The applicants claimed on their building policy for water damage linked to a neighbour's downpipe. AFCA found the insurer could not decline the claim in full, limited it to front-of-property damage, and ordered cash settlement, expert cost reimbursement and $2,000 for non-financial loss.

The neighbour's downpipe was the proximate cause of the front damage, and the insurer did not establish that the subsidence exclusion applied to that damage.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination Case No: 507709 Determination Page 1 of 10 Case number: 507709 21 August 2018 1 Overview 1.1 Dispute The applicants lodged a claim on 28 July 2017, under their building policy for water damage to their property. The financial service provider (FSP) assessed the claim and said the damage was caused by factors excluded under the policy. 1.2 Issues and key findings Is the FSP entitled to decline the claim? The FSP is not entitled to deny coverage for the property in full because:  on balance, the water from the neighbour’s downpipe was the proxim ate cause of some of the damage  the FSP has not established any policy exclusions apply to that aspect of the claim. However, the FSP is only liable for the front of the property damaged by water from the downpipe. Are the applicants entitled to compensation? The FSP is required to pay the applicants $2,000 compensation due to the stress and inconvenience of the claim. 1.3 Determination This determination is in favour of the applicants. Subject to the applicants accepting this determination, within a further 14 days, the FSP is to:  commission a costed scope of works for the damage to the front of the property and cash settle the applicants for this amount, plus 20% on the amount;  reimburse the applicants for the cost of all expert reports related to the claim;  settle the applicants $2,000 for non-financial loss compensation. Case No: 507709 Determination Page 2 of 10 2 Reasons for determination 2.1 Is the FSP entitled to decline the claim? Applicants required to establish a valid claim It is established insurance law that the applicants carry the initial onus to show that the terms and conditions of the relevant insurance policy cover the loss. This is known as a valid claim. Once the applicants establish a valid claim, the onus then shifts to the FSP to demonstrate the loss is not covered, either by way of one of the policy exclusions or on some other basis. The applicants’ policy is an insured events policy. Therefore, the policy only responds where one or more of the listed events causes the damage, subject to any exclusions. The policy provides cover for loss or damage to buildings from water leaks. However, the FSP says the damage was caused by a combination of tree roots, ground movement and subsidence, which is excluded under the policy and was not the result of any listed event. Parties divided about the cause of damage The policy provides cover for ‘water and oil leaks’ which relates to loss or damage caused by water or oil leaking or escaping from house gutters, drainpipes or pipes. The applicants obtained supporting expert information regarding a stormwater downpipe situated on their neighbour’s adjoining house and provided reports from an engineer (WP), a builder (BC) and a horticultural specialist (GH). The information provided by the applicants’ experts supports the position that damage has been caused by the runoff from the neighbour’s downpipe into the applicants’ property and trees have not contributed to the damage. The FSP obtained information from its engineer, (FM), who concluded the water ingress from the neighbouring property did not cause, nor contribute to the movement of the house. FM acknowledges, however, the downpipe may have contributed to the wall damage. Applica nts’ experts say damage is from the neighbour’s downpipe The parties have provided differing opinions about various possible contributing causes of damage. A summary of the key conclusions from the applicants’ experts are: Engineer WP says:  the front left of the house had been exposed to excessive water ingress, the soil was wet and provided evidence of flowing water;  water has been flowing and pooling under the front half of the lounge room; Case No: 507709 Determination Page 3 of 10  bluestone, subsurface and grout was wet above soil level and if water ingress ceased, footing would be dry;  no evidence of mould, meaning water inflow has been excessive;  concrete stumps supporting flooring has risen one inch above soil level;  halfway down the lounge room floor the footing and subsurface was dry with no evidence of water ingress;  no other properties are affected except that between the applicants’ and neighbour’s property. Builder BC says his observations were similar to FM’s report (the FSP’s engineer), however, the cause of movement is where there is a point of contention. BC does not dispute the floor is out of level, but concludes damage is a result of excess water and states:  tree roots have not been a factor in the movement;  floorboards have peaked recently due to water