Home / Financial Firm (Unknown - Credit) / Determination 504753

Determination 504753

Hardship assistance, early super release and default notices on home loan

FirmFinancial Firm (Unknown - Credit)
Decided2018-03-27
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The applicant, in financial hardship on a home loan, complained about the FSP's assistance, super release refusal and default interest. AFCA found the FSP largely met its obligations but issued default notices during hardship assessment, ordering $500 non-financial loss, a refund of notice costs and a time-limited sale period.

A lender must cease collection and recovery action while a hardship assessment is in progress, but otherwise met its hardship obligations and was entitled to default interest.

Issues

Subjects and remedies

financial hardshiploan or hardship variationpay non financial lossrefund fees or charges

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 504753 Determination Page 1 of 5 Case number: 504753 27 January 2018 1 Overview 1.1 Dispute The dispute is about the financial difficulty the applicant is experiencing in making repayments to his home loan with the FSP. The applicant says the FSP:  did not assist him with his financial difficulty  should have assisted him with early release of his superannuation and  should not have charged default interest. 1.2 Issues and key findings Did the FSP meet its financial difficulty obligations? The FSP largely met its financial difficulty obligations. The FSP provided appropriate assistance to the applicant, including a moratorium on repayments, flexible short term arrangements that assisted in light of his self-employment and extensions of time for payment. The FSP reasonably declined assistance when the applicant failed to provide information. It was appropriate for the FSP to decline the applicant ’s request for it to support the early release of his superannuation. However, the FSP sent a default notice two days after the applicant had requested assistance, which was inconsistent with its hardship obligations. The FSP should apply $500 in non-financial loss compensation for the stress and anxiety this default notice may have caused the applicant. Was the FSP entitled to charge default interest? The FSP was entitled to charge default interest as the account was in default at the time. The contract allowed the charging of default interest in these circumstances. Should I exercise my power to vary the credit contract? It is not appropriate to vary the loan contract because the applicant cannot establis h he can afford to maintain repayments even if the contracts are varied. 1.3 Determination The determination is mostly in favour of the FSP. Case No: 504753 Determination Page 2 of 5 The applicant is in financial difficulty and the sale of the security property appears to be his only option for repayment of the home loan. There fore, if the applicant accepts this determination, then the following should occur:  The FSP must within seven days: o Apply $500 non-financial loss compensation to the loan. o Refund any costs associated with the issuing of the default notice in November 2017.  Allow the applicant three months, from the date of his acceptance, to provide an unconditional contract of sale for the security property with a settlement period of not more than 60 days. The FSP must forbear taking enforcement action during these periods.  If the home loan is not repaid in full following the sale of the security property, then the FSP must genuinely consider if any repayment arrangement is appropriate for the applicant to repay the shortfall debt before it commences recovery action.  If a repayment arrangement cannot be mutually agreed to by the parties, then the FSP is entitled to resume recovery action for the shortfall debt.  If the applicant fails to sell or settle the security property within the allowed timeframes, then the FSP must provide a notice in writing to the applicant to remedy the breach within seven days. If the breach is not remedied within seven days from the date of the notice, then the FSP is entitled to resume recovery action. 2 Reasons for Determination 2.1 Did the FSP meet its financial difficulty obligations to the applicant? The FSP has obligations to customers experiencing difficulty The FSP has obligations under the National Credit Code and Code of Banking Practice to work with customers experiencing financial difficulty and to try to assist them. A customer should also be willing to work with their financial services provider by engaging in the hardship assessment process. This includes responding to reasonable requests for information and proposing a realistic repayment plan that will result in the repayment of the debt within a reasonable timeframe. Other loans with the FSP that will not be considered in this dispute The applicant says that his financial difficulty began after he took out a loan with the FSP for a second property, which he claims he could not afford at the time. Issues relating to that loan, including responsible lending and whether the FSP had met its financial difficulty obligations, were resolved at a preliminary view. Accordingly, those issues will not be considered in this dispute. The applicant also had two personal loans with the FSP at the time of his financial difficulty. These loans were assigned to a third party in 2016. As the third party is not Case No: 504753 Determination Page 3 of 5 a member of FOS, under our Terms of Reference these loans cannot be considered in this determination. The FSP largely met its financial difficulty obligations The available information shows that the FSP largely met its hardship obligations to the applicant because it:  requested information from the applicant in order to assess his hardship request on several occasions  provided a six month moratorium on repayments and capitalised the arrears to enable the applicant to seek employment and improve his situation  appropriately declined assistance to the applicant when information was not provided and communicated its decision to decline assistance in writing  a ppropriately declined the applicant’s request for early release of superannuation as he could not show serviceability to the loan  when the applicant was self-employed, provided flexible short term arrangements to give the applicant time for funds to come in. Based on the above, the FSP largely met its financial difficulty obligations in trying to assist the