Home / Financial Firm (Unknown - Insurer) / Determination 508070
Determination 508070
Claim declined for collapse of strata retaining wall
Summary
The strata body corporate claimed for removal of debris after its retaining wall collapsed, and the insurer declined the claim as the damage was expected. AFCA found the body corporate was aware the wall had failed, so the damage was not accidental, and awarded no compensation.
Accidental damage under the policy requires damage not expected, and the complainant had prior knowledge that the wall had failed and would collapse.
Issues
- Claim denial primary · not upheld
“The panel is satisfied that in October 2016 ... the complainant became aware that the wall had failed and required demolition and replacement.”
- Delay secondary · upheld
“Whilst there is evidence of some delay on the part of the insurer, the complainant did not request internal complaint resolution review until almost two months after the insurer issued its decline letter.”
Subjects and remedies
no remedy
Text of the determination
Determination | Case number: 508070 Page 1 of 7
Case number: 508070 26 November 2018
1 Determination overview
1.1 Complaint
The complainant is a representative of the body corporate responsible for the
regulation and maintenance of the block of units and an owner of one of the units
located on the insured property. For clarity, reference to the strata and the
complainant includes all persons representing the relevant body corporate.
On 22 May 2017, the complainant lodged a claim under the strata policy held with the
financial firm (insurer) following the collapse of a retaining wall. The insurer denied the
claim saying damage resulted from policy excluded factors. Namely, long term soil
movement and inadequate construction of the wall.
The complainant disagrees with the insurer ’s decision. In addition, the complainant
says the insurer failed to:
offer a product that aligned to what was requested at policy inception; and
comply with the Code of Conduct during the claim processing and claim complaint
process.
1.2 Issues and key findings
Has the complainant established a valid claim under the policy?
The complainant has not established a valid claim under the policy. This is because:
the complainant was aware in October 2016, the wall required removal and
reinstatement due to its pre-existing defects
the wall’s collapse was inevitable and foreseeable for the purposes of the policy’s
definition of accidental damage.
Is the complainant entitled to an award of compensation?
The complainant is not entitled to compensation in the circumstances of this
complaint.
Determination | Case number: 508070 Page 2 of 7
1.3 Determination
This determination is in favour of the insurer.
The insurer is not required to take any further action.
Determination | Case number: 508070 Page 3 of 7
2 Reasons for determination
2.1 Has the complainant established a valid claim under the policy?
Policy provides cover for accidental damage subject to exclusions
The complainant carries the initial onus to establish any loss or damage arising from
an event is covered by the terms and conditions of the policy. This is kno wn as a valid
claim.
Once established and if the insurer seeks to deny the claim, the onus shifts to it. In
such a case, the insurer bears the onus to establish, on the balance of probabilities, it
is entitled to rely upon a policy exclusion, or otherwise deny the claim.
The complainant ’s policy provides cover for accidental damage to the common
(strata) property. The policy defines accidental damage as something not intended or
expected.
On 28 October 2016, the complainant’s neighbour (JT) emailed the complainant
about the subject wall. JT tendered an engineer’s report (NB) who advised that the
wall had failed and recommended the wall to be demolished and a new wall built
given it has rotated 11 degrees.
On 22 May 2017, the complainant lodged a claim for the removal of debris for a
retaining wall following its collapse.
At the time of collapse, the complainant had development approval for the
construction of a new wall.
The complainant is not claiming for the reinstatement of the wall, only the removal of
debris and the reinstatement of the services such as water mains and electrical
trench.
Retaining wall has been subject to movement in 2016
The complainant tendered the neighbouring engineer’s report dated 18 October 2016.
In his report, NB confirmed the wall has failed. In addressing the cause of failure, NB
says the excessive retaining height and failure in the drainage behind the wall caused
the observed failure.
NB outlined the subject wall’s defects as:
rotation, sliding and cracking especially in the middle section
height of wall extended in the area where retaining is at its highest
white marks on wall indicated drainage measures failed
weep holes are blocked.
Determination | Case number: 508070 Page 4 of 7
In concluding his findings, NB recommended the wall to be demolished and replaced.
The exchanged information shows:
the complainant was aware of the wall ’s identified issues
during the strata regular meetings, the committee were progressively working on
addressing the wall, applying for the development approvals through the local city
council and obtaining relevant quotes.
Complainant has not established a valid claim under the policy
As stated, the complainant has the initial onus to establish a valid claim covered by
the terms of the policy.