ingress and added moisture under the house;  subfloor ventilation and root action from trees are not a major contributing factor;  on inspection of the subfloor, water has been pooling in the front half of the lounge room and corridor, however, back half was dry;  bluestone footings were damp, surface was wet and sticky;  the stump has a waterline. FSP says damage is a result of movement and trees When the claim was lodged the FSP engaged assessor (AJ) and FM, to inspect the property and comment on the cause of damage. FM concludes:  the property has poor subfloor ventilation and it is not possible for water to enter the subfloor;  there is settlement from the center of the house towards the front of the house;  movement is a result of long term differential footing movement from a combination of differential changes in moisture of the reactive clay foundation soils;  BC (the applicants’ builder) does not possess the expertise, qualification or experience to offer an opinion;  trees within the zone are susceptible to damage from tree root dryi ng of the foundation soils resulting in settlement of the footings;  damage to the floorboards was observed remote from the subject water leaks (minor);  damage is not consistent with heave, rather settlement as FM took a floor level whereas applicants’ exp erts have not. The initial report by FM requested that a suitably qualified and experienced structural engineer attend immediately to inspect the movement related damage, however, the panel notes the FSP has not provided information to confirm whether the additional inspection, by a structural engineer, took place. Case No: 507709 Determination Page 4 of 10 On balance, part of the damage is linked to the neighbour’s downpipe It is appropriate to first determine the proximate cause of the loss. What is the proximate cause of the loss is a question of fact depending upon the circumstances in each case. It is well established at law that the proximate cause is not necessarily the first or the last or the sole cause of the loss. It is the effective or dominant or operative cause of the loss. If there are several causes operating contemporaneously, then each must be examined for the qualities of predominance and efficiency as the active, efficient cause that sets a relevant train of events in motion. Having reviewed the available evidence, the panel is more persuaded by WP’s, BC ’s and GH’s reports. This is because:  damage is confined and localised in the area of the downpipe, showing water staining, efflorescence and paint blistering on the adjoining wall;  AJ confirmed the left and right-hand side to both terraces did not present as having cracking to the solid brickwork;  GH is a specialist and provides detail about the type of trees and how they impact the soils, while the FSP’s information is a broad example and does not address the applicants’ type of trees;  The FSP has not arranged for experts to physically enter and inspect the subfloor or take soil tests, where the applicants’ experts have physically inspected the subfloor and provided photographs to support their statements;  FM’s report maintains w ater is unable to reach the subfloor, however, photographs show this is not correct  The applicants’ footage showing the downpipe dispersing water, also shows extreme inundation of water ingress (as opposed to FM ’s report which has not provided any footage on how the water reacts when traveling down the pipe)  The applicants’ reports provide a clearer understanding as to why the cracking damage, gaps an d windows’ damage is worse at the front;  The property was built in 1870 and the claim was lodged on 28 July 2017, the FM report is silent on why damage has only occurred recently;  All the reports mention the applicants’ property is in good condition, whereas neighbour’s property is in poor condition with areas of lifted roof sheets;  No evidence to show an additional inspection was completed in 2017, by a structural engineer, as requested by FM. While the panel accepts there has been movement and settlement, for the above reasons the panel is satisfied the proximate cause of damage is the downpipe not being connec ted correctly to the lower roof of the neighbour’s property. As a result, the water travelled down the wall into the subfloor, causing movement. Applicants’ have established a valid claim The panel is satisfied that the magnitude of the localised damage, combined with the available information, confirms there is a causal link between the property damage and the neighbour’s downpipe. Case No: 507709 Determination Page 5 of 10 Although seasonal changes in moisture causing differential soil movement could be considered a cause, the FSP does not address why the cracking damage worsened suddenly in mid-2017. Further, while FM suggests tree roots may have influenced the property, it has not addressed GH’s findings. Given GH’s expertise, the panel is persuaded tree roots did not affect the applicants’ pr operty to the extent suggested by FM. The panel is satisfied the applicants have established the most likely