applicant. The FSP was not obliged to support the early release of his superannuation The applicant called the FSP on 31 October 2017. He said he had been unable to work since March 2017 due an assault that had blinded him in one eye. He said he was pursuing victims of crime compensation, but the process could take up to 12 months and the outcome was uncertain. The applicant said he was unable to receive any government benefits and requested that the FSP support an early release of his superannuation to assist him. A request for an early superannuation release is in substance a request for financial difficulty assistance. A lender should give genuine consideration to such requests in the context of all available options of assistance . Supporting a release of superannuation is an option of last resort – in many cases there are more appropriate options available. The contact notes show that the FSP told the applicant it would not be supporting an early release of superannuation as the applicant could not show he could service the loan. The FSP told the applicant his request would be reconsidered if he obtained employment and asked the applicant to complete a Statement of Financial Position. It was appropriate for the FSP to decline the applicant’s request for early release of superannuation, as the information the applicant provided to the FSP showed he would be unable to maintain the loan repayments in the future. In these circumstances, an early release of superannuation would likely provide a temporary rather than long- term solution to the applicant’ s difficulties, and could potentially result in him losing both his property and superannuation funds. Case No: 504753 Determination Page 4 of 5 The FSP inappropriately served a default notice The applicant requested hardship assistance on 31 October 2017. In reply, the FSP asked him to provide a Statement of Financial Position. The FSP proceeded to personally serve a default notice on the applicant on 1 November 2017. The FSP also posted a default notice to the applicant on 2 November 2017. The FSP did not perform an appropriate hardship assessment before issuing the default notices. Issuing default notices in these circumstances is inconsistent with a bank’s hardship obligations. This is because a lender should cease collections and recovery action while a hardship assessment process in taking place. The FSP should apply $500 in non-financial loss compensation to the applicant for the stress and anxiety these default notices may have caused the applicant. The FSP should also refund any costs incurred in relation to the issuing of the default notices. 2.2 Was the FSP entitled to charge default interest? The terms and conditions of the contract allow the FSP to charge default interest on the overdue amount when the loan is in default. The account was in arrears at the time default interest was charged. There was also no arrangement in place that was being met by the applicant at the time the interest was charged. In these circumstances, the FSP was entitled the charge default interest. 2.3 Is it appropriate to vary the loan contract? It is not appropriate to vary the loan contract I would only vary a credit contract where I am satisfied that the applicant may be able to meet the terms of the variation and where it is reasonable to do so in all the circumstances. Where it is apparent that a borrower will not be able to afford the loan over the long - term, the sale of the security property may be the only viable option. As of 24 January 2018, the loan is $52,000 in arrears. The minimum monthly repayments to the loan are $2,245 and the last repayment made to the loan was in April 2017. The available information shows the applicant:  has been in financial difficulty since 2013  is currently unemployed and says he is unable to receive any government benefits  is awaiting a victims of crime compensation payout, but the duration and outcome of this is uncertain  has no capacity to make even reduced repayments to the loan  has not provided any information to suggest his situation will improve On the available information, I would not vary the credit contract because the applicant cannot establish that he can afford to maintain repayments, even if the contracts are varied. I would not require the FSP to support an early release of superannuation as this would be likely to provide a temporary rather than long-term, solution to the applicant’s difficulties. Case No: 504753 Determination Page 5 of 5 The applicant should be given a chance to sell the property The applicant is in financial difficulty and the sale of the security property appears to be his only option for repayment of the home loan. Therefore, if the applicant accepts this determination, then the following should occur: The FSP must within seven days:  Allow the applicant three months, from the date of his acceptance, to provide an unconditional contract of sale for the security property with a settlement period of not more than 60 days  Forbear taking enforcement action during this three month period.  If the home loan is not repaid in full following the sale of the security property, then the FSP must genuinely consider if any repayment arrangement is appropriate for the applicant to repay the shortfall debt before it commences recovery action.  If a repayment arrangement cannot be mutually agreed to by the parties, then the FSP is entitled to resume recovery action for any shortfall debt.  If the applicant fails to meet any of these terms, then the FSP must provide a notice in writing to the applicant to remedy the breach within seven days. If the breach is not remedied within seven days from the date of the notice, then the FSP is entitled to resume recovery action. 3 Supporting information 3.1 Decision basis and process This disputes has been the subject of a preliminary view mostly in favour of the applicant. The matter progressed to a determination as the applicant did not respond to the preliminary view. I have considered all the material submitted by the applicant and the FSP in order to reach my decision. I am satisfied that the material I relied upon in reaching my findings has been exchanged between them. I am required to do what is fair in all the circumstances, having regard to legal principles, applicable industry codes or guidance as to practice, good industry practice and previous relevant decisions of FOS and its predecessors.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.