The complainant’s obligation is to establish that the damage was accidental, that is,
not intended or expected.
The panel accepts that the damage was not intended.
However, the panel is satisfied that in October 2016, some six months prior to the
damage, the complainant became aware that the wall had failed and required
demolition and replacement.
The exchanged material confirms that on the basis of this information, the
complainant was making arrangements to have the wall demolished and replaced.
Given the complainant was aware the wall had failed, the panel is satisfied that the
complainant was aware the wall would collapse, which it ultimately did.
The result is that the panel is not satisfied that the complainant has met its obligations
to establish that the damage was not expected. The insurer is therefore entitled to
deny the claim.
The complainant says the insurer failed to provide adequate cover
The complainant says the insurer should not be entitled to rely on policy exclusions
because in 2003, prior to policy inception, the insurer was provided with details of the
property. The complainant indicates the insurer was aware of the pre-existing issues,
and as such, failed to provide adequate cover.
Approximately 13 insurance renewals were issued to the complainant since policy
inception.
The insured is required to read the PDS to ensure the purchased policy is adequate
and meets his/her insurance needs. In addition, at each renewal, the insured has an
obligation to review the renewal notice and check if anything has changed and
consider whether the policy remains adequate and/or needs to be modified.
The complainant does not dispute receipt of policy documentation.
Determination | Case number: 508070 Page 5 of 7
In addition, the complainant says the insurer was provided with a recent valuation.
Notably, the purpose of valuation is to ensure the cover in place is sufficient in case of
total loss. The panel does not accept the insurer was required to ensure the
complainant ’s cover is adequate. As discussed above, that is the obligation of the
insured.
Consequently, the panel is satisfied the insurer is entitled to rely on the coverage
detailed within the policy documentation.
2.2 Is the complainant entitled to an award of compensation?
We may award compensation for non-financial loss
Under the Financial Ombudsman Service (FOS) Terms of Reference, we may award
compensation (capped at $3,000) for non-financial loss. We will consider
compensation in situations where:
the insurer erred in processing of the complainant ’s claim
the complainant has (as a result of the error) suffered an unusual degree or extent
of inconvenience.
The complainant is dissatisfied with the insurer ’s claim and complaint handling
The complainant says the insurer contravened the general insurance code of practice
2014 (the Code) because:
It took too long processing the claim
it provided little support and/or response to queries raised.
In addition, the complainant says the insurer failed to query the safety of the
occupants or the well-being of the insured.
The complainant says the insurer ’s conduct was disrespectful, arrogant and lacked
consciousness.
The details of the relevant timeline of events are contained within section 3.2 of this
determination.
Whilst there is evidence of some delay on the part of the insurer, the complainant did
not request internal complaint resolution review until almost two months after the
insurer issued its decline letter.
There is no material to suggest the occupants of the complainant’s property were in
any danger.
Having considered all of the exchanged material, the panel is not satisfied that an
award of compensation is appropriate in the circumstances of this complaint.
Determination | Case number: 508070 Page 6 of 7
3 Supporting information
3.1 The determination is made under FOS Terms of Reference
The Australian Financial Complaints Authority ( AFCA) has commenced managing
com s previously lodged with F inancial O mbudsman S ervice (FOS) .
This determination is made under FOS Terms of Reference but has adopted the
following terminology for consistency with AFCA. In this determination the AFCA
terms have the same meaning as the FOS terms defined in paragraph 20.1 and
Schedule 1, 2 & 3 of the FOS Terms of Reference.
FOS definitions AFCA term
applicant complainant
financial services provider financial firm
dispute complaint
claim claim
3.2 Relevant timeline of events
Based on the available material, the following is a relevant timeline of events:
Date Description
22 May 2017 Complainant lodged the claim.
25 May 2017 Expert report is issued by complainant appointed DB.
31 May 2017 I nsurer issued a claim denial email.
31 May 2017 Complainant challenged the denial notice.
25 August 2017 I nsurer engaged an expert MS to attend the property and issue a
report on the cause of damage.
30 August 2017 Expert report is issued by insurer appointed MS.
17 October 2017 I nsurer issued the official denial letter.
6 December 2017 Complainant requested internal complaint resolution review of claim
Determination | Case number: 508070 Page 7 of 7
Date Description
denial (IDR).
31 December
2017
I nsurer issued the IDR letter.
3.3 Policy Wording
Accidental
means something that is not intended or expected by You and would not be
expected from the standpoint of a reasonable person in Your position.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.