Cash settlement amount for storm damage to home building; cracking damage and rebuild or total loss claims
Text of the determination
Determination
Case No: 506260 Determination Page 1 of 8
Case number: 506260 6 September 2018
1 Overview
1.1 Dispute
The applicant lodged a claim under her home insurance policy with the financial
services provider (FSP) after her home was damaged by a storm in November 2016.
The FSP accepted the applicant’s claim and sought to arrange for the repair of her
property. However, after the parties were unable to agree on the scope of works for
the repairs, the FSP decided to cash settle the claim.
The FSP cash settled the building claim for $135,583.29, being the estimated cost of
repairing the damage to the property, based on a scope of works and quotation
prepared by its contractors.
The applicant says the cash settlement paid by the FSP is not sufficient to address
all of the damage to her home caused by the storm. She says the FSP should be
required to pay her the cost of demolishing and rebuilding the home (estimated at
$250,000) or the total amount of the building sum insured ($390,600).
1.2 Issues and key findings
Should the settlement amount for building repairs be increased?
The scope of works approved by the FSP provides an accurate assessment of the
works required to repair the damage caused by the storm . However, the cash
settlement amount should be increased by $12,084.33 to allow for additional risks,
including unforeseen variations to the scope of works.
The FSP is not required to pay the applicant the cost of demolishing and rebuilding
her home (or the full amount of the building sum insured) as her home is capable of
being repaired for a lesser amount.
1.3 Determination
This determination is partially in favour of the applicant.
The FSP is required to pay the applicant an additional amount of $12,084.33 in full
and final settlement of her claim. The FSP is not required to pay interest on this
amount.
Case No: 506260 Determination Page 2 of 8
2 Reasons for determination
2.1 Should the cash settlement for building repairs be increased?
FSP accepted claim for storm damage
The applicant’s policy provides cover for damage to her property caused by the
events listed in the policy (including storm), subject to the conditions and exclusions
set out in the policy.
The FSP accepts that the applicant’s property was damaged by a severe storm in
November 2016. During the storm, a large section of the roof detached, allowing
water to enter the property and causing some of the ceilings to collapse.
The FSP cash settled the applicant for damage to her contents items, paid her
temporary accommodation costs and reimbursed her for certain meal expenses. The
applicant has not disputed the FSP’s settlement of these aspects of her claim.
However, the applicant is dissatisfied with the cash settlement amount of
$135,583.29 paid by the FSP for the damage to the building caused by the storm.
Policy sets out how claims will be settled
Under the terms of the applicant’s policy, the FSP may settle a claim for damage to
her property by:
repairing or rebuilding the damaged part of the property, or
paying the applicant the cost of repairing or rebuilding the damaged part of the
property.
It is clear from the terms of the policy that the FSP has the discretion to decide which
settlement method to adopt. However, FOS expects an insurer to act reasonably in
exercising its discretion.
The applicant’s policy schedule reflects that she had selected the ‘replacement
benefit’ available under the policy. In these circumstances, the FSP is required to
repair or rebuild the damaged part of the property to the condition it was in when new
(but not better).
The policy states that, where the property is a total loss (that is, it is uneconomical to
repair or rebuild), the FSP will pay the applicant the full amount of the building sum
insured.
Cash settlement was based on quotations obtained
During the claim process, the FSP’s eng ineer (IE) prepared a detailed scope of
works for the repair of the damage to the property caused by the storm.
The FSP obtained a quotation from its builder (AA) for $111,329.68 to undertake the
repairs set out in IE’ s scope of works. A second quotation for $97,454.27 was
provided by the builder (BB) who completed the initial inspection.
Case No: 506260 Determination Page 3 of 8
The FSP authorised AA to undertake the repairs in February 2017. However, the
applicant was concerned that the scope of works did not address all of the damage to
the property caused by the storm. Accordingly, the repairs did not proceed.
The scope of works was expanded to include additional items, including the
replacement of the roof trusses. As a resul t, AA’s quotation for the building repairs
was increased to $120,843.29.
The applicant remained dissatisfied with the scope of works and sought payment of
the total amount of the building sum insured ($390,600) or the cost of demolishing
and rebuilding the home (estimated at $250,000).
When the parties were unable to agree on the scope of works, the FSP cash settled
the claim for a total amount of $135,583.299 in November 2017.
This amount reflected AA’s quotation for the building repairs ($120,843.29), pl us
quotations provided by the applicant for replacement of the pool liner ($13,860) and
repairs to the fence.
Applicant says cash settlement amount is insufficient
The applicant says the cash settlement amount for the building repairs is not
sufficient to repair all of the damage to her property caused by the storm in
November 2016.
In particular, the applicant says the settlement amount does not provide for the repair
of cracking and movement damage to her property, which she considers was caused
by the foundations being exposed to water during the storm.