cause of the claimed damage at the front of the property was due to the neighbour’s downpipe allowing water to enter the subfloor area. In addition, the property was built in 1870 and there is no sign of pre-filling cracks or prior damage until after claim lodgement. For the above reasons, the panel is satisfied the applicants have established a valid claim. FSP has not established the application for exclusions The FSP has relied on its policy exclusions for subsidence and movement, which excludes ‘the settling, shrinkage or expansion in buildings or foundations, walls or pavements’ . The FSP has, however, failed to establish, on the balance of probabilities, that the damage would have occurred in the absence of water from the downpipe. FSP only liable for part of the applicants’ claim However, the available evidence suggests that the damage caused by the downpipe is localised at the front of the property and adjoining areas (front living room, floorboards, entry, and upper bedroom above the living room). Although photographs from FM identified light cracking to the rear and the bathroom, there is insufficient information to suggest this damage is related to the downpipe. The applicants say all damage should be covered at the property, as the water ingress has impacted the front footings of the house, resulting in the house falling forward. While the panel notes the applicants require all damage to be repaired, the available expert opinion does not support this view. FM confirmed water ingress issues did not cause, but may have contributed to the floor peaking and in reviewing the photos, damage to the flooring in the living area is next to the affected wall. However, there is limited information establishing how flooring removed from the affected area was impacted by the downpipe leaking. In light of the above, the panel considers it is fair in all the circumstances that the FSP bears the cost of repairs to the front section of the property only. Upon acceptance of this determination by the applicants, the FSP is to commission a costed scope of works for the damage to the front of the property, in accordance with this determination. The FSP is to cash settle the applicants in accordance with the costed scope of works plus 20%. Case No: 507709 Determination Page 6 of 10 In this regard, the panel is of the view that given some of the damage is covered under the policy and some is not, it is fair that the FSP cash settle that component of the damage that is covered under the policy. The FSP is to then add 20% to the costed scope of works, to allow for the transference of risks of repairs to the applicants and the absence of a life time warranty on the work, were the FSP to manage the remediation process, via its nominated builder. The parties are to work together to resolve this matter. 2.2 Are the applicants entitled to compensation? FSP to cover applicants’ expert costs Under paragraph 9.4 of the Terms of Reference, FOS may award the professional costs incurred by the applicants in the course of the dispute. In this case, the panel considers the expert material provided by the applicants was crucial in establishing their case and as such it is satisfied the FSP should contribute to the applicants’ professional costs, provided they can establish proof of payment. The FSP is to reimburse these expenses, up to a maximum of $3,000 per report. The FSP is to pay interest on these amounts, in accordance with section 57 of the Insurance Contracts Act 1984 (the Act), from the date the applicants incurred the costs, until payment is made by the FSP. FOS can award compensation in certain circumstances Under paragraph 9.3(b) of the Terms of Reference, the Financial Ombudsman Service (FOS) may award an amount of compensation (capped at $3,000) for non- financial loss where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or peace of mind by the FSP. However, FOS expects applicants to be moderately robust and bear the usual stress and inconvenience associated with an insurance claim. Applicants are entitled to compensation The FSP’s engineer FM did not conduct any soil testing or enter the subflo or to establish if there was a link between the downpipe and movement in the front area. The applicants have been living in an unsafe environment with two young children since July 2017 and through two years of winter months. There is no dispute that dam age was severe as confirmed by FM’s reports and the applicants were moved out after the event to temporary accommodation for two months. In the panel’s view, this position would have caused unnecessary stress and inconvenience to the applicants. Taking in to account all the circumstances around the applicants’ safety, the panel considers the applicants are entitled to $2,000 in non-financial loss compensation. Case No: 507709 Determination Page 7 of 10 3 Supporting information 3.1 FOS approach to this dispute Due to the nature of the dispute, it has been referred directly to a panel for determination, in line with the Operational Guidelines to the FOS Terms of Reference. The