims. I accept the real estate letters establish the rental agreement between the applicant and her tenants at July 2017 was $1,500 monthly, for the purpose of the policy. Given this, the FSP is required to pay the applicant $6,000. This includes one month for repairs and three months for settlement after re-levelling, at $1,500 per month. Tenant relocation is outside of FSP’s control The applicant claimed $17,380 for her tenants’ accommodation, relocation and contents protection costs during repairs. She also claimed $17,000 based on her estimate of the professional costs she would have charged for time she spent disputing the FSP’s decision. The FSP argues these costs are not included in the policy, which I accept. The FSP is not required to pay these claims. Case No: 508434 Determination Page 6 of 7 3 Supporting information 3.1 FOS approach to this dispute This dispute has not been the subject of a FOS recommendation. Due to the nature of the dispute, it has been referred directly for determination, in line with the Operational Guidelines to the FOS Terms of Reference. I have decided this dispute based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. I reviewed and considered all material provided by the parties. While the parties raised numerous issues in their submissions, for the purposes of this determination, I have restricted commentary to those issues I consider directly relevant to the outcome only. 3.2 Policy Additional buildings benefits Landlord Insurance includes a range of additional buildings benefits which are automatically included in your Policy when you obtain buildings cover. The amount we will pay is in addition to the sum insured … If you make a claim for an additional buildings benefit, you will not need to pay an excess. The amounts we will pay and any limits that apply are listed in the table below and are inclusive of GST. Loss of rent Any loss of rent equal to the weekly amount as stated on your Rental Agr eement or Periodic Tenancy Agreement for up to 12 months and a maximum of $52,000 if your buildings or sections of your buildings suffer loss or damage and are uninhabitable as a result. How we settle a loss of rent claim If we decide to pay your loss of rent claim: We will pay you loss of rent equal to the weekly amount as stated on your rental agreement or periodic tenancy agreement for up to 12 months. The most we will pay is $52,000. Glossary Rent The amount of money paid, or payable, by the tenant to rent your rental property. Case No: 508434 Determination Page 7 of 7 3.3 Expert comment Record Key points FSP’s expert (HC ) Structural and civil engineering consultant Report 01 - 09 - 2014  As the foundation material below bedroom 3 is well above average, we would recommend that no repairs be carried out until the moisture content of the foundation material has dried out and stabilised.  This may take a period of approximately 12 m onths from when the broken stormwater drain is repaired. Applicant’s expert (TD ) Civil engineering and construction consultant Report 20 - 12 - 2016  It is our opinion that the broken stormwater pipe has caused excessive wetting of the foundation soils, thus causing set tlement of the strip footings and thereby cracking and movement to the house. Applican t’s expert (RI ) Chartered civil engineer Report 21 - 03 - 2018  Noting that block flood testing has not been done of both stormwat er and sewerage and now that some time has elapsed, it would seem appropriate to ensure that you do not have an ongoing plumbing situation that will make a ny repairs redundant.  The conundrum is that if it was just one leak then it has permeated through the whole of the subfloor int ernally and it is continuing to be drying out and thus dropping the stumps; equally, it is possible that the leak affecting internal has now been terminated but there is an external leak continuing that is maintaining and/or lifting the strip footings around the perimeter.  The full scope of works can be scoped by others far more adept than I, taking int o account [my summary] above. RI Chartered civil engineer Email to FSP 10 - 05 - 2018  You did raise the question about how can we be sure if we found all the leaks, and I indicated that cameras don't do it. The best and only method is to utilise a block flood test of the sewer and/or stormwat er (in this case I would test only the stormwater). If it drops, there is a leak. You then use a camera, find the leak and fix it. The reafter the flood test needs to be re - done again, and if it continues to drop you find the next leak, and continue until it holds water.  I have attached the methodology of testing plumbing that is utilised when we commission plumbers to do investigations .

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.