The applicant also says the property has sustained further damage as a result of
being exposed to the elements in the months following the storm. The applicant says
there is additional water damage and mould growth throughout the property.
FSP is not liable for cracking and movement damage
The reports provided by the various contractors who inspected the property confirm
there is cracking damage in several areas.
In particular, there are cracks in the walls at the south-eastern corner of the lounge.
There are also cracks in the external block walls of Bedroom 1 and the en suite
bathroom, as well as cracks to the concrete and tiled floors in these areas.
The detailed scope of works prepared by the FSP’ s engineer (IE) for the repair of the
damage caused by the storm did not include the cracking damage to the external
walls and the floors.
When the applicant raised concerns that this damage had been excluded from scope
of works, IE explained that this damage had not been caused by the storm.
The section of the property comprising Bedroom 1 and the en suite bathroom (where
cracking damage was observed) was originally constructed as an open carport.
Case No: 506260 Determination Page 4 of 8
The carport was later enclosed (by a previous owner of the property) and then
converted into a bedroom by the applicant’s partner. As part of these works, tiles
were laid in the en suite bathroom over the existing concrete floor.
The available information indicates that the foundations for this section of the building
were designed for an open carport and therefore did not provide adequate support
once the carport was fully enclosed (leading to the cracking damage observed).
The engineer (TC) appointed by the applicant considered it likely that the slab and
footings of the carport did not comply with relevant standards for residential footings.
TC concluded that the cracking to the south eastern corner of the dwelling (including
the lounge room) had been caused by minor differential movement of the
foundations, as would be expected in ordinary course. TC noted that the foundation
soil in this area of the property had not experienced significant saturation.
The applicant provided a report from her builder (HH) dated June 2017, which
advised that further cracking had occurred following the storm, as a result of moisture
penetration to the footings.
However, the information provided by the FSP’s assessor (CC) indicates that the
cracking damage had not worsened since the storm. CC attended the property and
took photographs of the damage in November 2016 and again in August 2017.
Based on the available information, I am satisfied that the cracking and movement
damage to the applicant’s property was not caused by the storm in November 2016.
The nature and extent of the damage is not consistent with it having been caused by
rainwater entering the foundations (as suggested by the applicant), noting the
absence of any information to suggest that water ponded around the footings during
or after the storm.
The applicant says the cash settlement amount should be increased to reflect
quotations (totalling approximately $58,000) provided by the FSP’s builder (BB) for
additional works to the foundations and external walls in the area of Bedroom 1 and
the en suite bathroom.
However, I am satisfied that the FSP arranged for BB to provide these quotations to
the applicant on the basis that the works would be undertaken at her own expense,
(as the relevant damage had not been caused by the s torm).
For the reasons outlined above, the FSP is not liable for the cracking and movement
damage to the property. Accordingly, the FSP is not required to increase the cash
settlement amount to reflect the costs of the additional works quoted by BB.
FSP’ s scope of works for building repairs is generally appropriate
As outlined above, the cash settlement amount for the building repairs was based on
a scope of works prepared by the FSP’s engineer (IE) (updated to include the roof
trusses).
Having carefully reviewed IE’s report and scope of works, I am satisfied that these
documents generally provide an accurate assessment of the damage to the property
Case No: 506260 Determination Page 5 of 8
caused by the storm and a detailed breakdown of the works required to repair the
damage.
The repairs included in IE ’s scope of works are generally consistent with the claim -
related damage as identified in the reports prepared, and the photographs taken by,
the FSP’s contractors following their initial assessments of the property.
In his report prepared in June 2017, the applicant’s builder (HH) advised that the
condition of the property had deteriorated further in the months following the storm.
HH advised that moisture and mould growth had spread throughout the property,
compromising the electrical wiring, timber framework and flooring.
Following receipt of HH’s report, the FSP arranged for its assessor (CC) to reinspect
the property in August 2017. CC confirmed that there was mould affecting the
gyprock wall in Bedroom 1 (due to the temporary tarpaulin having become loose).
However, CC advised that the remainder of the property remained dry and
unaffected by mould, and there were no other signs that the damage had worsened.
CC’s report includes photographs of the property taken during his initial and
subsequent inspection.
Based on the information provided, I am satisfied that the condition of the property
did not deteriorate significantly in the period between the date of the storm and the
offer of the cash settlement amount.
On this basis, I am satisfied that the scope of works prepared by IE remains
adequate. I note that the scope of works included the repair of minor damage to the
wall in Bedroom 1, which is the area in which mould growth was identified in the
months following the storm.
Cash settlement amount should be increased to better reflect cost of repairs
As outlined above, the final cash settlement amount paid by the FSP was based on a
quotation for $120,843.29 provided by AA for the repairs set out in IE’s scope of
works.