panel consists of an Ombudsman and two representatives with consumer and insurance experience. The panel has decided this dispute based on what is fair in all the circumstances, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions (which are not binding). There has been a full exchange of all material information relied on for the purposes of this determination and each party has had the opportunity to address any issues raised by the other. While the parties have raised numerous issues in their submissions, for the purposes of this determination, the panel has restricted its commentary to those issues that it considers directly relevant to the outcome only. 3.2 Key Reports Record Key points FSP ’s expert ( AJ ) Report 1 - 8 - 17 ‘ A leak detection report and roof report were commissioned, and the leak report found that the damage has not been caused by a leaking water pipe. Our cont ractor found all the wat er pipes to be in good condition and water tight. The commissioned Roof Report found that the neighbour's roof sheets have completely rusted and that several sheets have lifted. Our cont ractor found that the roof to be in very good condition and completely wat ertight. [ . . . ] the resultant damage viewed at the time of appointment, i.e. the cracking, presented as ground movement, but noted that both terraces to both LH, and RHS, did not present as having such profound cracking to the solid brickwork.’ FSP’s expert ( FM ) Report 1 - 9 - 17 ‘ There are a number of trees and vegetation locat ed in relatively close proximity to the subject house. In particular, there are trees (varying in height from between 7m to 9m high approximately) located in the vicinity of the southeast corner of the house (in the neighbouring property). From review of historical photographs [ FM ] understands that these trees were previously 3m to 4m high (approximately) in December 2007, indicating that these trees have grown in the last 9 to 10 years. There are also trees (varying in height from between 3m to 4m high approximately) loc ated in the vicinity of the northeast corner of the house (in the neighbouring property) and a tree (4m high approximately) located in the vicinity of the northwest Case No: 507709 Determination Page 8 of 10 corner of the house (in the neighbouring property). Sub - floor Stamp observed to timber floor joist wit hin the subfloor below the eastern end of the hearth. It is FM's opinion that the water ingress issues at the neighbouring property did not cause, nor contribute to the building movement related damage to the subject house. It is FM's opinion that the buil ding movement relat ed damage has been caused by ongoing long - term differential footing movement resulting from a combination of; differential changes in the moisture contents of the reactive clay foundation soils, and undersized and/or shallow footings . It is FM 's opinion that the subject water ingress issues did not cause, however may have contributed to, the ridge located at some of the adjoining floorboards, as discussed in paragraphs 4.12 and 4.13. Considering this damage was observed at, and remot e fro m, t he subject water leaks it is FM 's opinion that this damage would have occurred irrelevant of the wat er leaks. It is FM's opinion that the ridge locat ed at some of the adjoining floorboards has been caused by an inc reas e in the moisture content of the f loorboards causing them to swell/expand horizontally into the masonry walls at their perimeters and buckle resulting in the observed ridge, due to the factors discussed in paragraph 4.13. It is FM's opinion that the downpipe discharge to the veranda roof, previously located in the vicinity of the southeast corner of the house, may have contributed to on - going long - t erm damp conditions to the wall in this area and corresponding paint blistering, efflorescence and water staining as discussed in paragraphs 4.1 4 and 4.15.’’ FM recommends that a suitably qualified and experienced structural engineer is engaged immediat ely to inspect the building movement related damage at the subject property and to provide advic e on remedial measures. ’ Applicant’s expert (B C ) R eport 3 - 10 - 17 ‘The timber strip floor that has always been there has peaked in a number of areas to the front half of the dwelling. My observations were similar to the Building Report produced by FM and I do not need to note these in my report. However, the cause of this movement is where I have a point of contention with the FM report. Having ca refully read the Report from FM and hav ing conducted a thorough inspection of the dwelling including the sub - floor I am of the opinion that the downpipe that was not connected to the lower roof of the adjacent dwelling contributed heavily to the water saturation of the sub - floor area to the dwe lling. Water has permeated through this wall to the sub - floor. It has also caused dampness to the front wall where efflorescence is noticeable. With reactive soils and constant wetting this has caused clay expansion and the footing to heave which in turn h as caused severe cracking to the walls. The added moisture under the Case No: 507709 Determination Page 9 of 10 house has also caused peaking to the strip flooring. I am a lso of the opinion that poor sub - floor ventilation and root action from the small trunked are not a major contributing factor to the movement that has occurred. I revisited the site on Monday 2 nd October 2017 to inspect under the house. A large section of flooring had been removed. As I suspected, water has been pooling under the house in the front half of the lounge room and corri dor. The bluestone footings were damp, the ground surface was very wet, damp and sticky. On one stump you could see where the water line extended. To confirm my opinion for the cause of the damage I asked the owners to remove a section of flooring in the f ront lounge room so that the sub - floor can be properly assessed and checked for water ponding. ’ Applicant’s expert ( WP ) Report 3 - 10 - 17 ‘ At the time of the inspection, the timber floor adjacent the area of house with serious damage and cracking, had been r emoved to gain access to the substructure footings. This location was in the lounge room gaining access to the front half of the house. On inspection of the footings, it was evident the front left of the house had been exposed to excessive water ingress. T he area was extensively wet, evident of flowing water. ‘ In addition to the above, the water has been flowing and in turn pooling under the house in the front half of the lounge room. The water flow had started at the bluestone footings and at the time of inspection, the bluestone and grout was still wet above the soil level. It would have been expected that this section of footing would be dry if the water ingress had ceased recently. The subsurface and ground surface was very wet and damp. There was no ev idence of mould on the soil of bluestone footing meaning the water inflow had been excessive. The concrete stumps supporting the timber flooring also indicated dampness, rising typically 1 inch above the current soil level. Half way along the lounge room f loor, moving away from Dover Street, the bluestone footing and subsurface soil were in fact dry. There was no evidence of any water ingress in the area. In is important to note that the front of the house is concreted to approximately 1.2m from the house w ith drainage. This area is also covered with a permanent awning protecting the front of the house from any water ingress. All adjoining properties have a similar arrangement. It was noted that next door down pipe has recently been extended (see photos.). P reviously, this down pipe would have drained on to the brick ledge of both their and 34 (D) Street properties at level 1. I believe this would have caused excess water flow between the two properties in turn flowing through bluestone footings. It is my opi nion that damage caused at 34 (D) Street has been caused by water ingress from the adjoining property, causing the footings to movement. Again, it is important to note that Case No: 507709 Determination Page 10 of 10 issue is not evident for any other of the 4 other properties except between ( the ap plicants and neighbours property) where the recently extended down pipe has occurred. ’ FSP ’s expert ( FM ) Report 23 - 11 - 17 ‘ It is [FM]'s opinion that the ridge located at some of the adjoining floorboards has been caused by an increase in the moisture content of the floorboards causing them to swell/expand horizontally into the masonry walls at their perimeters and buckle resulting in the observed ridge. This swelling/ expanding of the timber floorboards is expected to be due to a combination of poor sub floor ventilation, potential water ingress to the subfloor from the downpipe discharge above and potentially inadequate acclimatisation of the timber floorboards. Applicant’s expert ( GH ) Report 19 - 1 - 18 With regards to the species of trees and plants in yo ur garden beds at the front of your property I provide the following; Ligustrum Japonicum: Small growing tree to 4 metres wit h a predominantly fibrous root system emanating from a shallow tap root (dicot). The root system would be fibrously matted to appro ximately 35cm deep to 2 metres diameter. It is highly unlikely to have the capacity to cause any structural damage to paving, brickwork or foundations. It is sited over 5m from the house. Wisteria Sinensis x (2) - Each plant is approximately 1.5meteres high by 2 met res wide. The above ground growth is a good indication of the extent of root growth. It is unlikely that the roots have extended far beyond the upper footprint of the plant which is approximately 2 metres away from the hous e. The calliper of the w isteria is about 40mm meaning the plants of a relatively young age without extensive roots. Trachelospermum jasminoides: Height, growth and insubstantial root system incapable of causing damage. Daphne Odora: Height, growth and insubstantial root system in capable of causing damage. Liriope Muscari: Height, growth and insubstantial root system incapable of causing damage. ’