Based on the available information, I am satisfied that AA’s quotation represents a
reasonable basis for determining the cash settlement amount. The FSP was willing to
authorise AA to carry out the repairs on that basis.
However, I consider the cash settlement amount should be increased by an
additional 10% ($12,084.33) in order to make an appropriate allowance for the
additional risks borne by the applicant as a result of her building claim being cash
settled.
Such risks include:
any variations to the scope of works which may be required during the course of
the repairs (given such variations are not uncommon where the repairs are
extensive and the FSP would have been liable for any resulting increase in
costs, if the repairs had been carried out by its builder), and
the additional risks assumed by the applicant due to the absence of the lifetime
guarantee.
Case No: 506260 Determination Page 6 of 8
Accordingly, the FSP is required to pay the applicant an additional amount of
($12,084.33) in full and final settlement of her claim. The FSP is not required to pay
interest on this amount.
FSP is not required to pay cost of demolishing and rebuild property
The applicant says the FSP should be required to pay the cost of demolishing the
property and rebuilding it so that it complies with current building standards.
The property has been the subject of a number of extensions and renovations over
its lifetime. Further renovations were being carried out by the applicant’s partner at
the time the storm occurred.
The FSP’s builder (BB) and engineer (IE) advised tha t many of the works carried out
at the property did not comply with applicable standards and may have been
completed without the necessary approvals.
The applicant’s builder (HH) has advised that it is pointless to attempt to repair the
existing building because so many of the previous renovations are non-compliant.
As the applicant has replacement cover, the cash settlement amount should reflect
the cost of rebuilding the damaged part of the property to the condition as close as
possible to when it was new (but not better).
However, this does not mean that the FSP is required to pay the cost of building a
new property in circumstances where the property is capable of being repaired to a
condition equivalent to that when it was new.
Further, the policy clearly states that the FSP is not liable for any costs required to
ensure that the building complies with relevant standards in circumstances where it
was non-compliant at the time the event giving rise to the claim occurred.
The available information estab lishes that the storm damage to the applicant’s
property can be repaired for an amount which is less than the estimated cost of
demolishing and rebuilding the property. Accordingly, the FSP is entitled to settle the
claim for the reasonable cost of repairs.
FSP is not required to pay full amount of building sum insured
During the course of this dispute, the applicant’ s solicitor submitted that the FSP
should be required to settle her for the full amount of the buildi ng sum insured
($390,600) on the basis that her home was a ‘total loss’.
For the purposes of the policy, the applicant’s home is defined to be a ‘total loss’
where it is uneconomical to repair or rebuild.
As outlined above, the applicant’s home can be repaired for an amount which is less
than the building sum insured. In these circumstances, the FSP is not required to pay
the applicant the full amount of the building sum insured.
Case No: 506260 Determination Page 7 of 8
3 Supporting information
3.1 FOS approach to this dispute
This dispute has not been the subject of a Financial Ombudsman Service (FOS)
recommendation. Due to the nature of the dispute, it has been referred directly for
determination, in line with the Operational Guidelines to the FOS Terms of
Reference.
This dispute has been determined based on what is fair in all the circumstances,
having regard to the relevant law, good industry practice, codes of practice and
previous FOS decisions (which are not binding).
There has been a full exchange of all material information relied on for the purposes
of this determination and each party has had the opportunity to address any issues
raised by the other. All of the material provided by the parties has been reviewed and
considered.
While the parties have raised numerous issues in their submissions, for the purposes
of this determination, commentary has been restricted to those issues which are
considered directly relevant to the outcome only.
3.2 Terms of policy
Subject Terms
Settlement of
building claims
How we settle a buildings claim
We will decide how we will settle your claim
If your buildings suffer loss or damage , we will decide whether to:
repair
rebuild, or
pay you the cost to repair or rebuild that part of your buildings that suffered
loss or damage.
If we do, we will:
pay you up to the buildings sum insured, as listed on your schedule
only repair, rebuild or pay you for the part or parts of the building that actually
sustained loss or damage ….
try to match any material used to repair your buildings with the original
materials or nearest equivalent available to the original materials …
If we decide to repair or rebuild your buildings and your current schedule shows
‘including replacement benefit’
We will repair or rebuild the part of your b uildings that suffered the loss or
damage to a condition as close as possible to when new, but not better.
If we rebuild your buildings, we will also pay the amounts that you need to pay to
ensure your buildings comply with government legislation and loc al authority
bylaws, unless:
you were required to pay these amounts before the loss or damage occurred,
and you did not do so …
Case No: 506260 Determination Page 8 of 8
Subject Terms
Total loss
settlement
If your building is a total loss
We will pay the sum insured for your buildings, as listed on your schedule, after
deducting
any excess
any unpaid premium ….
Total loss when we decide that it is uneconomical to repair or rebuild your
buildings or cont ents.